Site 00023376 - Site 1.2.1

  • Status

    Confirmatory sampling completed. No further action required.
  • Site Status

    Closed
  • Classification

    Medium Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    Federal Real Property
  • Property Type

    Federal (DFRP Property Number 06959)

Site Location

Locate this site on map
  • Latitude, Longitude

    45.4314, -73.6725
  • Municipality

    Montréal, QC
  • Federal Electoral District

    Dorval--Lachine--LaSalle

Site Management Strategy

  • Additional assessment

Contaminant Details

Contamination Estimate

  • Hectares

    0

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PAHs (polycyclic aromatic hydrocarbon) Soil
Metal, metalloid, and organometallic Soil

Action Plan

Site closed. No futher action is required.

Additional Information

The site is located in a Federal real property or in a Federal Program Lands.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km11,599
5 km191,668
10 km725,741
25 km3,311,737
50 km4,703,413

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $125,000.00
  • Remediation

    $780,665.00

FCSAP Expenditures

  • Assessment

    $100,000.00
  • Remediation

    $534,989.00

Financial/Annual Information

2013-2014

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AECLACT088
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2012-2013

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AECLACT088
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2011-2012

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AECLACT088
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $11,609.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $9,868.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2010-2011

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    795
  • Highest Step Completed

    08 Implement Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $525,121.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $525,121.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    795
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $243,935.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2008-2009

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    795
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $75,000.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $60,000.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    795
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $50,000.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $40,000.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No