Site 10868001 - TCE Contamination - Highbury Complex

  • Status

    Remedial action plan completed. Remediation / risk management underway.
  • Site Status

    Active
  • Classification

    High Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    Federal Real Property
  • Property Type

    Federal (DFRP Property Number 10868)

Site Location

Locate this site on map
  • Latitude, Longitude

    43.0001, -81.2038
  • Municipality

    London, ON
  • Federal Electoral District

    London--Fanshawe

Site Management Strategy

  • Remediation
  • Continous Monitoring
  • Risk Management

Contaminant Details

Contamination Estimate

  • Hectares

    3

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Groundwater
PHCs (petroleum hydrocarbons) Soil
BTEXs (benzene, toluene, ethylbenzene, and xylene) Groundwater
BTEXs (benzene, toluene, ethylbenzene, and xylene) Soil
PAHs (polycyclic aromatic hydrocarbon) Groundwater
PAHs (polycyclic aromatic hydrocarbon) Soil
Halogenated Hydrocarbon Groundwater
Halogenated Hydrocarbon Soil

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km4,076
5 km144,029
10 km342,542
25 km450,226
50 km717,177

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $267,940.15
  • Remediation

    $16,597,055.42

FCSAP Expenditures

  • Assessment

    $95,899.91
  • Remediation

    $13,954,231.25

Financial/Annual Information

2022-2023

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $4,524,518.58
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $3,845,840.79
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    5767 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2021-2022

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $814,414.57
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $692,252.38
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $5,355,420.43
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $4,552,107.37
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    13648.78 t
  • Closed

    No

2019-2020

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $4,210,660.89
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $3,579,061.76
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2018-2019

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $618,240.70
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $525,504.59
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2017-2018

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $208,974.18
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $177,628.05
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2016-2017

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $71,443.92
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $60,727.33
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2015-2016

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $171,211.97
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $145,530.17
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2014-2015

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $297,153.85
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $252,580.77
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2013-2014

  • Reporting Organization

    National Defence
  • Internal Identifier

    0221-C001
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $94,003.27
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $79,902.78
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2012-2013

  • Reporting Organization

    National Defence
  • Internal Identifier

    S-5822
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $151,161.91
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2011-2012

  • Reporting Organization

    National Defence
  • Internal Identifier

    S-5822
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $121,863.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2010-2011

  • Reporting Organization

    National Defence
  • Internal Identifier

    S5822
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    National Defence
  • Internal Identifier

    S5822
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2008-2009

  • Reporting Organization

    National Defence
  • Internal Identifier

    S5822
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $4,474.73
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    National Defence
  • Internal Identifier

    S5822
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $36,225.33
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $28,980.26
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    National Defence
  • Internal Identifier

    S5822
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $55,308.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $44,246.44
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2005-2006

  • Reporting Organization

    National Defence
  • Internal Identifier

    S5822
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $61,470.24
  • Total Remediation Expenditure

    $68,450.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $51,653.47
  • FCSAP Remediation Expenditure

    $14,115.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No