Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00002442
Soil contamination with lead containing paint at former lightning shed |
Initial testing completed. No further action required. | 2010-2011 | 03 Initial Testing Program | |
00002586
Fill material |
Initial testing completed. No further action required. | 2010-2011 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00002587
Staining in APU Building |
Initial testing completed. No further action required. | 2010-2011 | 03 Initial Testing Program | |
00003795
138 - Chippewas of Georgina Island - 06198 - CHIPPEWAS OF GEORGINA ISLAND FIRST NATION / 0402400405 |
Historical review not required. | 2013-2014 | 01 Identify Suspect Sites | |
00007643
138 - Chippewas of Georgina Island - 06198 - CHIPPEWAS OF GEORGINA ISLAND FIRST NATION / 0404311809 |
Initial testing completed. No further action required. | 2012-2013 | 03 Initial Testing Program | |
00008383
Mosley Street Armoury |
Initial testing completed. No further action required. | 2014-2015 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00008574
Aurora Armoury |
Initial testing completed. No further action required. | 2018-2019 | 3 Low Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00012660
KESWICK (JERSEY RIVER) ( South Breakwater) |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
00012731
Pefferlaw River (Waterlot) |
Initial testing completed. No further action required. | 2014-2015 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00015122
Gibraltar Point - Unassessed |
Historical review completed. No further action required. | 2023-2024 | 02 Historical Review | |
00015237
Sturgeon River Lamprey Barrier Dam - Unassessed |
Historical review completed. No further action required. | 2012-2013 | 02 Historical Review | |
00016553
BLACK RIVER (MOSSINGTON) (No Contamination Identified) |
Initial testing completed. No further action required. | 2017-2018 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022952
KESWICK (JERSEY RIVER)(Marina waterlot) |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00022953
KESWICK (JERSEY RIVER) (Entrance Channel) |
Initial testing completed. No further action required. | 2013-2014 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00026079
PIN 614048 AREA C- House |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00026080
PIN 614127 B - Porch and Barn |
Initial testing completed. Detailed testing underway. | 2023-2024 | 03 Initial Testing Program | |
00027916
Black River at Sutton |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
00027924
Rouge River near Markham |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 2 Medium Priority for Action | 06 Classify the site using the CCME National Classification System |
09820002
PIN 614053.2 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820003
PIN 614075 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820004
PIN 614076 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820006
PIN 614104.2 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820007
PIN 614106 |
Confirmatory sampling completed. Long term monitoring underway. | 2023-2024 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09820009
PIN 614120 |
Remediation / risk management completed. Confirmatory sampling underway. | 2023-2024 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
09820011
PIN 614132 |
Detailed testing completed. Remedial action plan under development. | 2023-2024 | 3 Low Priority for Action | 06 Classify the site using the CCME National Classification System |
09820032
PIN 614070.1 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820035
PIN 614142 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820044
PIN 614019 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820051
PIN 614020 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09820057
PIN 614042 |
Remedial action plan completed. Remediation / risk management underway. | 2023-2024 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |