Appendix H: Audit Program for the Post-Installation Stage
Stage: 7. Post-installation Stage
Objective: 7.A To establish that the system operates in accordance with
the design objectives and other measurement criteria,
and project costs/benifits have been achieved.
Criterion: 7.A.1 A formal post-installation review has been undertaken and
the results reported to management.
Audit Step: 7.A.1.1 Has a Post-Installation report or
similar document been prepared?
Audit Step: 7.A.1.2 Verify that it contains the following:
- documentation of the system's
actual achievements
- comparison of those achievements
against the original objectives
- recommendations for improvements
- actual resource use, compared to
the original plan, with reasons for
variance
- actual milestones achieved,
compared to the original plan, with
reasons for variance
- updated cost/benefit analysis
Audit Step: 7.A.1.3 Verify actual resource use in source
documents.
Audit Step: 7.A.1.4 Verify the updated cost/benefit
analysis against source documents.
Audit Step: 7.A.1.5 Determine that the updated
cost/benefit analysis has taken into
consideration the human resource
impact requirements.