Site 00024667 - Harriet Harbour
-
Status
Remedial action plan completed. Remediation / risk management underway. -
Site Status
Active -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
National Park of Canada -
Property Type
Canada Lands
Site Location
-
Latitude, Longitude
52.29278, -131.19889 -
Municipality
North Coast E, BC -
Federal Electoral District
Skeena--Bulkley Valley
Site Management Strategy
- Assessment
Contaminant Details
Contamination Estimate
-
Hectares
125
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Sediment |
Metal, metalloid, and organometallic | Surface water |
Metal, metalloid, and organometallic | Sediment |
Metal, metalloid, and organometallic | Soil |
Action Plan
Site is under asssessment steps.
Additional Information
The site is located in a National Park of Canada.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 7 |
10 km | 31 |
25 km | 196 |
50 km | 647 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$291,040.37 -
Remediation
$1,009,183.81
FCSAP Expenditures
-
Assessment
$291,040.37 -
Remediation
$626,869.03
Financial/Annual Information
- 2022-2023
- 2021-2022
- 2020-2021
- 2019-2020
- 2018-2019
- 2017-2018
- 2016-2017
- 2015-2016
- 2014-2015
- 2013-2014
- 2012-2013
- 2011-2012
- 2010-2011
2022-2023
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2021-2022
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$8,331.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$5,775.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$991.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$72,196.64Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$60,570.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$52,677.82Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$44,330.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$305,342.39Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$35,500.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$260,203.39Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$204,535.46FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$255,612.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$233,879.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Parks Canada AgencyInternal Identifier
AWPGWHA008Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
Parks Canada AgencyInternal Identifier
857Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$291,040.37Total Remediation Expenditure
$48,054.57Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$291,040.37FCSAP Remediation Expenditure
$48,054.57FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 39