Site 00012832 - Redstreak Sinkhole

  • Status

    Initial testing completed. No further action required.
  • Site Status

    Closed
  • Classification

    Not a Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    National Park of Canada
  • Property Type

    Canada Lands

Site Location

Locate this site on map
  • Latitude, Longitude

    50.634883, -116.03911
  • Municipality

    East Kootenay G, BC
  • Federal Electoral District

    Kootenay--Columbia

Contaminant Details

Contamination Estimate

  • Hectares

    0

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Soil
Metal, metalloid, and organometallic Soil
Other inorganics Soil

Action Plan

Site closed. No futher action is required.

Additional Information

The site is located in a National Park of Canada.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km0
5 km790
10 km1,357
25 km7,291
50 km8,973

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $10,000.00

FCSAP Expenditures

  • Assessment

    $8,000.00

Financial/Annual Information

2013-2014

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWPKOOT007
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2011-2012

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWPKOOT007
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2010-2011

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    757
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    757
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2008-2009

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    757
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    757
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    757
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2005-2006

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    757
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $10,000.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $8,000.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No