Site 29757009 - Plateau (demolition site), DRDC-Trials
-
Status
Confirmatory sampling completed. Long term monitoring underway. -
Site Status
Active -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 05906)
Site Location
-
Latitude, Longitude
46.9309, -71.521 -
Municipality
Saint-Gabriel-de-Valcartier, QC -
Federal Electoral District
Portneuf--Jacques-Cartier
Site Management Strategy
- Periodic Monitoring
- Risk Management
Contaminant Details
Contamination Estimate
-
Hectares
63
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
Metal, metalloid, and organometallic | Surface water |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Soil |
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) | Surface water |
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) | Groundwater |
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) | Soil |
Energetics | Groundwater |
Energetics | Soil |
Other inorganics | Groundwater |
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 5 |
5 km | 2,638 |
10 km | 20,811 |
25 km | 496,110 |
50 km | 986,016 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$565,154.94 -
Remediation
$801,947.08
FCSAP Expenditures
-
Assessment
$188,039.34 -
Remediation
$685,436.14
Financial/Annual Information
- 2023-2024
- 2022-2023
- 2021-2022
- 2020-2021
- 2019-2020
- 2018-2019
- 2017-2018
- 2016-2017
- 2015-2016
- 2014-2015
- 2013-2014
- 2012-2013
- 2011-2012
- 2010-2011
- 2009-2010
- 2008-2009
- 2007-2008
- 2006-2007
- 2005-2006
2023-2024
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$30,825.45Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$26,201.63FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2022-2023
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$23,269.48Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$19,779.06FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2021-2022
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$18,669.71Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$15,869.25FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$15,133.41Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$12,863.40FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$14,319.87Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$12,171.89FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$90,877.81Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$77,246.14FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$26,449.92Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$26,449.92FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$214,088.05Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$181,974.84FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$130,336.60Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$110,786.11FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
National DefenceInternal Identifier
0449-C119Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$42,592.53Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$36,203.65FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
National DefenceInternal Identifier
0449-C040Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$48,026.05Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$40,822.15FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
National DefenceInternal Identifier
S-10131Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$63,201.50Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$53,721.28FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
National DefenceInternal Identifier
S-10131Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$2,000.00Total Remediation Expenditure
$84,156.70Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$71,346.82FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
National DefenceInternal Identifier
S10131Highest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$47,654.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$40,760.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
National DefenceInternal Identifier
S10131Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$100,060.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
National DefenceInternal Identifier
S10131Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$72,138.54Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$57,710.83FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
National DefenceInternal Identifier
S10131Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$14,299.39Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$11,439.51FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
National DefenceInternal Identifier
S10131Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$97,661.42Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$78,129.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
National DefenceInternal Identifier
S10131Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$231,341.59Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 41