Site 00027712 - Ile Sainte-Hélène

  • Status

    Detailed testing completed. Remediation / risk management planned.
  • Site Status

    Active
  • Classification

    Insufficient Information

Site Details

Site Location

Locate this site on map
  • Latitude, Longitude

    45.52063, -73.53519
  • Municipality

    Montréal, QC
  • Federal Electoral District

    Ville-Marie--Le Sud-Ouest--Île-des-Soeurs

Contaminant Details

Contamination Estimate

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Soil

Additional Information

Numéro de lots cadastral: 2395698; 2627040; 2627041; 2395699; 2627042

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km1,758
5 km404,121
10 km1,493,790
25 km3,377,681
50 km4,703,430

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $543,786.39

FCSAP Expenditures

  • Assessment

    $152,717.31

Financial/Annual Information

2022-2023

  • Reporting Organization

    The Jacques-Cartier and Champlain Bridges Inc.
  • Internal Identifier

    JCP- sections 4,5 et 6
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $536,686.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $147,037.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2021-2022

  • Reporting Organization

    The Jacques-Cartier and Champlain Bridges Inc.
  • Internal Identifier

    JCP- sections 4,5 et 6
  • Highest Step Completed

    01 Identify Suspect Sites
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    The Jacques-Cartier and Champlain Bridges Inc.
  • Internal Identifier

    JCP- sections 4,5 et 6
  • Highest Step Completed

    01 Identify Suspect Sites
  • Total Assessment Expenditure

    $7,100.39
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $5,680.31
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2019-2020

  • Reporting Organization

    The Jacques-Cartier and Champlain Bridges Inc.
  • Internal Identifier

    JCP- sections 4,5 et 6
  • Highest Step Completed

    01 Identify Suspect Sites
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No