Search Results Summary
Criteria:
  • Reason for Federal Involvement: National Park of Canada
Select Additional Criteria...
Sort Key:Municipality (ascending)
Sites Found:295
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00000910
Gilman River
Confirmatory sampling completed. No further action required. 2021-2022 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00002330
Decca station
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00002331
Maintenance Garage Compound
Detailed testing completed. No further action required. 2013-2014 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00002336
Pine Lake Dump Site Barrel Cache
Remediation / risk management completed. No further action required. 2013-2014 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00002338
Warden's Operation Building
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00002363
Southwest Brook at Terra Nova National Park (CHS)
Detailed testing completed. No further action required. 2015-2016 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00008322
Former site of the Long Beach Visitor Information Centre
Detailed testing completed. Remedial action plan under development. 2022-2023 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00008323
Abandonned bridge, former Combers Beach access road
Detailed testing completed. No further action required. 2022-2023 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00008324
Sunwapta Warden Station
Confirmatory sampling completed. No further action required. 2013-2014 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008325
Maligne Lake Warden Station
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008326
Athabasca Falls Warden Station
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008328
Fort Conger Historic Site
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00012243
Louisbourg (Metal Impacted Soil- Lighthouse Area)
Remediation / risk management completed. No further action required. 2012-2013 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00012826
Pukaskwa National Park, Administration Building Gas Shed
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00012829
Lake Louise Service Station
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012830
Bath Creek Tie Camp
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012831
Lake Louise CPR Power House
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012832
Redstreak Sinkhole
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012833
Dolly Varden Pit
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012834
16 Mile Pit
Confirmatory sampling completed. No further action required. 2013-2014 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00012835
Abandoned barrels, with no known affiliation
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012836
Barrels at Active Research Camp or Cabin, known affiliation
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012837
Barrels at Inactive/Abandonned Cabin/Settlement, known affiliation
Detailed testing completed. No further action required. 2013-2014 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00012838
Barrels in active fuel caches, known affiliation
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012839
Empty barrels sites
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012840
K17 Nestor 2 living quarters building D
Detailed testing completed. No further action required. 2020-2021 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00012843
Wastes other than barrels
Historical review completed. No further action required. 2013-2014   02 Historical Review
00012844
Snow Creek
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012846
Hawk Creek
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012847
Grey Owl Marina
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012848
Waskesiu Lawn Bowling Green
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012849
Bear Trap Landfill
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
00012850
Former Site of the Port Renfrew Motel
Confirmatory sampling completed. No further action required. 2013-2014 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00012851
Roland Bay: Abandoned oil well site (Well L-41)
Detailed testing completed. No further action required. 2020-2021 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00012852
Spring River: abandoned oil well site (Well N-58)
Detailed testing completed. No further action required. 2020-2021 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00012853
Sheep Creek: placer gold mine
Detailed testing completed. No further action required. 2020-2021 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00012854
Castel Bay: abandoned oil well site (Well C-68)
Detailed testing completed. No further action required. 2017-2018 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00012855
Kusrhaak: abandoned oil well site (Well D-16)
Detailed testing completed. No further action required. 2017-2018 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00012856
Anthracite Townsite
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00012857
Bankhead Power Station
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012858
Parks Canada Landfill
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012859
Minnewanka Power Plant
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012860
Old Banff Industrial Block
Confirmatory sampling completed. No further action required. 2013-2014 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00012861
Public Library Site
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00012863
Former Forestry Camp
Initial testing completed. Detailed testing underway. 2022-2023 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012864
Monarch Campground
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00012865
Amiskwi Mill Site
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013376
Castle Junction Household Dump
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013777
Cedar Island - Close to the navigational aid
Initial testing completed. No further action required. 2021-2022 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00018840
Terra Nova Park - Bungalow # 11 - Unassessed
Historical review completed. No further action required. 2016-2017   02 Historical Review
00021566
Newport
Initial testing completed. No further action required. 2008-2009 N Not a Priority for Action 03 Initial Testing Program
00022198
Stalag Salt Storage
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00022200
Garden River Public Works Yard
Initial testing completed. No further action required. 2021-2022 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022201
Fifth Meridian Market AST
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022202
Garden River Trading (Charlie Rose) AST
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022203
Old Parks Compound
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022809
Vermillion Warden Station
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00022827
Garden River Landfill
Initial testing completed. No further action required. 2021-2022 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022828
Northlands School Historic AST
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022829
Garden River Sewage Lagoon
Historical review completed. No further action required. 2021-2022   02 Historical Review
00022830
Former Septic Tile Field
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022975
Louisbourg (Metals/PAHs in Soil - Former Coal Ash Area)
Remediation / risk management completed. No further action required. 2012-2013 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00023442
Gilman Glacier Camp
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023445
Church Historic AST
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023446
Swanson Camp 6 Sawmill at Sweetgrass Landing
Historical review completed. No further action required. 2013-2014   02 Historical Review
00023447
Swanson's Sawmill Camp # 3 Peace River
Historical review completed. No further action required. 2013-2014   02 Historical Review
00023448
Northern Transport Company Sawmill near Sawmill Island
Historical review completed. No further action required. 2013-2014   02 Historical Review
00023449
Sweetgrass Station Abattoir
Historical review completed. No further action required. 2013-2014   02 Historical Review
00023455
Northwest Astotin Lake
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023456
Mount Agassiz
Confirmatory sampling completed. No further action required. 2015-2016 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00023457
Active Pass
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023458
Major Shore Light
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023459
Former Shed and Boat House
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023460
Abandoned Light Station
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023461
Saturna Island Fuel Shed
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023462
Saturna Island Light Tower
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023463
Saturna Island Dump
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023464
Saturna Island Service Pit
Remedial action plan completed. Remediation / risk management underway. 2022-2023 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00023467
Oil trap, operational centre's garage at Forillon National Park
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00023472
Torngat Mountains NP, Upper Kangalaksiorvik Lake
Remediation / risk management completed. No further action required. 2013-2014 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00023478
Brackley Pumphouse
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023481
Jasper National Park - Municipal Sewage Lagoon
Initial testing completed. Detailed testing underway. 2022-2023 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023482
Brewster Chalet
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00023483
Airport Fuel Tank
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00023974
Ingonish Beach Detachment
Historical review completed. No further action required. 2013-2014   02 Historical Review
00024052
Belza Farmhouse
Confirmatory sampling completed. No further action required. 2013-2014 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00024128
Illecillewaet Campground : Campsite # 30
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00024292
Sandy Pond Day-Use Area
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024297
Alpine Lakes
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
00024298
Former Wildlife Park
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024299
Russell Island Homestead
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024300
Former asphalt plant
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024304
Keltic Incinerator Site
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024309
Struggle Site
Initial testing completed. No further action required. 2018-2019 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024310
Tablesands site
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024573
Former Headquarters Service Station Site
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024575
Haslam Pit Pumphouse Former UST
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024576
Sandy Pond Boardwalk
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024581
Cape Gulch, Shoal Cove and Tallek Arm
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024582
Parmenter Island
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024586
Lac-à-la-Pêche Sawmill
Detailed testing completed. Remediation / risk management planned. 2022-2023 2 Medium Priority for Action 05 Detailed Testing Program
00024587
Ile des Cinq Point
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024588
Wabenaki refuge generator and former storage tank
Historical review completed. Initial testing underway. 2022-2023   02 Historical Review
00024589
Coude Lake Forest Camp
Detailed testing completed. Remediation / risk management planned. 2022-2023 2 Medium Priority for Action 05 Detailed Testing Program
00024590
Waber Lake Forest Camp
Historical review completed. Initial testing underway. 2022-2023   02 Historical Review
00024591
Wapizagonke-North camping storage tank
Historical review completed. Initial testing underway. 2022-2023   02 Historical Review
00024592
Edouard Lake Storage Tank
Historical review completed. Initial testing underway. 2022-2023   02 Historical Review
00024594
Rivière à la Pêche garage
Historical review completed. Initial testing underway. 2022-2023   02 Historical Review
00024667
Harriet Harbour
Remedial action plan completed. Remediation / risk management underway. 2022-2023 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00024668
Dixon Residence
Detailed testing completed. No further action required. 2013-2014 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024676
Harbour of Cap-des-Rosiers
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024680
Walker Acquisition
Remedial action plan completed. Remediation / risk management underway. 2022-2023 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00025558
Creosote Treated Wood - Bennett Brook
Initial testing completed. No further action required. 2014-2015 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025561
Martin's Point Landfill
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00025562
Slant's River Landfill
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025566
Anthracite Mine Site
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00025780
2501 Shingle Bay Road
Detailed testing completed. Remedial action plan under development. 2022-2023 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00025781
Wasagaming Drive Commercial Property
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00025782
Donald Mine Site
Detailed testing completed. Remediation / risk management planned. 2022-2023 1 High Priority for Action 05 Detailed Testing Program
00025786
Cap-des-Rosiers Harbour Parking and Land
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00025787
Grande-Grave Harbour Land
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
00025807
2 Landing Road, mallorytown (dock and parking lot)
Initial testing completed. No further action required. 2013-2014   03 Initial Testing Program
00025822
Jasper NP Abandoned Oil Tank
Confirmatory sampling completed. No further action required. 2015-2016 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00026392
Former Gas/Diesel Fuelling Station - Administration Compound
Historical review planned. 2022-2023   01 Identify Suspect Sites
00026433
Pukaskwa National Park Borrow Pit
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00026456
Jasper National Park Fish Hatchery
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00026478
Yoho Brothers Gas Station
Detailed testing completed. Remedial action plan under development. 2022-2023 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00026481
Banff Airstrip Site
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00027546
Olde Barrels Cove
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
00027551
Point Pelee Marsh
Detailed testing completed. Remediation / risk management planned. 2022-2023 1 High Priority for Action 05 Detailed Testing Program
00027552
Boulder Creek Operations Center
Historical review planned. 2022-2023   01 Identify Suspect Sites
00027609
Radium Hot Springs Heating Fuel Tanks
Historical review planned. 2022-2023   01 Identify Suspect Sites
00027618
Cap-des-Rosiers Harbour South Jetty
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00027660
Kenow Fire Impacted Areas
Remedial action plan completed. Remediation / risk management underway. 2022-2023 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
00027779
Yoho Ranch
Confirmatory sampling completed. No further action required. 2021-2022 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00027859
Point Wolfe River at Fundy National Park
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00027882
Pukaskwa River at Pukaskwa National Park
Detailed testing completed. Remedial action plan under development. 2022-2023 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00027892
Rouge River at Scarborough
Detailed testing completed. Remedial action plan under development. 2022-2023 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00027925
Little Rouge Creek at Scarborough
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00027986
Clark Lake
Historical review planned. 2022-2023   01 Identify Suspect Sites
01187002
Operations Compound
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02087001
Cavendish Maintenance Compound
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
02087002
Dalvay Compound - Chemical Storage Building
Confirmatory sampling completed. No further action required. 2016-2017 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02087003
Green Gables
Historical review not required. 2013-2014   01 Identify Suspect Sites
02538001
Compound
Initial testing completed. Detailed testing underway. 2022-2023 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03842004
Ingonish Compound
Confirmatory sampling completed. No further action required. 2017-2018 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
03842005
Cheticamp Compound
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03842008
Broad Cove Incinerator Site
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03842010
Cheticamp Compound Fuel Spill Site
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
03863001
Potato Disinfection Pit - Former AGCAN Research Station
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
10667001
Camp Henry
Remediation / risk management completed. No further action required. 2013-2014 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
10667002
Maintenance Compound
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
12897001
Grey Owl Waste Disposal Ground
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
12897002
Maintenance Compound Garage, Former UST Site
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
12897004
Townsite Washroom Former UST
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
12897005
Clear Lake Golf Course
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
12897006
Boreal Island Construction Site
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
12897007
Former small landfills
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
12897008
Golf course maintenance yard former UST
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
13478002
Zahurski's Point Oil Dump Pit
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
13567001
Fort Walsh NHS Landfill
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
14567001
Commercial Property at Block 5 Lot 8, Waskesiu Townsite
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
14567002
Lobstick Maintenance Yard
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
14567003
Main Compound Fuel Storage
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
14567004
Narrows Campground Generator Site
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
14567005
Overflow Campground
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
14567006
Waskesiu Golf Course
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
14567007
Camp 18 Gravel Pit
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
14567008
Administration Parking Lot
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
14567009
Salt Shed
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
14567010
Waskesiu Breakwater
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 05 Detailed Testing Program
15404001
Rimrock Dump
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404002
Stephen Pit
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404004
Fairview Pit
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404005
Niblock Pit
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
15404008
Minnewanka Landfill
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
15404011
Carrot Creek Landfillsite
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
15404012
Cascade Borrow Pit
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404013
Cascade Landfill
Detailed testing completed. Remedial action plan under development. 2022-2023 1 High Priority for Action 06 Classify the site using the CCME National Classification System
15404014
Castle Junction Tradewaste Site
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404015
Golf Course Dump
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404016
Old Lake Louise Lumber Mill
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404022
Bankhead
Initial testing completed. Detailed testing underway. 2022-2023 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404031
Lake Louise Compound
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
15404032
Saskatchewan Crossing Warden Station
Confirmatory sampling completed. No further action required. 2013-2014 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
15404034
Lake Louise Overflow
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404037
Mosquito Creek
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404040
Silverhorn
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404044
Forty Mile Creek Landfill
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
15404045
Bow River Backwater
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404047
Bow Summit Repeater Tower
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404055
Old Lake Louise Compound
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404058
Old Government Horse Corral
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
15404060
Fairview Lagoon
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404061
Mount Coleman Rest Area
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404062
Bankhead Railsiding
Remedial action plan completed. Remediation / risk management underway. 2022-2023 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
15404067
Banff Golf Course Dump
Initial testing completed. No further action required. 2021-2022 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404069
Red Earth Creek Sawmill
Historical review completed. No further action required. 2013-2014   02 Historical Review
15404070
Fairholme Ranch
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15404072
Banff Springs Golf Course
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
15412001
A1 Waste Transfer Station
Remedial action plan completed. Remediation / risk management underway. 2022-2023 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
15412002
A2 Maligne Lake Dump
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412003
A3 Km 29.7 Maligne Lake Road
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412004
A4 Maligne Lake Road Borrow Pit
Historical review completed. No further action required. 2013-2014   02 Historical Review
15412005
A5 Km 35.0 Maligne Lake Road Borrow Pit
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412006
A6 Km 39.1 Maligne Lake Road Borrow Pit
Initial testing completed. No further action required. 2013-2014 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412007
A7 Pyramid Bench
Remedial action plan completed. Remediation / risk management underway. 2022-2023 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
15412008
A8 Pocahontas/Hwy #16 Dump/Fiddle Area Dump
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412009
A9 Km 1.6/2.0 Miette Road - Old Pocahontas Dump
Historical review completed. Initial testing underway. 2022-2023   02 Historical Review
15412010
A10 Km 10.5 Miette Hot Springs Road Borrow Pit
Historical review completed. No further action required. 2013-2014   02 Historical Review
15412011
A11 Km 14.1 Miette Hot Springs Road Storage
Initial testing completed. No further action required. 2013-2014 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412012
A13 Sleepy Hollow Road / Waste Disposal Site
Confirmatory sampling completed. No further action required. 2018-2019 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
15412013
A14 Woodlot Landfill
Remedial action plan completed. Remediation / risk management underway. 2022-2023 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
15412014
A15 Sleepy Hollow Work Camp Site
Initial testing completed. No further action required. 2013-2014 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412015
B1 Trade Waste Pit
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
15412016
C1 JNP Maintenance Compound
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
15412017
C2 JNP Tangle Creek Compound
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
15412018
Jasper National Park, C3 Townsite Block S Site
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
15412019
C4 Miette Sewage Plant Site (Old Maintenance Area)
Initial testing completed. No further action required. 2017-2018 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412066
Sunwapta Borrow Pit
Initial testing completed. No further action required. 2013-2014 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412067
X1 Beauvert Lake Dump Site
Initial testing completed. No further action required. 2013-2014 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412068
X2 93A - small pit
Initial testing completed. No further action required. 2013-2014 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412069
X3 Highway 93 Beauty Creek Borrow Pit
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
15412070
X4 Wapiti Winter Camp
Initial testing completed. No further action required. 2013-2014 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412071
X5 Ranger Creek
Historical review not required. 2017-2018   01 Identify Suspect Sites
15412072
X6 Maligne Lake
Historical review completed. No further action required. 2013-2014   02 Historical Review
15412073
X7 Pocahontas Mine (pits)
Historical review completed. No further action required. 2013-2014   02 Historical Review
15412074
X10 Highway 16 West, Km 20.6
Historical review completed. No further action required. 2013-2014   02 Historical Review
15412075
Kerkeslin Borrow Pit
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412077
X8 Miette Rd. Km 15
Initial testing completed. No further action required. 2013-2014 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15412078
X9 Highway 93 Km 15
Historical review completed. No further action required. 2013-2014   02 Historical Review
15412079
Stormwater Outfall
Remedial action plan completed. Remediation / risk management underway. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
15412080
Snow Dump
Remedial action plan completed. Remediation / risk management underway. 2022-2023 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
15457001
Parkway Landfill
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15457002
Old Parks Canada Maintenance Compound/Trade Waste Landfill
Confirmatory sampling completed. No further action required. 2013-2014 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
15457003
North Camp Landfill
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15457004
South Entrance Landfill
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15457005
Recreational Area Sewage Lagoon
Detailed testing completed. No further action required. 2021-2022 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
15457006
Administration Area Sewage Lagoon
Detailed testing completed. No further action required. 2021-2022 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
15457008
Recreational Landfill
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15457009
Garage outflow pipe
Detailed testing completed. No further action required. 2013-2014 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
15457011
Golf Course
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15457012
Gas/Diesel Filling Station
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15457013
Abatoir Landfill
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
15841002
Garden River Old Dump
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
16103002
Redstreak Pit
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
16103004
Marble Canyon
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
16103005
Kootenay Crossing
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
16103008
Four Mile Pit
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
16103009
Vermillion Pit
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
17800005
Sewage Lagoon
Initial testing completed. No further action required. 2013-2014   03 Initial Testing Program
17800007
Old Woodlot
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
17800008
McLean's Point
Confirmatory sampling completed. Long term monitoring underway. 2022-2023 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
17800009
Truck Compound
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
17800016
Cape Beal HFDF Site
Detailed testing completed. Remedial action plan under development. 2022-2023 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
18730006
Boulder Creek Compound
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18730007
Ottertail Pit
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18730008
Lumber Yard Dump #3
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18730009
Field Dumpsite #1& #2
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18730010
Field Firehall
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18730014
Boulder Creek Old Special Waste Storage
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18730015
West Gate
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18730016
Emerald Intersection
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
18730017
Hoodoo Creek Campground
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18730018
Old Leanchoil Warden Station
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18752001
Rogers Pass Maintenance Compound
Remediation / risk management completed. Confirmatory sampling underway. 2022-2023 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
18752002
Mountain Creek
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
18752003
East Gate Complex
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
18752004
Hermit Pit-Salt Storage
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18752005
Beaver Pit - Glacier Industrial Trade Waste Pit
Detailed testing completed. Remedial action plan under development. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
18752006
One Mile Sites
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
18752007
Old SRAWS Site
Initial testing completed. Detailed testing underway. 2022-2023   03 Initial Testing Program
18753001
Mt. Fidelity
Confirmatory sampling completed. No further action required. 2017-2018 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
20106003
Haines Junction Research Landfill
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
20106004
Wardens Operational Center
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
20106005
Garage
Remedial action plan completed. Remediation / risk management underway. 2022-2023 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
22623002
Glenburnie Salt Shed
Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
56482014
Lake Hazen Camp (site 14)
Confirmatory sampling completed. No further action required. 2013-2014 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
56482015
Ward Hunt Island (site 15)
Confirmatory sampling completed. No further action required. 2019-2020 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
56482016
Tanquary Fiord old camp (site 17)
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
56482017
Tanquary fiord, Runway (site 17A)
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
56482018
Tanquary fiord, New Camp
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
56488001
Park Works Compound
Confirmatory sampling completed. No further action required. 2013-2014 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
56488002
Trade Waste Pit
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
56488003
Prince of Wales Hotel
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
56488006
Former Fuel Storage Site (UST)
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
56491004
030 Copper Island
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
56491005
Beban Camp
Confirmatory sampling completed. No further action required. 2013-2014 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
56491006
032 Lucky Seven
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
56491007
Finger Point
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
56491008
073 George Island
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
56491009
016 Apex Mountain
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
56491010
029 Skincuttle Island
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
56511002
DEW Line Access Trail
Initial testing completed. No further action required. 2013-2014 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
56525067
K83 Campbell's cabin