Site 00025805 - South side of Chambly canal: lock 1 to railroad bridge
-
Status
Initial testing completed. Detailed testing underway. -
Site Status
Active -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 06688)
Site Location
-
Latitude, Longitude
45.444411, -73.276675 -
Municipality
Chambly, QC -
Federal Electoral District
Beloeil--Chambly
Site Management Strategy
- Remediation
- Assessment
- Risk Management
Contaminant Details
Contamination Estimate
-
Cubic Meters
1,360 -
Hectares
2
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Surface soil |
PAHs (polycyclic aromatic hydrocarbon) | Surface soil |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Surface soil |
Metal, metalloid, and organometallic | Soil |
Other inorganics | Groundwater |
Other organics | Surface soil |
Action Plan
The site is under assessment steps.
Additional Information
The site is in a national historic site of Canada.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 4,220 |
5 km | 44,896 |
10 km | 107,098 |
25 km | 1,284,236 |
50 km | 4,337,805 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$39,304.00
FCSAP Expenditures
-
Assessment
$28,168.00
Financial/Annual Information
2020-2021
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
04 Classify Contaminated Site Using the CCME National Classification SystemTotal Assessment Expenditure
$39,304.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$28,168.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
Parks Canada AgencyInternal Identifier
AECCHAT003Highest Step Completed
02 Historical ReviewTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed