Site 36868019 - Klemtu RCMP

  • Status

    Confirmatory sampling completed. No further action required.
  • Site Status

    Closed
  • Classification

    Medium Priority for Action

Site Details

Site Location

Locate this site on map
  • Latitude, Longitude

    52.58686, -128.52019
  • Municipality

    Kitasoo 1, BC
  • Federal Electoral District

    Skeena--Bulkley Valley

Contaminant Details

Contamination Estimate

  • Cubic Meters

    10

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Soil

Action Plan

Phase 2 ESA completed. Contaminated soil observed beneath the heating oil AST and in an area formerly used to store hazardous materials. Groundwater results are all below applicalbe CCME aquatic life guidelines. Accessible soil was remediated in 2007. Risk assessment for remaining inaccessible soils confirmed acceptable risk levels. No further work required.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km182
5 km349
10 km349
25 km349
50 km349

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $48,093.00

FCSAP Expenditures

  • Assessment

    $38,474.00

Financial/Annual Information

2007-2008

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    PR E/386
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $27,933.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $22,346.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2006-2007

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    PR E/386
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $20,160.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $16,128.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    1 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2005-2006

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    36868-019
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2004-2005

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    36868-019
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No