00002427
Canada Centre for Inland Waters - ECCC
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008431
CFRB Hamilton/HMCS Star
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008500
Winona Rifle Range
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012702
GRIMSBY (Unassessed)
Initial testing completed. No further action required. 2005-2006   03 Initial Testing Program
00013754
Burlington Canal South Pier Inner (Unassessed)
Historical review completed. No further action required. 2022-2023   02 Historical Review
00013755
Burlington Breakwater North (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00013756
Burlington Breakwater South (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00013769
Burlington Bay Main Light (Guano Cleanup inside the Burlington Canal Lighthouse)
Remediation / risk management completed. No further action required. 2006-2007 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00013812
Fifty Mile Point Sector - Unassessed
Historical review not required. 2012-2013   01 Identify Suspect Sites
00013828
Grimsby Breakwater (No Contamination Identified)
Historical review not required. 2009-2010   01 Identify Suspect Sites
00015137
Hamilton Emergency
Historical review not required. 2014-2015   01 Identify Suspect Sites
00015186
Burlington Small Craft Harbours Office (No Contamination Identified)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00015187
Canadian Centre for Inland Waters (CCIW) - Unasses
Historical review completed. No further action required. 2021-2022   02 Historical Review
00016614
STONEY CREEK (FIFTY POINT) (No Contamination Identified)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00016615
STONEY CREEK (FIFTY POINT) (Inner Basin Water lot)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00016616
STONEY CREEK (FIFTY POINT) (Water lot north of the channel)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00024951
John Foote Armoury
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00027702
Burlington
Detailed testing completed. No further action required. 2022-2023 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
00027998
Train 92 Burlington
Long term monitoring completed. No further action required. 2022-2023   10 Long-Term Monitoring (Optional)
54117001
Burlington Lift Bridge (Parcel A)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
54118001
Burlington Lift Bridge (Parcel B)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
54118002
Former Diesel UST
Initial testing completed. No further action required. 2011-2012   03 Initial Testing Program
54118003
Soil on NE and SW sides of bridge
Detailed testing completed. No further action required. 2015-2016 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
N0075001
West Entrance at North Wall
Remediation / risk management completed. No further action required. 2011-2012 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy