Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Project | Original Estimated Total Cost (millions) |
Revised Estimated Total Cost (millions) |
Actual Cost Total (millions) |
2010-11 (millions) | Expected date of close-out |
|||
---|---|---|---|---|---|---|---|---|
Main Estimates |
Planned Spending |
Total Authorities |
Actual | |||||
Community, Contract and Aboriginal Policing | ||||||||
Radio Modernization – Newfoundland | 25.4 | 23.9 | 17.3 | 1.5 | 1.5 | 1.5 | 1.5 | FY 2012-13 |
Emergency Response Team Level I Tactical Armoured Vehicle (Pre-PPA) | 13.6 | 13.6 | 3.1 | 3.1 | 3.1 | 3.1 | 3.1 | FY 2011-12 |
West Coast Marine Patrol Vessels (EPA) | 48.9 | 31.0 | 0.0 | 16.9 | 16.9 | 16.9 | 0.0 | FY 2014-15 |
National Police Services | ||||||||
Real Time Identification (RTID) | 124.0 | 146.8 | 117.8 | 17.9 | 17.9 | 17.9 | 10.9 | FY 2012-13 |
Temporary Residents Biometrics Project | 22.9 | 30.4 | 3.2 | 1.9 | 1.9 | 1.9 | 1.5 | FY 2012-13 |
Internal Services | ||||||||
Alberta – Detachment – Grande Cache (PPA) | 7.1 | 5.7 | 0.5 | 0.6 | 0.6 | 0.6 | 0.5 | FY 2016-17 |
Alberta – Detachment – High Level (PPA) | 11.7 | 11.4 | 0.9 | 1.0 | 1.0 | 1.0 | 0.5 | FY 2014-15 |
British Columbia – Division Headquarters (P3) (EPA) | 38.8 | 38.8 | 7.8 | 2.5 | 2.5 | 2.5 | 1.6 | FY 2013-14 |
British Columbia – Detachment – 100 Mile House (PPA) | 10.9 | 8.1 | 0.8 | 0.5 | 0.5 | 0.5 | 0.4 | FY 2013-14 |
British Columbia – Detachment – Golden (EPA) | 12.1 | 8.4 | 0.6 | 0.1 | 0.1 | 0.1 | 0.0 | FY 2012-13 |
National Criminal Justice Index (NCJI)/ N-III Project | 23.7 | 18.5 | 18.5 | 0.5 | 0.5 | 0.5 | 0.5 | FY 2010-11 |
Newfoundland – Detachment – Springdale (EPA) | 7.6 | 6.0 | 5.3 | 4.0 | 4.0 | 4.0 | 2.2 | FY 2011-12 |
North West Territories – Detachment – Inuvik (PPA) | 16.0 | 20.6 | 0.1 | 0.0 | 0.0 | 0.0 | 0.0 | FY 2014-15 |
Nova Scotia – Headquarters Replacement (EPA) |
24.5 | 4.0 | 2.0 | 0.4 | 0.4 | 0.4 | 0.4 | FY 2013-14 |
Nova Scotia – Detachment – Ingonish (PPA) | 7.4 | 5.8 | 0.4 | 0.0 | 0.0 | 0.0 | 0.0 | Future Years |
Nunavut – Headquarters Phase I (EPA) | 23.8 | 24.3 | 24.3 | 0.1 | 0.1 | 0.1 | 0.1 | FY 2009-10 |
Ontario – Ottawa – L.H. Nicholson Headquarters Replacement (73 Leikin) (EPA) |
44.5 | 44.5 | 35.7 | 7.4 | 7.4 | 7.4 | 9.5 | FY 2012-13 |
Ontario – Ottawa – Connaught TWTS – New Administration Building (EPA) | 6.7 | 6.7 | 6.7 | 0.3 | 0.3 | 0.3 | 0.3 | FY 2010-11 |
Ontario – Ottawa – TPOF – Armoury Expansion (PPA) | 4.7 | 5.4 | 0.0 | 0.6 | 0.6 | 0.6 | 0.0 | FY 2012-13 |
Saskatchewan – Regina, Depot – Electrical Distribution Network Replacement (EPA) | 24.4 | 21.6 | 19.2 | 12.5 | 12.5 | 15.0 | 14.7 | FY 2011-12 |
Saskatchewan – Regina, Depot Permanent Dormitory (EPA for Phases 1&2) | 86.5 | 83.1 | 17.4 | 27.8 | 27.8 | 27.8 | 14.8 | FY 2014-15 |
Fixed Wing Sustainment Program (EPA) | 33.8 | 61.1 | 47.6 | 8.6 | 8.6 | 16.0 | 15.5 | FY 2013-14 |
Total | 618.7 | 619.4 | 329.2 | 108.1 | 108.1 | 118.0 | 78.1 |
* PPA – preliminary project approval
* EPA – effective project approval