Search Results
Search Results Summary | |
---|---|
Criteria: |
|
Sort Key: | Province or Territory (ascending) |
Sites Found: | 59 |
Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00004540
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - 0902474805 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00006798
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - 7000078196 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00006821
581 - Seabird Island - 09657 - PEKW'XE:YLES (PECKQUAYLIS) - 7000069696 |
Initial testing completed. No further action required. | 2017-2018 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00006921
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - 0903340807 |
Confirmatory sampling completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00006922
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - 0903341007 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00006923
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - 0903341207 |
Historical review completed. Initial testing underway. | 2022-2023 | 02 Historical Review | |
00006924
565 - Matsqui First Nation - 08035 - SAHHACUM 1 - 0903341307 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00006925
565 - Matsqui First Nation - 08035 - SAHHACUM 1 - 0903341407 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 03 Initial Testing Program | |
00008202
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - BC04825711 |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00008203
565 - Matsqui - 08036 - MATSQUI MAIN 2 - BC04825811 |
Confirmatory sampling completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00008268
565 - Matsqui - 08036 - MATSQUI MAIN 2 - BC04832512 |
Detailed testing completed. Remediation / risk management planned. | 2022-2023 | 2 Medium Priority for Action | 05 Detailed Testing Program |
00008269
579 - Leq' a: mel First Nation - 08066 - AYLECHOOTLOOK NO. 5 - BC04832612 |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
00008288
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - BC04835412 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00008292
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - BC04835512 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00008293
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - BC04835612 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00008294
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - BC04835712 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00008295
565 - Matsqui First Nation - 08036 - MATSQUI MAIN 2 - BC04835912 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00008308
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838612 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00008309
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838712 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00008310
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838812 |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00008311
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838912 |
Detailed testing completed. No further action required. | 2014-2015 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00011135
Fraser River at Cox |
Confirmatory sampling completed. No further action required. | 2010-2011 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00013027
831-C04 Matsqui - Heating fluid leak |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00013028
849-C01 Mission Institution - Fuel Storage Tank System |
Initial testing completed. No further action required. | 2009-2010 | 03 Initial Testing Program | |
00021009
Mission Field Office - Unassessed |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00021081
Ruskin Spawning Channel |
Initial testing completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00021101
Stave River Fish Release - Unassessed |
Historical review completed. No further action required. | 2019-2020 | 02 Historical Review | |
00021237
Mission Enumeration Station - Unassessed |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00021373
MISSION |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00023377
831-L01 Matsqui Institution - Former Landfill |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00023378
848-L01 Ferndale Institution - Landfill for Clean Fill |
Confirmatory sampling completed. No further action required. | 2020-2021 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00024755
831-C01 Matsqui used oil tank |
Detailed testing completed. No further action required. | 2020-2021 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00025000
MAT-2 PMQ Heating Oil USTs |
Detailed testing completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00025004
MAT-6 Sewage Treatment Facility |
Detailed testing completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00025005
MAT-7 Former Septic Field |
Confirmatory sampling completed. No further action required. | 2023-2024 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00025006
MAT-8 Antenna Towers and Arrays |
Detailed testing completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00025007
MAT-9 Former building complex |
Detailed testing completed. No further action required. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00025008
MAT-10 Northwest corner of the property |
Initial testing completed. No further action required. | 2021-2022 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00025009
MAT-11 Main Operations Complex |
Detailed testing completed. No further action required. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00025831
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04847413 |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00026511
564 - Kwantlen First Nation - 08031 - LANGLEY 3 - BC04854614 |
Historical review planned. | 2022-2023 | 01 Identify Suspect Sites | |
05059001
565 - Matsqui - 08036 - MATSQUI MAIN 2 - 7000003693 |
Detailed testing completed. No further action required. | 2014-2015 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05109002
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - 7000078296 |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
05109003
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - 7000131001 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
05109004
578 - Sumas First Nation - 08061 - UPPER SUMAS NO. 6 - 0902064105 |
Confirmatory sampling completed. No further action required. | 2009-2010 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
16555003
Abbotsford Research Farm |
Initial testing completed. No further action required. | 2015-2016 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
16560001
831-C03 Matsqui Firefighting Training Area |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 2 Medium Priority for Action | 08 Implement Remediation/Risk Management Strategy |
19118019
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04832412 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
19118025
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04837812 |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
19118029
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838012 |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
19118030
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838112 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 03 Initial Testing Program | |
19118032
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838212 |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
19118034
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838312 |
Initial testing completed. No further action required. | 2016-2017 | 03 Initial Testing Program | |
19118036
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838412 |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
19118039
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04838512 |
Historical review completed. Initial testing underway. | 2022-2023 | 02 Historical Review | |
19118042
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04837912 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 03 Initial Testing Program | |
19118043
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04839312 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 03 Initial Testing Program | |
19118044
578 - Sumas First Nation - 08061 - UPPER SUMAS 6 - BC04839412 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 03 Initial Testing Program | |
N0020001
Former Fire Training Area |
Confirmatory sampling completed. No further action required. | 2013-2014 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
- Version:
- 40