Site 70069014 - Eureka - North Airstrip Apron

  • Status

    Confirmatory sampling completed. Long term monitoring underway.
  • Site Status

    Active
  • Classification

    Medium Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    Other Canada Lands
  • Property Type

    Canada Lands

Site Location

Locate this site on map
  • Latitude, Longitude

    79.997711, -85.840627
  • Municipality

    Qikiqtaaluk, Unorganized, NU
  • Federal Electoral District

    Nunavut

Site Management Strategy

  • Periodic Monitoring
  • Additional assessment

Contaminant Details

Contamination Estimate

  • Cubic Meters

    1,755

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Soil
BTEXs (benzene, toluene, ethylbenzene, and xylene) Soil
PAHs (polycyclic aromatic hydrocarbon) Soil

Action Plan

Highest step comlpeted 4, On-going Step 5. The site requires further assessment. There is currently no funding source and access to the site is very limited as CFS Eureka is o nly open for 30 days per year. (KS April 2015) (April 2016; JM) No change in status. Site not accessed in 2015/16. (April 201 7; KS) Plan is for risk management monitoring for 17/18. (April 2018; KS) Funding not available for 18/19.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km0
5 km0
10 km0
25 km0
50 km0

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $39,668.94
  • Remediation

    $13,670.00

FCSAP Expenditures

  • Assessment

    $19,629.04
  • Remediation

    $8,670.00

Financial/Annual Information

2021-2022

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2019-2020

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2018-2019

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2017-2018

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $8,670.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $8,670.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2016-2017

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2015-2016

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2014-2015

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2013-2014

  • Reporting Organization

    National Defence
  • Internal Identifier

    0138-C010
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2012-2013

  • Reporting Organization

    National Defence
  • Internal Identifier

    S-10527
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $15,132.63
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2011-2012

  • Reporting Organization

    National Defence
  • Internal Identifier

    S-10527
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2010-2011

  • Reporting Organization

    National Defence
  • Internal Identifier

    S10527
  • Highest Step Completed

    06 Reclassify the Site Using CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    National Defence
  • Internal Identifier

    S10527
  • Highest Step Completed

    06 Reclassify the Site Using CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2008-2009

  • Reporting Organization

    National Defence
  • Internal Identifier

    S10527
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $5,000.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    National Defence
  • Internal Identifier

    S10527
  • Highest Step Completed

    07 Develop Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $18,951.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $15,160.80
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    National Defence
  • Internal Identifier

    S10527
  • Highest Step Completed

    04 Classify Contaminated Site Using the CCME National Classification System
  • Total Assessment Expenditure

    $5,585.31
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $4,468.24
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2005-2006

  • Reporting Organization

    National Defence
  • Internal Identifier

    S10527
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No