Site 22039001 - Daniel J. MacDonald Building

  • Status

    Initial testing completed. No further action required.
  • Site Status

    Closed
  • Classification

    Not a Priority for Action

Site Details

Site Location

Locate this site on map
  • Latitude, Longitude

    46.23611, -63.12628
  • Municipality

    Charlottetown, PE
  • Federal Electoral District

    Charlottetown

Site Management Strategy

  • Other

Action Plan

Phase II Environmental Site Assessment Follow-up to be completed to ensure petroleum hydrocarbons and TPH in soil and groundwater remain below guidelines. This is currently not considered a contaminated site.

Additional Information

This site was reported in 2003/2004 as a contaminated site in error, though there are impacts present on the property, the levels present are not in exceedance of guidelines. A request is being made to have this record of a contaminated site at this property removed.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km7,774
5 km48,804
10 km67,675
25 km98,280
50 km152,575

Financial/Annual Information

2006-2007

  • Reporting Organization

    Public Services and Procurement Canada
  • Internal Identifier

    Atlantic 22039001
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2005-2006

  • Reporting Organization

    Public Services and Procurement Canada
  • Internal Identifier

    Atlantic 22039001
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No