Site 32025001 - GOCB - Moose Factory Island
-
Status
Remediation / risk management completed. No further action required. -
Site Status
Closed -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal activities -
Property Type
Non-Federal (Private Sector)
Site Location
-
Latitude, Longitude
51.251687, -80.613398 -
Municipality
Cochrane, Unorganized, North Part, ON -
Federal Electoral District
Timmins--James Bay
Site Management Strategy
- Other
Contaminant Details
Contamination Estimate
-
Cubic Meters
10
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
Metal, metalloid, and organometallic | Soil |
Action Plan
Remediation completed. No more action required as property is to be sold as in in 2012.
Additional Information
Metal (antimony, nickel and zinc) impacted soils in an area 20m2 to a depth of 0.2m on the northeast corner of the site. Estimated volume is 10m3. Has been remediated.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 577 |
5 km | 2,799 |
10 km | 3,003 |
25 km | 3,714 |
50 km | 3,714 |
Financial/Annual Information
2013-2014
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2012-2013
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Public Services and Procurement CanadaInternal Identifier
Ontario 32025001Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version: