Search Results
Search Results Summary | |
---|---|
Criteria: |
|
Sort Key: | FCSI Identifier (ascending) |
Sites Found: | 253 |
Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00000862
Gabarus (Metals Impacts in Soil) |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00001118
New Minas RCMP |
Initial testing completed. No further action required. | 2012-2013 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00001159
Guysborough RCMP |
Historical review completed. No further action required. | 2006-2007 | 02 Historical Review | |
00001171
Tatamagouche RCMP |
Historical review completed. No further action required. | 2006-2007 | 02 Historical Review | |
00001172 | Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00001173 | Historical review completed. No further action required. | 2006-2007 | 02 Historical Review | |
00001174
Stellarton RCMP |
Historical review completed. No further action required. | 2006-2007 | 02 Historical Review | |
00001176
North Sydney RCMP |
Historical review completed. No further action required. | 2006-2007 | 02 Historical Review | |
00001326
The Atlantic Food and Horticulture Research Centre |
Detailed testing completed. No further action required. | 2020-2021 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00001327
Sheffield Mills Research Farm |
Detailed testing completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00001387
The Atlantic Food and Horticulture Research Centre |
Detailed testing completed. No further action required. | 2022-2023 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00001537
Sheffield Mills Research Farm |
Detailed testing completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00001538
Sheffield Mills Research Farm |
Detailed testing completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00001539
Sheffield Mills Research Farm |
Detailed testing completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00004795
23 - Eskasoni - 06043 - ESKASONI 3 / 0202500305 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00004796
23 - Eskasoni - 06043 - ESKASONI 3 / 0202500405 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00004797
23 - Eskasoni - 06043 - ESKASONI 3 / 0202500505 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00004807
23 - Eskasoni - 06043 - ESKASONI 3 / 0202501505 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00004808
23 - Eskasoni - 06043 - ESKASONI 3 / 0202501605 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00004809
23 - Eskasoni - 06043 - ESKASONI 3 - 0202501705 |
Historical review planned. | 2022-2023 | 01 Identify Suspect Sites | |
00004812
23 - Eskasoni - 06043 - ESKASONI 3 - 0202502005 |
Historical review completed. No further action required. | 2015-2016 | 02 Historical Review | |
00004924
23 - Eskasoni - 06043 - ESKASONI 3 / 0202513205 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00005054
23 - Eskasoni - 06043 - ESKASONI 3 / 0202526205 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00005055
23 - Eskasoni - 06043 - ESKASONI 3 - 0202526305 |
Historical review planned. | 2022-2023 | 01 Identify Suspect Sites | |
00005056
23 - Eskasoni - 06043 - ESKASONI 3 - 0202526405 |
Historical review planned. | 2022-2023 | 01 Identify Suspect Sites | |
00005196
23 - Eskasoni - 06043 - ESKASONI 3 / 0202540405 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00006158
27 - Millbrook - 06059 - MILLBROOK 27 / 0202636605 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00006159
27 - Millbrook - 06059 - MILLBROOK 27 / 0202636705 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00006164
23 - Eskasoni - 06043 - ESKASONI 3 - 0202637205 |
Historical review completed. No further action required. | 2015-2016 | 02 Historical Review | |
00006165
23 - Eskasoni - 06043 - ESKASONI 3 / 0202637305 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00006167
23 - Eskasoni - 06043 - ESKASONI 3 / 0202637505 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00006355
23 - Eskasoni - 06043 - ESKASONI 3 - 1000014293 |
Historical review completed. Initial testing underway. | 2022-2023 | 02 Historical Review | |
00008671
Former CFS Sydney, NS, Pinetree Landfill |
Confirmatory sampling completed. No further action required. | 2022-2023 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00012243
Louisbourg (Metal Impacted Soil- Lighthouse Area) |
Remediation / risk management completed. No further action required. | 2012-2013 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00012244
Sydney Bar - Benzene and TPH in Soil |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00013176
LOUISBOURG (Impacted Sediments- PAHs and Metals) |
Initial testing completed. Detailed testing underway. | 2022-2023 | 03 Initial Testing Program | |
00013199
PORT MORIEN (Impacted Sediments- Metals/PAHs) |
Initial testing completed. Detailed testing underway. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00013200
PORT MORIEN (Impacted Soil- Former UST) |
Confirmatory sampling completed. No further action required. | 2021-2022 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00013418
Millbrook RCMP |
Historical review completed. No further action required. | 2007-2008 | 02 Historical Review | |
00013425
Sydney RCMP |
Historical review completed. No further action required. | 2009-2010 | 02 Historical Review | |
00013446
Pictou RCMP |
Historical review completed. No further action required. | 2007-2008 | 02 Historical Review | |
00013447
Reserve Mines RCMP |
Historical review completed. No further action required. | 2007-2008 | 02 Historical Review | |
00013504
Eskasoni RCMP |
Historical review completed. No further action required. | 2007-2008 | 02 Historical Review | |
00016806
Baillie Brook - Zinc in Soil near Light |
Initial testing completed. No further action required. | 2012-2013 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00016807
Baillie Brook East Breakwater - No Suspected Contamination |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00016808
Baillie Brook West Breakwater - No Suspected Contamination |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00016859
Pictou Bar (Divested 2006)(Potential metals, PAHs and hydrocarbons in soil) |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
00016883
Trenton Range Front (Lead in Soil) |
Confirmatory sampling completed. No further action required. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00016884
Trenton Range Rear (Zinc in Soil) |
Initial testing completed. No further action required. | 2012-2013 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017182
Ballast Grounds - No Soil |
Historical review completed. No further action required. | 2009-2010 | 02 Historical Review | |
00017185
Battery Point - Main-a-Dieu (No Suspected Contamination) |
Historical review completed. No further action required. | 2009-2010 | N Not a Priority for Action | 02 Historical Review |
00017186
Battery Point Range Front- No Issues |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00017187
Battery Point Range Rear - No Issues |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00017211
Cape Blomidon VHF - No Further Assessment Required |
Historical review completed. No further action required. | 2008-2009 | N Not a Priority for Action | 02 Historical Review |
00017247
Derby Point - Metals in Soil |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00017285
Glace Bay North Breakwater (No Soil) |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00017286
Glace Bay Range Front (DFO SSC standards met - no further assessment required) |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017287
Glace Bay Range Rear (Metals in soil meet SSCs - No further Assessment Required) |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017301
Halls Harbour (No Suspected Contamination) |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00017334
Lingan Range Front (Metals in Soil) |
Initial testing completed. No further action required. | 2012-2013 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017335
Lingan Range Rear (Arsenic in soil) |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017336
Little Bras dOr Range Front (Metal Impacts In Soil) |
Confirmatory sampling completed. No further action required. | 2017-2018 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00017337
Little Bras dOr Range Rear (Metals Impacts in Soil) |
Remediation / risk management completed. No further action required. | 2016-2017 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00017338
Little Bras dOr Inner Sector Light (No Soil) |
Historical review completed. No further action required. | 2009-2010 | 02 Historical Review | |
00017344
Little Lorraine (Metals in Soil) |
Initial testing completed. No further action required. | 2012-2013 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017358
Louisbourg Northeast Arm Range Front (Unassessed) |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00017359
Louisbourg Northeast Arm Range Rear (Unassessed) |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00017360
Louisbourg Range Front (Metal Impacts in Soil) |
Remediation / risk management completed. No further action required. | 2016-2017 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00017361
Louisbourg Range Rear (Copper in Soil) |
Detailed testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00017362
Louisboug SAR (No Impacts Identified) |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00017380
Main-à-Dieu (Metals and BTE in Soil) |
Detailed testing completed. No further action required. | 2015-2016 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00017381
Main-a-Dieu Harbour (No Suspected Contamination) |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00017394
Minas Basin - No Soil |
Historical review completed. No further action required. | 2009-2010 | 02 Historical Review | |
00017396
Moque Head - No Impacts |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00017410
Northwest Bar - Unassessed |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00017450
Port Morien (No Suspected Contamination) |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00017453
Porter Point - No Petential Contamination Identified |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00017464
Rouse Point - No Impacts Identified |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00017497
Sydney Radar ( Metals in Soil not Exceeding SSCs) |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017498
Sydney South Arm Range Front - Metals in soil not exceeding DFOs SSC |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017499
Sydney South Arm Range Rear - Metals in soil not exceeding DFOs SSC |
Initial testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017509
Upper Pereau (No Impacts Identified) |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00017533
Donkin VHF Site (No Suspected Contamination) |
Historical review completed. No further action required. | 2008-2009 | N Not a Priority for Action | 02 Historical Review |
00017545
Birch Hill Camp - Unassessed |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00017548
Glace Bay CPC Building (Unassessed) |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00017561
North Sydney Tide Gauge (Unassessed) |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00017569
Sydney Fisheries and Oceans Building (Unassessed) |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00017582
Point Aconi (No Land) |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00017593
Sydney Southeast Bar - No Impacts |
Historical review completed. No further action required. | 2013-2014 | 02 Historical Review | |
00017713
ALDER POINT (no soil impacts - burn area Closed) |
Detailed testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00017714
ALDER POINT (no soil impacts by former UST closed) |
Detailed testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00017715
ALDER POINT (Soil Impacts - waste oil tank) |
Confirmatory sampling completed. No further action required. | 2017-2018 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00017730
BIG ISLAND - Unassessed |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00017781
GABARUS - unassessed |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00017782
GLACE BAY (Sediment impacts) |
Initial testing completed. No further action required. | 2022-2023 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017783
GLACE BAY (Soil Impacts- Hydrocarbons and Metals) |
Remediation / risk management completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00017806
LINGAN (Hydrocarbon Impacts - Burn Pit 2 Area) |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00017807
LINGAN (PAHs in Waterlot Sediment) |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00017808
LINGAN (Metal Impacts in Soil - North End of Property) |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00017809
LINGAN (Hydrocarbon Impacts from Adjacent AST) |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00017811
SCOTS BAY (LITTLE COVE) (No Land-Based Contamination) |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00017834
LOUISBOURG (No soil GW impacts from former storage tanks Closed) |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
00017835
LOUISBOURG (No soil impacts in waste disposal area Closed) |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
00017866
NORTH SYDNEY-BALLAST GROUNDS (hydrocarbon staining by AST Closed) |
Initial testing completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017877
PEREAUX (DELHAVEN) (Metals in Sediment) |
Initial testing completed. No further action required. | 2015-2016 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017880
Pictou Landing (Benzene in Soil, Cadmium in Water) |
Detailed testing completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00017884
POINT ACONI (MCCREADYVILLE) (PAH and Metals in Sediments) |
Initial testing completed. No further action required. | 2015-2016 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00017894
PORT MORIEN (No Soil Impacts- Burn Area) |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
00017905
SCATARIE ISLAND - Unassessed |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00022801
Membertou RCMP |
Initial testing completed. No further action required. | 2007-2008 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022975
Louisbourg (Metals/PAHs in Soil - Former Coal Ash Area) |
Remediation / risk management completed. No further action required. | 2012-2013 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00023043
BAILEYS BROOK (LISMORE) - Soil Impacts- AST/Dispenser Area |
Confirmatory sampling completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00023091
SCOTS BAY (LITTLE COVE) (Contaminated Marine Sedim |
Initial testing completed. No further action required. | 2021-2022 | 03 Initial Testing Program | |
00023124
NORTH SYDNEY-BALLAST GROUNDS (Sediment contamination) |
Initial testing completed. No further action required. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00023143
ALDER POINT (Sediment impacts) |
Initial testing completed. Detailed testing underway. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00024367
PEREAUX (DELHAVEN) (No Issues in Soil) |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00025328
South Bar (Sediment Impacts) |
Initial testing completed. Detailed testing underway. | 2022-2023 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00025351
Eastern Nova Scotia Area Office |
Historical review completed. No further action required. | 2018-2019 | 02 Historical Review | |
00026385
New Minas RCMP |
Confirmatory sampling completed. No further action required. | 2013-2014 | I Insufficient Information | 09 Confirmatory Sampling and Final Reporting |
00027852
Salmon River at Union |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
02731002
The Atlantic Food and Horticulture Research Centre |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
02731003
Sheffield Mills Research Farm |
Detailed testing completed. No further action required. | 2015-2016 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
02731004
The Atlantic Food and Horticulture Research Centre |
Confirmatory sampling completed. No further action required. | 2020-2021 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
02731005
Sheffield Mills Research Farm |
Confirmatory sampling completed. No further action required. | 2015-2016 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
02738001
Sheffield Mills Research Farm |
Confirmatory sampling completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
02739001
Aldershot Landfill/Former Incinerator |
Initial testing completed. Detailed testing underway. | 2022-2023 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
02739002
Mill Pond and Sewage Lagoons - Aldershot |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
02739003
Former Garage (B46) and Septic Tank Area - Aldershot |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | N Not a Priority for Action | 08 Implement Remediation/Risk Management Strategy |
02739004
Former Photo Lab (B95) - Aldershot |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
02739006
Active Grenade Range - Aldershot |
Detailed testing completed. No further action required. | 2014-2015 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
02739007
Active 100m Range - Aldershot |
Initial testing completed. No further action required. | 2006-2007 | 2 Medium Priority for Action | 03 Initial Testing Program |
02739008
Active 600m Range - Aldershot |
Detailed testing completed. No further action required. | 2014-2015 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
02739010
Demolition Range - Aldershot |
Initial testing completed. No further action required. | 2006-2007 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
02739011
Former 500yd Range - Aldershot |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
02739012
Meadowview Landfill - Aldershot |
Long term monitoring completed. No further action required. | 2017-2018 | N Not a Priority for Action | 10 Long-Term Monitoring (Optional) |
02739013
Rocket Range |
Initial testing completed. No further action required. | 2006-2007 | 03 Initial Testing Program | |
02739014
Former Building 37 Aldershot |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
02739022
Former Revolver Range - Aldershot |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
02739026
Former EME Vehicle Maintenance Garage and Sewer - Aldershot |
Initial testing completed. Detailed testing underway. | 2022-2023 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
02739027
UST Building 209 - Aldershot |
Detailed testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
02739030
Former Vehicle Compound (B140) Aldershot |
Detailed testing completed. No further action required. | 2011-2012 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
02739040
Unidentified Range 1 & 2 |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
02739053
Tent City Areas |
Historical review completed. No further action required. | 2006-2007 | 02 Historical Review | |
02739055
Peach Lake - Aldershot |
Detailed testing completed. No further action required. | 2009-2010 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
02739056
Alleged Drum Dump Area - Aldershot |
Initial testing completed. No further action required. | 2015-2016 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03130001
Truro Armoury (4001) - Armoury Building (B1) |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03130003
Truro Armoury (4003) - Indoor Rifle Range |
Initial testing completed. No further action required. | 2000-2001 | 03 Initial Testing Program | |
03130005
Truro Armoury (4004) - Former POL Storage Locations |
Detailed testing completed. No further action required. | 2009-2010 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
03136001
Truro RCMP District Office Site |
Confirmatory sampling completed. No further action required. | 2020-2021 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03138001
Masstown (2501) - Receiver Building |
Historical review completed. No further action required. | 2001-2002 | 02 Historical Review | |
03138002
Masstown (2502) - Antenna Field |
Historical review completed. No further action required. | 1999-2000 | N Not a Priority for Action | 02 Historical Review |
03214001
Cobequid Biodiversity Centre (Metals & Hydrocarbons in Soil near Residence) |
Detailed testing completed. No further action required. | 2005-2006 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
03214002
Cobequid Biodiversity Centre (Metals in Soil near the Hatchery) |
Detailed testing completed. No further action required. | 2005-2006 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
03214003
Cobequid Biodiversity Centre (Metals/Hydrocarbons-Soil-Burn Pit & Debris Areas) |
Detailed testing completed. No further action required. | 2005-2006 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
03275001
Westville GOCB - Government of Canada Building |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
03280001
BAILEYS BROOK (LISMORE) - Waterlot Sediment Impacts - PCBs & Metals |
Initial testing completed. No further action required. | 2019-2020 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03280002
BAILEYS BROOK (LISMORE) - PHC Impacts - Fmr Tractor Garage |
Initial testing completed. Detailed testing underway. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03281001
LITTLE HARBOUR (PICTOU COUNTY) (Hydrocarbon Soil Impacts near Waste Oil Tank) |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03281002
LITTLE HARBOUR (PICTOU COUNTY) (Sediment Impacts- |
Initial testing completed. No further action required. | 2021-2022 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03288003
New Glasgow Armoury (2901) - Armoury Buidling |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03288004
New Glasgow Armoury (2902) - POL Storage Building |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03288005
New Glasgow Military Parking (9301) - Coal Ash Disposal Area |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03288006
New Glasgow Armoury - Military Parking (9302) |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03634001
MAIN-À-DIEU (Metal Impacted Soil) |
Confirmatory sampling completed. No further action required. | 2022-2023 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03634002
Main-A-Dieu |
Initial testing completed. No further action required. | 2022-2023 | 03 Initial Testing Program | |
03640001
Parks Canada Trade Waste Site |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03640002
Former Town Landfill |
Initial testing completed. No further action required. | 2013-2014 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03640005
Former military disposal site |
Remediation / risk management completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03640006
Maintenance Compound Fuel Spill Site |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03641001
Scatarie Island - Hydrocarbon, Metal, PAH and PCB Impacted Soil |
Confirmatory sampling completed. No further action required. | 2017-2018 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03642001
Guyon Island - Metals and Hydrocarbon Impacts in Soil/GW |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03660002
CFS Sydney- FPS Radar Site (1701)- Scrap Stg Compound |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03660003
CRS Sydney - FPS Radar Site (1702) - Radar Building B55 |
Initial testing completed. No further action required. | 2001-2002 | 03 Initial Testing Program | |
03660004
CFS Sydney - FPS Radar Site (1703) - Former PCB Storage |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03660005
CFS Sydney FPS Radar Site(1704) Former Furnace Oil Tank (B1) |
Initial testing completed. No further action required. | 2001-2002 | 03 Initial Testing Program | |
03660006
CFS Sydney FPS Radar Site (1705) Former Furnace Oil Tank B57 |
Initial testing completed. No further action required. | 2001-2002 | 03 Initial Testing Program | |
03660007
CFS Sydney FPS Radar Site (1706) Former Furnace Oil Tank B50 |
Initial testing completed. No further action required. | 2001-2002 | 03 Initial Testing Program | |
03662001
Sydney Rifle Range (3801) - Rifle Range |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03685001
Flint Island - Metal Impacts in Soil |
Detailed testing completed. No further action required. | 2012-2013 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
03687001
Low Point - Metals in Soil, Hydrocarbons in Soil/GW |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03690001
Glace Bay Armoury (1801) - Armoury (B1) |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03690002
Glace Bay Armoury (1802) - POL Storage |
Initial testing completed. No further action required. | 2001-2002 | 03 Initial Testing Program | |
03690003
Glace Bay Armoury (1803) - South Fence (Naphtha) |
Initial testing completed. No further action required. | 2001-2002 | 03 Initial Testing Program | |
03708001
Victoria Park (4101) - Headquarters Building (B8) |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03708002
Victoria Park (4102) - Quarter Masters Stores (B35) |
Initial testing completed. No further action required. | 1999-2000 | 03 Initial Testing Program | |
03708003
Victoria Park (4103) - Heating Plant (B11) |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
03708004
Victoria Park (4104) - Former Maintenance Garage (B34) |
Initial testing completed. No further action required. | 1999-2000 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03708005
Victoria Park (4105) - Former Garage B27 |
Initial testing completed. No further action required. | 1999-2000 | 03 Initial Testing Program | |
03747001
Sydney Range Front (Soil Impacts Around Light - Metals/HC/PAHs) |
Remediation / risk management completed. No further action required. | 2016-2017 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03752001
Point Aconi (Metal Impacts in Soil) |
Initial testing completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
03759002
Canadian Coast Guard College (Metals & Toulene in Soil - Fmr. Bldg. N of creek) |
Detailed testing completed. No further action required. | 2016-2017 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
03759003
Canadian Coast Guard College (Metal/PAH impacts in Crawley Creek Sediment) |
Remediation / risk management completed. No further action required. | 2016-2017 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
03760004
North Sydney Armoury (3001) - B32 |
Initial testing completed. No further action required. | 1999-2000 | N Not a Priority for Action | 03 Initial Testing Program |
03765001
Real Property |
Detailed testing completed. No further action required. | 2018-2019 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05340001
26 - Membertou - 06054 - CARIBOU MARSH 29 - 1000038295 |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
05340002
26 - Membertou - 06056 - MEMBERTOU 28B - 1000028195 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 03 Initial Testing Program | |
05340003
26 - Membertou - 06056 - MEMBERTOU 28B - 1000012493 |
Historical review completed. Initial testing underway. | 2022-2023 | 02 Historical Review | |
05358001
27 - Millbrook - 06059 - MILLBROOK 27 - 1000000393 |
Historical review completed. Initial testing underway. | 2022-2023 | 02 Historical Review | |
12856001
Lingan Beach Road |
Detailed testing completed. No further action required. | 2009-2010 | I Insufficient Information | 05 Detailed Testing Program |
14985001
Four Star / Broughton |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
15039001
Dominion 4 |
Confirmatory sampling completed. No further action required. | 2020-2021 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
16662001
Victoria Junction Tailings Basin |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
21872001
Hospital Road, Point Edward / Keating Point, Cape Breton, NS |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
29734001
SOUTH BAR (Hydrocarbon Impacts- Gear Shed Area) |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
30020001
NEW WATERFORD (Metals Impacted Soil in Dredge Disposal Area) |
Detailed testing completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
30020002
NEW WATERFORD (Waterlot Sediment Impacts - PAHs) |
Initial testing completed. No further action required. | 2022-2023 | 03 Initial Testing Program | |
32962001
Sydney Range Rear (Soil-metals/petroleum) |
Remediation / risk management completed. No further action required. | 2016-2017 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38002001
Dominion 26 |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38003001
Dominion 20 |
Long term monitoring completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 10 Long-Term Monitoring (Optional) |
38007001
Lingan - Mine Waste Rock Pile (LWRP) |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38007002
Lingan - Mine Waste Rock Pile (GDNW) |
Confirmatory sampling completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38007003
Lingan - Mine Waste Rock Pile (SDSM) |
Confirmatory sampling completed. No further action required. | 2018-2019 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38008001
Domestic Coal Yard |
Initial testing completed. Detailed testing underway. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
38009001
Princess Site - Mine Waste Rock Pile |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38009002
Princess Site - Princess Wash Plant Site |
Confirmatory sampling completed. No further action required. | 2018-2019 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38009003
Princess Site - Edwards Pond |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38010001
Victoria Junction (Main Pile) |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38010002
Victoria Junction (small pile) |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38018001
Former Gowrie Wash Plant |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38019001
Dominion No.22 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |
38037001
Dominion 21 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |
38076001
Tom Pit-Tobin Road |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
38086001
Franklin - Waste Rock |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38086002
Franklin (#5 Prospect) - mine water |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38090001
Site 38090001 |
Historical review not required. | 2020-2021 | I Insufficient Information | 01 Identify Suspect Sites |
38099001
Beaver & Nicholson |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38107001
Broughton (Waste Rock Pile) |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38128001
Dominion 6 (PCD1 - Clyde Mine) |
Confirmatory sampling completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38162001
Dominion 6 - (Waste Rock Pile) |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38204001
Dominion 25 - Mine Waste Rock Pile |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38204002
Dominion 25 - Mine Water discharge to surface |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38240001
Dominion 11 - Covered Waste Rock |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38240002
Dominion 11 - Mine Water passive treatment system |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38245001
Dominion no. 3 |
Confirmatory sampling completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38314001
GBU3 Oily Waste |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38378001
Summit (waste rock pile) |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
38410001
Dominion No. 18 |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38433001
New Victoria Mine Water Treatment Facility |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
38439001
Dominion No. 14 |
Confirmatory sampling completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38461001
New Waterford Residential Property |
Detailed testing completed. Remediation / risk management planned. | 2022-2023 | 3 Low Priority for Action | 05 Detailed Testing Program |
38495001
Gowrie No. 4 |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38504001
Dominion 5 & 10 - Mine Waste Rock |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
38620001
Neville Street Passive Treatment System |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
38642001
Phalen Ocean Dump (PHOD) |
Confirmatory sampling completed. No further action required. | 2018-2019 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
56665001
AECL Heavy Water Plant Site |
Confirmatory sampling completed. No further action required. | 2018-2019 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
69813001
New Glasgow Armoury (7101) - Vac Lot Proposed Armoury Site |
Initial testing completed. No further action required. | 2000-2001 | 03 Initial Testing Program | |
81492001
Port Caledonia Sydney VHF (Soil not exceeding SSCs) |
Detailed testing completed. No further action required. | 2019-2020 | 2 Medium Priority for Action | 05 Detailed Testing Program |
N7084001
North Sydney Armoury (3002) - B35 |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N7089001
Disposed - Mason St. Garage (2401) - Former POL/Storage Area |
Long term monitoring completed. No further action required. | 2013-2014 | N Not a Priority for Action | 10 Long-Term Monitoring (Optional) |
N7090001
Disposed- Mason St.Garage (2402) Former Diesel UST & Pump |
Confirmatory sampling completed. No further action required. | 2013-2014 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
N7091001
Disposed - Mason St Garage (2403) - Maintenance Garage (B1) |
Remediation / risk management completed. No further action required. | 2012-2013 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N7092001
Disposed - Mason St Garage (2404) - Office Storage Building |
Detailed testing completed. No further action required. | 2019-2020 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
N7095001
Former CFS Sydney |
Confirmatory sampling completed. No further action required. | 2020-2021 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
- Version:
- 40