Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00000923
Disposed Brit Prop No 4 Site 14 (6301) West Side of Property |
Historical review completed. No further action required. | 1999-2000 | N Not a Priority for Action | 02 Historical Review |
00000924
Disposed - Brit Prop No 4 Site 14 (6302) - Boiler House |
Historical review completed. No further action required. | 1999-2000 | 02 Historical Review | |
00001368
Atlantic Cool Climate Crop Research Centre |
Detailed testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 05 Detailed Testing Program |
00001369
Atlantic Cool Climate Crop Research Centre |
Confirmatory sampling completed. No further action required. | 2011-2012 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00001370
Atlantic Cool Climate Crop Research Centre |
Confirmatory sampling completed. No further action required. | 2011-2012 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00001371
Flings Brook - Atlantic Cool Climate Crop Research Centre |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00001410
Atlantic Cool Climate Crop Research Centre |
Remediation / risk management completed. No further action required. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00001451
Atlantic Cool Climate Crop Research Centre |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00001543
Atlantic Cool Climate Crop Research Centre |
Confirmatory sampling completed. No further action required. | 2014-2015 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00012247
Cape Spear - Dwelling/Beacon Building - Area 1 |
Confirmatory sampling completed. No further action required. | 2017-2018 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00018167
Bull Head - Minor Aid |
Initial testing completed. Detailed testing underway. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00018205
Chain Rock - Minor Aid |
Initial testing completed. No further action required. | 2021-2022 | 03 Initial Testing Program | |
00018270
Fort Amherst - Lightstation - DFRP# 34885 |
Detailed testing completed. No further action required. | 2015-2016 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00018459
North Head - Minor Aid |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
00018596
St. John's (Dockyard - Unassessed) |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00018597
St. John's (Harbour - Dockyard - Unassessed) |
Historical review not required. | 2012-2013 | 01 Identify Suspect Sites | |
00018598
St. John's (Harbour - Range Front) |
Historical review completed. Initial testing underway. | 2022-2023 | 02 Historical Review | |
00018799
Petty Harbour (North Wharf Light - Unassessed) |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00018800
Petty Harbour (S. Breakwater Light - Unassessed) |
Historical review not required. | 2009-2010 | 01 Identify Suspect Sites | |
00018824
St. John's (Southside Small Boat Basin - Parking - Unassessed) |
Historical review completed. No further action required. | 2016-2017 | 02 Historical Review | |
00018866
Bay Bulls (Warehouse) |
Detailed testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 05 Detailed Testing Program |
00018943
Petty Harbour Bait Holding Unit 9 |
Historical review not required. | 2015-2016 | 01 Identify Suspect Sites | |
00019255
Petty Harbour (Waterlot) |
Initial testing completed. Detailed testing underway. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00019256
Petty Harbour (Uplands) |
Initial testing completed. No further action required. | 2008-2009 | N Not a Priority for Action | 03 Initial Testing Program |
00019348
St. John's (Prosser's Rock - Uplands - DFRP# 55785) |
Detailed testing completed. No further action required. | 2012-2013 | N Not a Priority for Action | 06 Classify the site using the CCME National Classification System |
00019349
St. John's (Prosser's Rock - Waterlot - DFRP# 55785) |
Detailed testing completed. No further action required. | 2018-2019 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00019394
Witless Bay (SCH - DFRP# 10641) |
Detailed testing completed. No further action required. | 2015-2016 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00022927
Cape Spear - Equipment Building - Area 2 |
Confirmatory sampling completed. No further action required. | 2017-2018 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00342001
Atlantic Cool Climate Crop Research Centre |
Detailed testing completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
00342002
Atlantic Cool Climate Crop Research Centre |
Confirmatory sampling completed. No further action required. | 2011-2012 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00360001
GOCB - Governement of Canada Building - Mount Pearl, NL |
Initial testing completed. No further action required. | 2009-2010 | 03 Initial Testing Program | |
00371001
Sir Humphrey Gilbert Building - St. John's, NL |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00418001
Disposed - 20 Amherst Heights (6101) - AST at PMQ |
Historical review completed. No further action required. | 1996-1997 | N Not a Priority for Action | 02 Historical Review |
00418003
Disposed - CFS St John's (4802) - 300 Compound. |
Confirmatory sampling completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00418004
Disposed - CFS St John's (4803) - B815 |
Initial testing completed. No further action required. | 2019-2020 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00418005
Disposed - CFS St John's (4804) - 400 & 500 Compounds - PMQs |
Initial testing completed. No further action required. | 2019-2020 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00418006
Disposed -CFS St John's(4805) Lower Compound -Motor Storage |
Initial testing completed. No further action required. | 2019-2020 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
22403001
Taxation Centre |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
32039001
Disposed-British Prop.No1, Site 5(6201)Garage/waste oil tank |
Initial testing completed. No further action required. | 2019-2020 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
32039002
Disposed -British Prop.No1,Site5 (6202)Yard/fill area,tanks. |
Initial testing completed. No further action required. | 2019-2020 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
32039003
Disposed -British Prop. No1,Site 5(6203)-Former Machine Shop |
Initial testing completed. No further action required. | 2019-2020 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
32041001
Disposed-British Prop.No4,Site15 (6303)E side pop/bulk tanks |
Confirmatory sampling completed. No further action required. | 2019-2020 | N Not a Priority for Action | 09 Confirmatory Sampling and Final Reporting |
32044001
CFS St Johns (4910) - Southside Road Tank Farm |
Remediation / risk management completed. No further action required. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
32044002
CFS St Johns (5210) - Shea Height's Tank Farm |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
32046002
Pier 26 (5301) - British Property Site 7c (Cabot Boatshed) |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
32047002
Pier 27 (5302) - Brit. Prop. Site 7c |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 3 Low Priority for Action | 09 Confirmatory Sampling and Final Reporting |
55786001
John Cabot Building |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
72019001
St. John's (Base - Administration Bldg) |
Detailed testing completed. No further action required. | 2015-2016 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
72019002
St. John's (Base - Berth 28) |
Long term monitoring completed. No further action required. | 2013-2014 | 2 Medium Priority for Action | 10 Long-Term Monitoring (Optional) |
72019003
St. John's (Base - Waterlot) |
Initial testing completed. Detailed testing underway. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
72078001
Area 1 |
Remediation / risk management completed. No further action required. | 2011-2012 | I Insufficient Information | 08 Implement Remediation/Risk Management Strategy |
72078002
Area 2 |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
72078003
Area 3 |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
72078004
Area 4 |
Initial testing completed. No further action required. | 2011-2012 | 03 Initial Testing Program | |
80195001
St. John's (CN Property Storage Facility) |
Detailed testing completed. No further action required. | 2014-2015 | N Not a Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0090001
Iron Rack |
Remediation / risk management completed. No further action required. | 2015-2016 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0090002
Zone 1 & 2 Area North of Graving Dock |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
N0090003
Zone 3 - Area West of Graving Dock |
Detailed testing completed. No further action required. | 2015-2016 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0090004
Zone 4 - Area South of Graving Dock |
Detailed testing completed. No further action required. | 2008-2009 | 1 High Priority for Action | 05 Detailed Testing Program |
N0090005
Zone 5 - Former CNR Property |
Detailed testing completed. No further action required. | 2008-2009 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N0090006
Zone 6 - Area South of Waterford River |
Detailed testing completed. No further action required. | 2008-2009 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
N7068001
Northern Fuel Cache Site - Argentia |
Initial testing completed. No further action required. | 2017-2018 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |