Search Results

Search Results Summary
Criteria:
  • Federal Electoral District: Halifax
Select Additional Criteria...
Sort Key:Municipality (ascending)
Sites Found:153
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00000855
Terence Bay (remediation complete)
Confirmatory sampling completed. No further action required. 2008-2009 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00000857
Bettys Island - Metals, Hydrocarbons and PAH contamination
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00000957
Disposed - Ahern Avenue (302) - Building 3
Initial testing completed. No further action required. 2011-2012 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008393
LST 209 deep ocean disposal site
Initial testing completed. No further action required. 2010-2011 I Insufficient Information 03 Initial Testing Program
00008521
Willow Park (4327) - TEME North Site
Remedial action plan completed. Remediation / risk management underway. 2022-2023 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008522
Willow Park (4328) - Armoury South Site
Initial testing completed. Detailed testing underway. 2022-2023 I Insufficient Information 03 Initial Testing Program
00011532
Sable Island - AEC 2 - PHC Impact in Soil at AEB Tank Farm
Detailed testing completed. No further action required. 2010-2011 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00011535
Sable Island - AEC 9 - Metal Impact in Groundwater at AEB Compound
Detailed testing completed. No further action required. 2010-2011 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00011540
Sable Island - APEC 10 - Abandonned Landfill
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012305
Pennant Harbour - Barium and Lead in Soil
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00012985
Fort Massey Cemetery
Historical review completed. Initial testing underway. 2022-2023   02 Historical Review
00013454
Tantallon RCMP
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00017326
Ketch Harbour Remote Receiver (Unassessed)
Historical review not required. 2013-2014   01 Identify Suspect Sites
00017368
Lower Prospect (No Soil)
Historical review completed. No further action required. 2009-2010   02 Historical Review
00017433
Terence Bay Graveyard (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017455
Prospect Wharf (No Issues)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00017473
Saul Island - Metals in Soil
Initial testing completed. No further action required. 2012-2013 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017500
Terence Bay Wharf (No Soil)
Historical review completed. No further action required. 2009-2010   02 Historical Review
00017550
Halifax Lab Complex (Unassessed)
Historical review not required. 2013-2014   01 Identify Suspect Sites
00017566
Sackville River Fishway - Unassessed
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017838
LOWER PROSPECT (no land based contamination CLOSE)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00017896
PROSPECT - unassessed Divested and Closed
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017900
SAMBRO (PAHs and Metals in Sediment)
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017907
Shad Bay- (No Impacts Identified)
Historical review completed. No further action required. 2008-2009 N Not a Priority for Action 02 Historical Review
00017922
TERENCE BAY (No Hydrocarbons in Soil)
Initial testing completed. No further action required. 2012-2013   03 Initial Testing Program
00017923
TERENCE BAY (Sediment Impacts)
Initial testing completed. Detailed testing underway. 2022-2023 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017931
UPPER PROSPECT (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00025108
HMC Dockyard Halifax PFAS Sitewide
Historical review planned. 2022-2023   01 Identify Suspect Sites
00027546
Olde Barrels Cove
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
00027605 Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00027606 Initial testing completed. Detailed testing underway. 2022-2023 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00027770
Georges Island National Historic Site
Remediation / risk management completed. No further action required. 2021-2022 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
02858006
Bedford Rifle Range (706) - Office Building (B47)
Confirmatory sampling completed. No further action required. 2009-2010 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02859004
CFAD Bedford (804) - Torpedo Dye Disposal Area - East B75
Long term monitoring completed. No further action required. 2013-2014 3 Low Priority for Action 10 Long-Term Monitoring (Optional)
02859005
Wrights Cove (8601) - Former Above Ground Fuel Lines
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02859012
CFAD Bedford (813) - B157, B158, B33*
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
02859015
CFAD Bedford (816) - Ammunition Disposal Furnace (BD188)
Initial testing completed. No further action required. 2009-2010 N Not a Priority for Action 03 Initial Testing Program
02859016
CFAD Bedford (817) - Former Transformer Huts*
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
02859049
CFAD Bedford (805) - Pump House with AST (B192)
Initial testing completed. No further action required. 2009-2010 N Not a Priority for Action 03 Initial Testing Program
02859050
Wrights Cove (8608) - National Gypsum Leased property
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884001
Melville Island (5901) - Marina Storage (B1)
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884002
Melville Island (5902) - Old Ice House (B2)
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884003
Melville Island (5903) - Clubhouse (B4)
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884004
Melville Island (5904) - Marina Storage (B6)
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884005
Melville Island (5905) - Bubbler Shed (B7)
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884006
Melville Island (5906) - Workshop (B8)
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884007
Melville Island (5907) - Former Chapel Site (B10)
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884008
Melville Island (5908) - Boat Storage/Parking Lot Site
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884009
Melville Island (5909) - Marina Railway Site
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884010
Melville Island (5910) - Fuel Storage/Dispensing Area
Confirmatory sampling completed. No further action required. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02884011
Melville Island (5911) - Cradle Yard
Confirmatory sampling completed. No further action required. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02884012
Melville Island (5912) - Mooring Field
Remedial action plan completed. Remediation / risk management underway. 2022-2023 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884013
Melville Island (5913) - Causeway
Initial testing completed. No further action required. 2000-2001 N Not a Priority for Action 03 Initial Testing Program
02898001
Bedford Basin Measured Mile Beacon - PCB, PAH, and metals in sediments of Waterlot
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
02907001
Disposed Willow Pk (4321) Frmr Heating Plant (EY4 CE Supply)
Confirmatory sampling completed. No further action required. 2019-2020 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02907002
Disposed - Willow Park (4322) - Paint Shop (EY7)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02907005
Disposed - Willow Park (4325) - CE Production Centre (EY5)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02907006
Willow Park POL Stores (4323)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02913001
Water Lots (9911) - HMCS Scotian
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02914001
Halifax Armoury Building (2201) - Main Armoury Building
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02916001
RA Park (3301) - Officers Mess (RA1)
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
02916002
RA Park (3302) - Office Facility (RA2)
Long term monitoring completed. No further action required. 2022-2023 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
02918001
Willow Park (4302) - Base Maintenance Shops (WL2)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918002
Willow Park (4303) - Base Maintenance Shops (WL3)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918004
Willow Park (4305) - Base Maintenance Shop (WL9)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918005
Willow Park (4306) - Utilities Shed (WL15) & Former WL34*
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918006
Willow Park (4307) - Former Service Station (WL23)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918007
Willow Park (4308) - Outdoor POL Storage Area (Fmr WL24)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918008
Willow Park (4309) - Former Radioactive Pit (Fmr WL27)
Confirmatory sampling completed. No further action required. 2019-2020 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02918010
Willow Park (4311) - Canex (WL30)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918011
Willow Park (4312) - RCCS Garage (WL31)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918012
Willow Park (4313) - POL Shed (WL33)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918013
Willow Park (4314) - Vehicle Paint Shop (WL34)
Confirmatory sampling completed. No further action required. 2018-2019 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918014
Willow Park (4315) - Outdoor Coiled Wire Storage area
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918015
Willow Park (4316) - Former Outdoor Bulk POL Storage WL39*
Confirmatory sampling completed. No further action required. 2018-2019 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918017
Willow Park (4318) - Suspect Fmr Grease/Oil Pit (WL17)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918018
Willow Park (4319) - Vehicle Maintenance Garage WL22
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918021
Willow Park (4301) - Base Maintenance HQ & Shops (WL1)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918022
Willow Park (4320) - Salt Dome (WL36)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919001
Dockyard (1001) - CE Office and Shops (D2)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919003
Dockyard (1003) - Rectifier House (D74)
Initial testing completed. No further action required. 2000-2001 3 Low Priority for Action 03 Initial Testing Program
02919004
Dockyard (1004) - Mainguy Building (D201)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919005
Dockyard (1005) - PMQ's and Garage (D77, D78, D79 & D81)
Remediation / risk management completed. No further action required. 2014-2015 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919006
Dockyard (1006) - Pollution Control DREA (D17)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919007
Dockyard (1007) - Sheet metal & Refrig. Shops (D19)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919008
Dockyard (1008) - SRU Building Bosuns Shops (D125)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02919009
Dockyard (1009) - Base Exchange (D82)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02919010
Dockyard (1010) - Electronics Shop (D20)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919011
Dockyard (1011) - Inflammable Stores (D57)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919012
Dockyard (1012) - Base Fire Hall (D196)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02919013
Dockyard (1013) - Base Supply (D40 and D155)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919014
Dockyard (1014) - Main Base Supply (D206)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919015
Dockyard (1015) - Underwater Repair building (D53)
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919016
Dockyard (1016) - Central Heating Plant (D62)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919017
Dockyard (1017) - Outside Fitters and Machine Shop (D108)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919019
Dockyard (1019) - Packing and Preservation Bldg (D67)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919020
Dockyard (1020) - SRU Main Building (D200)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919021
Dockyard (1021) - Submarine Shelter (D170)
Initial testing completed. Detailed testing underway. 2022-2023 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02919023
Dockyard (1023) - Corrosion Prevention & Sub Squadron
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919024
Dockyard (1024) - FMG and SRU (D166)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919025
Dockyard (1025) - Shipwrights Shop (D174)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919026
Dockyard (1026) - Base Transport (D172)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02919028
Dockyard (1028) - HazMat Facility (D207)
Initial testing completed. No further action required. 2002-2003   03 Initial Testing Program
02919029
Dockyard (1029) - Rectifier Building (D47)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919030
Dockyard (1030) - Maritime Command Headquarters (D14)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919031
Dockyard (1031) - Transformers East of Building D14
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919032
Water Lots (9908) - Dockyard
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02919035
Dockyard (1035) - Former D15
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919036
Dockyard (1037) - Former D19
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919037
Dockyard (1039) - Former D95
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919038
Dockyard (1047) - Former D71
Historical review completed. No further action required. 2000-2001 N Not a Priority for Action 02 Historical Review
02919039
Dockyard (1038) - Former D88
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919040
Dockyard (1040) - Former D20
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919041
Dockyard (1033) - Former B122 and 60
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919042
Dockyard (1042) - Former D159
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919043
Dockyard (1044) - Former D127
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919044
Dockyard (1045) - Former D109
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919045
Dockyard (1046) - Former D63
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919046
Dockyard (1032) - Fomer CN Rail Line btwn parking & building
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919047
Dockyard (1034) - Former D7
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919048
Dockyard (1036) - Former D17
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919049
Dockyard (1041) - Fomer D49
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919050
Dockyard (1043) - Former D59
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02920001
Stadacona (3701) - Heating Plant (S11)
Confirmatory sampling completed. No further action required. 2019-2020 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02920002
Stadacona (3702) - Diesel Shop (S88)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02920003
Stadacona (3703) - Protestant & RC Chapel (S7)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02920004
Stadacona (3704) - Pump House (S41)
Historical review completed. No further action required. 2000-2001   02 Historical Review
02920005
Stadacona (3705) - CE Production Centre (S30)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02920007
Stadacona (3707) - CFIC Building (S89)
Confirmatory sampling completed. No further action required. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02920009
Stadacona (3708) - Gardens - rear of Bldg S52(Admiral's Res)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02920011
Stadacona (7601) - Queens Printer Bulding S93 EPRINTIT
Historical review completed. No further action required. 2001-2002 N Not a Priority for Action 02 Historical Review
02920012
Stadacona (7602) - Queens Printer Bldg S93 Trident Offices
Historical review completed. No further action required. 2001-2002 N Not a Priority for Action 02 Historical Review
02920013
Stadacona (7603) - Queens Printer Bldf S93 Tattoo Off./Stge
Historical review completed. No further action required. 2001-2002 N Not a Priority for Action 02 Historical Review
02920014
Stadacona (7604) - Queens Printer Bldg S93 Furn./Coal chute
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02921001
Disposed - South & Harvey St (3501) - Main Marcom Building
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
03002002
Windsor Park (4501) - CHP (WP62) & POL Shed (WP58)
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03002004
Windsor Park (4503) - Former Heating Plant (WP45)
Initial testing completed. No further action required. 2000-2001 N Not a Priority for Action 03 Initial Testing Program
03002005
Windsor Park (4504) - Military Police (WP92)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
03002006
Windsor Park (4505) - PMQ Barracks
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
03002007
Windsor Park (4506) - Former Gas Chamber (WP49)
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
03002008
Windsor Park - Former RCE Garage (4507)
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
03002009
Windsor Park (4508) - Former Rifle Range (WP11 & WP30)
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03002011
Windsor Park (4510) - School Property (fmr WP42)
Initial testing completed. No further action required. 2000-2001 N Not a Priority for Action 03 Initial Testing Program
03002012
Windsor Park (4509) - PMQ's (WP4, WP5 & WP9 - WP12)
Initial testing completed. No further action required. 2011-2012 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03044004
DCD School (904) - Possible Former Greenhouse
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
03044007
DCD School (907) - Fire Fighting Training Area
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03044008
DCD School (908) - Contaminated Spoil Fill Area
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03044009
DCD School (909) - Creek, Lagoon and Beach
Confirmatory sampling completed. No further action required. 2019-2020 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
03044010
DCD School (910) - Former Ordnance Demolition Area
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03044011
DCD School (911) - Construction Debris Site
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
07610122
Sable Island
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
52106002
Fergusons Cove (1501) - Sound Range Building
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
81514001
Sable Island - Hydrocarbon Impacts in West Light A
Confirmatory sampling completed. No further action required. 2021-2022 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting