Site 00027714 - JCP- section 7 (Terrains au sud de Viger)

  • Status

    Historical review completed. Initial testing underway.
  • Site Status

    Suspected
  • Classification

Site Details

Site Location

Locate this site on map
  • Latitude, Longitude

    45.522265, -73.545678
  • Municipality

    Montréal, QC
  • Federal Electoral District

    Ville-Marie--Le Sud-Ouest--Île-des-Soeurs

Contaminant Details

Contamination Estimate

The following contaminated media may exist on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Soil
PAHs (polycyclic aromatic hydrocarbon) Soil

Additional Information

numéros de lot: 1 182 648; 1 182 645

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km12,330
5 km437,617
10 km1,549,032
25 km3,434,966
50 km4,713,857

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $6,684.39

FCSAP Expenditures

  • Assessment

    $5,347.51

Financial/Annual Information

2022-2023

  • Reporting Organization

    The Jacques-Cartier and Champlain Bridges Inc.
  • Internal Identifier

    JCP- section 7 (Terrains au sud de Viger)
  • Highest Step Completed

    02 Historical Review
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2021-2022

  • Reporting Organization

    The Jacques-Cartier and Champlain Bridges Inc.
  • Internal Identifier

    JCP- section 7 (Terrains au sud de Viger)
  • Highest Step Completed

    01 Identify Suspect Sites
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    The Jacques-Cartier and Champlain Bridges Inc.
  • Internal Identifier

    JCP- section 7 (Terrains au sud de Viger)
  • Highest Step Completed

    01 Identify Suspect Sites
  • Total Assessment Expenditure

    $6,684.39
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $5,347.51
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2019-2020

  • Reporting Organization

    The Jacques-Cartier and Champlain Bridges Inc.
  • Internal Identifier

    JCP- sections 7 et 8 (Terrains au sud de Viger)
  • Highest Step Completed

    01 Identify Suspect Sites
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No