FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
00025000
MAT-2 PMQ Heating Oil USTs
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00025004
MAT-6 Sewage Treatment Facility
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00025005
MAT-7 Former Septic Field
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00025006
MAT-8 Antenna Towers and Arrays
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00025007
MAT-9 Former building complex
Detailed testing completed. No further action required. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00025009
MAT-11 Main Operations Complex
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
11022001
Roundel EOD Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
11022032
Borden Landfill
Detailed testing completed. Remediation / risk management planned. 2023-2024 3 Low Priority for Action 05 Detailed Testing Program
11022035
Castle EOD Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
11022038
Amiens Rifle Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
11022039
Fire Fighting Training Area #1
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
11022042
Vimy Rifle Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
11022043
Mons Rifle Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
11022068
Petroleum Contaminated Soil Pile
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
11022121
Foxfield Battle Assault Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00008490
Alexandra Sm. Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
02561001
Granville Range-Granville Ferry
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
06872038
Sector OP-1 to OP-6
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02267011
CFS Barrington
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00008536
Gloucester Small Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
06875001
Camp Bouchard, Ex Ammo Dump
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
04089038
Blissville Airport
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00008538
CF18 Crash Site on AB Gov Land
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
15680002
42 Radar Squadron (Cold Lake)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
00008408
CFB Gagetown
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008409
Wellington Anti-Tank Range
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00008476
Amiens Small Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008477
Reichwald Sm. Arms Rifle Rng
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008478
Somme Small Arms Rifle Range
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008479
Flanders Sm. Arms Rifle Range
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008487
Vimy Small Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008488
Batoche Sm. Arms Rifle Rng
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024925
Building TA-1
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
04089007
Mons Small Arms Rifle Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
04089010
Shirley Rd. Dump
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
04089028
Static Range Impact Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00008480
Ardennes Sm. Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008481
Old Vimy Sm. Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008482
Old Amiens Small Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008483
Old Mons Small Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008485
Old Reichwald SmArms Rifle Rng
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008486
Dieppe Small Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00001005
Mewata Armoury
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008358
General Sir Arthur Currie Bldg
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024959
CAM-MAIN Hangar Legacy Hydrocarbon Plume
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
70070001
CAM-M LRR (Cambridge Bay, NU - Landfill)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
C7014001
DEW-Line - CAM-M Cambridge Bay
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
03660002
CFS Sydney- FPS Radar Site (1701)- Scrap Stg Compound
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03660004
CFS Sydney - FPS Radar Site (1703) - Former PCB Storage
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03662001
Sydney Rifle Range (3801) - Rifle Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
03690001
Glace Bay Armoury (1801) - Armoury (B1)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03708001
Victoria Park (4101) - Headquarters Building (B8)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03708003
Victoria Park (4103) - Heating Plant (B11)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00008338
Block 7741 Military Training Area
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
10885001
HMCS Prevost Marina
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008499
Cedar Springs Rifle Range & Danger Area
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
03144001
Debert Rifle Range (1201) - Rifle/Pistol Range
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00000996
Aircraft Fuel Dumping Ground
Detailed testing completed. Remediation / risk management planned. 2023-2024 3 Low Priority for Action 05 Detailed Testing Program
00024849
4 Wing Fire Hall, Blding 4
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024850
Transport Office (former EME shop), Blding 5
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024981
4 Wg Canex Gas Station
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
15684001
4 AES Runway Training Pad / ATCO Pipeline
Detailed testing completed. No further action required. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
15684036
Landfill Site 6
Initial testing completed. No further action required. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15684037
Landfill Site 8 (A/C Burial Site)
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15684038
Landfill Site 1
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
15684039
Central Heating Plant Investigation
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15684015
Small Arms Range
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15684017
Building 83
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
15684018
Skeet Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
15684020
TAC POL Farm
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
15684026
4 Wing Landfarm
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
15684030
Auto Hobby Club B168
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15684008
Base POL Farm
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
15684009
Firefighter Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
15684010
Old Imperial Oil Service Station
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
15684011
Building 111
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
15684012
Building 170
Initial testing completed. No further action required. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15684013
Dry Cleaning
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008644
COL-26 Colwood Section of Wilfert Rd near F-Jetty
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008645
COL-27 Colwood Laydown Area near Bldg 205
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00008649
COL-30 Colwood Joe’s Creek East of Wilfert Rd
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008650
COL-31 Colwood Bldg 65
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00008653
COL-34 Colwood Aggregate Storage Yard (Active Site)
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008655
COL-36 Colwood Helicopter Pad and Parking Lot
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
17451008
BP-1 Belmont Park - Former Canex Gas Station at Building 15
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
17451013
COL 4 Colwood Fire Fighting Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
17451023
BP-1b Belmont Park - Former Canex Gas Station at Building 17
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
17452014
RRU-3 Royal Roads University Boathouse Area
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008656
COL-37 Colwood Smart Island
Detailed testing completed. No further action required. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008657
COL-38 Colwood McCarthy Island
Detailed testing completed. No further action required. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008659
COL-40 Colwood North Western Bank of Dunn's Nook
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
17451002
COL-1B-1L Colwood Supply Area Bunkers 44, 45 & 48
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
17451004
COL-14 Colwood Supply Area Bldg 93 & 112
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
17451005
COL-16 Colwood Supply Area Building 66A
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00024844
B163 - Fire Hall
Initial testing completed. Detailed testing underway. 2023-2024 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024921
Argus Waste Drop Zone
Remediation / risk management completed. No further action required. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00024923
19 Wing Hangar 7
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025015
19 Wing PFAS Sitewide
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
00025073
19 Wing EOD Site
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025086
19 Wing Heritage Park
Confirmatory sampling completed. No further action required. 2023-2024 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
17970001
High Speed Refueling Compound
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
17970003
Refuelling Vehicle Compound near B-100
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
17970012
Comox FFTA (non-PFAS)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
17970014
Upper Tankfarm
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
17966001
Seal Bay Transmitter Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024903
Fire Fighting Training Area
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
12448002
Incinerator Site
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00000941
Suffield Experimental Proving Ground (EPG) Project
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008332
CPR Lakes
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008340
DRDC Transport Facility Site (CFB Suffield site)
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008407
Dunnage Pit
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00008501
DRDC Pile at Landfarm
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008517
Range Control Trenches
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
14976058
DRES Cameron Center
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
14976062
Serial 19 Trenches (WAD Site B)
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
14976042
490 Site - 604 Layout (EPG) Coyote & Rabbit Rds
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
14976044
DRES 155mm Gun Tower - EPG
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
14976054
DRES 490 Inner Compound Building area
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
14976055
DRES Chemical Mixing Dumpsite
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
14976056
DRES Willis Center Trench
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
14976057
DRES Range and Accuracy Layout
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
14976006
Cdn Abandoned Landfill Site (CAL Site)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
14976008
DRES Low Radioactive Waste Burial Site - EPG
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
14976011
DRES 25 Pounder Gun Tower - EPG
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
14976013
DRES 490 West Area (EPG) Coyote & Rabbit RDS (DRES site 6a)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
14976014
DRES Radioactive Liquid Spill(Near Fraggle Rock)-AtomicVault
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
14976016
DRES Willis Centre - EPG
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00273001
CFS ST John's (4710) - Cambrai Rifle Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00025087
Canadian Ranger Patrol Group Former Small Arms Range - Burgeo
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00025090
Canadian Rang. Pat. Grp. Former Small Arms Range - Channel
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00025106
5 CRPG - Former Small Arms Range - Terra Nova
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00025113
5 CRPG Former Small Arms Range - Bonavista (Port Rexton)
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00025107
5 CRPG - Former Small Arms Range - Port Saunders
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00025105
5 CRPG - Rocky Harbour (Cow Head)
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
N7019001
Northern Fuel Cache Site - Cartwright (Chopper Pad site)
Initial testing completed. Detailed testing underway. 2023-2024 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
N7087001
5 Wing Practice Target Area
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
69613001
LAB-3 SRR (Cape Kiglapait) Summit
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
N7040001
Saglek Bay Sediments
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
14876001
Landfill Site 34
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
14876002
Landfill Site 35
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
14876005
Landfill Site 32
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15729007
300 Meter Range (active)
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
15730002
Jimmy Lake Range
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
15730003
Shaver River Range
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
06972001
Pointe-Picard Marina - Marine sediments
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008339
Dundurn B155
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008528
Dundurn FFTA
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024864
Dundurn Fire Hall
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00025056
Dundurn Hardstand 6 Site
Initial testing completed. No further action required. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
14121002
Small Arms Ammunition Destruction Complex
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
14121005
Dundurn Demolition Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00000965
NAD-1 Naden Jr NCM
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00008436
YA-4 Yarrows Former Shipyard
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008593
DY-32 Dockyard Signal Hill Off. Mess & Prk Lot E of Bldg 520
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008616
NAD-10 Naden South - East of Admirals
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00008621
NAD-15 Naden North PMQ Housing
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008693
WP-11 Work Point Former USTs at PMQs
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
17403011
ESQ-1 - Esquimalt Harbour
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
17404001
DY-3 Dockyard Signal Hill Hood Bldg & Parking Lot
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024809
DY-10 Dockyard Signal Hill Building 575 & Surrounding Area
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00024932
WP-3d Work Point Former Outdoor 25 Yard Firing Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
17402009
WP-4n Work Point Dry Storage Area
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
17403003
DY-4 Dockyard FMF Consolidation
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
17403007
DY-1AG Dockyard B Jetty Fill
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024960
South RV Compound and P-151 Compound Area
Detailed testing completed. Remediation / risk management planned. 2023-2024 3 Low Priority for Action 05 Detailed Testing Program
00025088
Transport Fleet Compound (O-95)
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00025091
Training Area C2 Drainage
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
11022044
Langemark Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00008467
FOB Atlantic dump
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008562
Stream draining former DDT site in Farnham
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024826
Bronze Range (30 lines)
Detailed testing completed. Remediation / risk management planned. 2023-2024 N Not a Priority for Action 05 Detailed Testing Program
00024827
Palladium Range
Detailed testing completed. Remediation / risk management planned. 2023-2024 N Not a Priority for Action 05 Detailed Testing Program
06651003
Demolition site, CEF Farnham
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
16506001
Slesse Demolition Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
16506002
General Vokes Range
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00008389
9 Wing Heavy Equipment Building Site - Parcel #1
Detailed testing completed. No further action required. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00961002
9 Wing 25m Firing Range
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00978002
9 Wing POL Compound
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00978004
9 Wing B109 Wing Fire Hall
Detailed testing completed. No further action required. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00978006
9 Wing B16 Central Heat Plant (CHP)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00978007
9 Wing Bldg 21 POL Pumphouse
Detailed testing completed. No further action required. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00978022
Bldg 36 Curling Club
Remediation / risk management completed. No further action required. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00978024
9 Wing B106 Former CANEX site
Detailed testing completed. No further action required. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00978027
Scrap Compound / Supply Storage Area
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00978029
Building 108 Hoist
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00978009
Combined Outfalls - 1,2 & 3 & Drainage Ditch by FFTA
Remediation / risk management completed. No further action required. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00978011
Bldg 17 MSE Garage
Remediation / risk management completed. No further action required. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00978012
Bldg 108 Storage and Maintenance
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00978014
9 Wing B107 103 Rescue Unit
Remediation / risk management completed. No further action required. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00978015
9 Wing FFTA
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00978020
9 Wing B115 Former CANEX Site
Detailed testing completed. No further action required. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008449
CFB Shilo: Demolition Range
Detailed testing completed. Remediation / risk management planned. 2023-2024 N Not a Priority for Action 05 Detailed Testing Program
00008450
RTA Burial Pit
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008683
Former Grenade Range
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008684
Former Demolition Range
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00008500
Winona Rifle Range
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024904
Guelph Armoury
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008521
Willow Park (4327) - TEME North Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008522
Willow Park (4328) - Armoury South Site
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00024913
Shearwater Fire Hall Storage Shed (SH40) (Site 253)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024914
Shearwater CC-144B Challenger Crash Site (Site 249)
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024915
Shearwater Former FFTA (North Delta Taxiway) (Site 251)
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00024917
Shearwater FFTA (Alpha Taxiway) (Site 250)
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
52107001
Water lots(9905),Harbour Front (Naval staff house)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
03042001
West Chezzetcook Bombing Range (5769)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
03044007
DCD School (907) - Fire Fighting Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03044008
DCD School (908) - Contaminated Spoil Fill Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03044010
DCD School (910) - Former Ordnance Demolition Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03044011
DCD School (911) - Construction Debris Site
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
36056001
Water Lots (9912), Navy Buoys
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03010001
Water Lots (9906), French Cable Warf
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03011001
Shannon Park (3401) - Central Heating Plant (B4)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03011003
Shannon Park (3403) - Snow Stockpile area, behind (B4)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03011005
Shannon Park (3405) - Former Storage Building (B5)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03013004
DRDC (1408) - Waste solvent dumping (East of building 2)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
03013009
Water Lots (9913), DREA Accoustic Barge
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02920014
Stadacona (7604) - Queens Printer Bldg S93 Furn./Coal chute
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03002001
Windsor Park (4502) - Auto Hobby Club WP 87
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
03002002
Windsor Park (4501) - CHP (WP62) & POL Shed (WP58)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03002006
Windsor Park (4505) - PMQ Barracks
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
03009015
Dockyard Annex (1101) - Hazardous Storage Area (W45)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
03009024
Water Lots (9907), Dockyard Annex
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919047
Dockyard (1034) - Former D7
Remediation / risk management completed. No further action required. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919048
Dockyard (1036) - Former D17
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919049
Dockyard (1041) - Fomer D49
Remediation / risk management completed. No further action required. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919050
Dockyard (1043) - Former D59
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02920005
Stadacona (3705) - CE Production Centre (S30)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02920009
Stadacona (3708) - Gardens - rear of Bldg S52(Admiral's Res)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919041
Dockyard (1033) - Former B122 and 60
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919042
Dockyard (1042) - Former D159
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919043
Dockyard (1044) - Former D127
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919044
Dockyard (1045) - Former D109
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919045
Dockyard (1046) - Former D63
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919046
Dockyard (1032) - Fomer CN Rail Line btwn parking & building
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919032
Water Lots (9908) - Dockyard
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02919035
Dockyard (1035) - Former D15
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919036
Dockyard (1037) - Former D19
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919037
Dockyard (1039) - Former D95
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919039
Dockyard (1038) - Former D88
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919040
Dockyard (1040) - Former D20
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919023
Dockyard (1023) - Corrosion Prevention & Sub Squadron
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919024
Dockyard (1024) - FMG and SRU (D166)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919025
Dockyard (1025) - Shipwrights Shop (D174)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919029
Dockyard (1029) - Rectifier Building (D47)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919030
Dockyard (1030) - Maritime Command Headquarters (D14)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919031
Dockyard (1031) - Transformers East of Building D14
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919015
Dockyard (1015) - Underwater Repair building (D53)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919016
Dockyard (1016) - Central Heating Plant (D62)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919017
Dockyard (1017) - Outside Fitters and Machine Shop (D108)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919019
Dockyard (1019) - Packing and Preservation Bldg (D67)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919020
Dockyard (1020) - SRU Main Building (D200)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919021
Dockyard (1021) - Submarine Shelter (D170)
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02919006
Dockyard (1006) - Pollution Control DREA (D17)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919007
Dockyard (1007) - Sheet metal & Refrig. Shops (D19)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919010
Dockyard (1010) - Electronics Shop (D20)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919011
Dockyard (1011) - Inflammable Stores (D57)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919013
Dockyard (1013) - Base Supply (D40 and D155)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919014
Dockyard (1014) - Main Base Supply (D206)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918011
Willow Park (4312) - RCCS Garage (WL31)
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918017
Willow Park (4318) - Suspect Fmr Grease/Oil Pit (WL17)
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918018
Willow Park (4319) - Vehicle Maintenance Garage WL22
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918022
Willow Park (4320) - Salt Dome (WL36)
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919001
Dockyard (1001) - CE Office and Shops (D2)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919004
Dockyard (1004) - Mainguy Building (D201)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02865007
Water Lots (9909), McNabs Island
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02884012
Melville Island (5912) - Mooring Field
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02913001
Water Lots (9911) - HMCS Scotian
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02914001
Halifax Armoury Building (2201) - Main Armoury Building
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02916001
RA Park (3301) - Officers Mess (RA1)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
02918005
Willow Park (4306) - Utilities Shed (WL15) & Former WL34*
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863057
CFB Shearwater (245) - Hanger F
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863059
Water Lots (9910), Shearwater
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863061
Shearwater - PMQs, Former Brick Yard (Hornsby's) (234B)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02865002
McNabs Island (2602) - Flammable Stores Building (B5)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02865004
McNabs Island (2604) - Residence and AST (B10)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02865006
Water Lots (9903), Bedford Degaussing Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863030
Shearwater(230)-Bldg31,31A,31B,32(Mobl Spprt Maint)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863033
Shearwater(233)-Fmr MT Garage(BJ)Adjcnt Trnsfrmr Substn
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863035
Shearwater(235)-Frm Centrl Htg Plnt(G)Trnsfrmr Vault
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863040
CFB Shearwater (240) - West Hangar Line, Fmr UST at B15
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863041
CFB Shearwater (241) - East Hangar Line and Ramp Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863042
CFB Shearwater (242) - Hangar 3 and Annex
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863022
Shearwater (222A): Former POL (D) & UST (S) at bldg 212 & HY
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863023
Shearwater (223) - Building 4 and H (POL)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863024
Shearwater (224): Canex Garage (132), Former Firehall & UST
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
02863026
Shearwater (226) C. Heating Plant (56) & Fuel (rail) Comp.
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863028
Shearwater(228)-B9(Fmr Firehall,Tender Gar)Crown AssetsB70
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02863029
Shearwater(229)-Upr Fuel Cmpnd,Upgradient Dmpg Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02863016
CFB Shearwater (216) - Fill Area West of Alpha Taxiway
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863017
Shearwater (217) - Engine Run Up Area (DIPM Site)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863018
CFB Shearwater (218) - Suspect Burn Pit No 1
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863019
CFB Shearwater (219) - Suspect Burn Pit No 2/Coal Storage
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
02863020
Shearwater (220) - Fill Area South of Hangar H
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863021
Shearwater (221) - Lower Fuel Compound and Firing Range
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863009
Disposed: Shearwater (209) - Coast Guard Assigned Property
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863010
Shearwater (210) - Fire Fighting Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863011
CFB Shearwater (211) - Landfill 1
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02863012
CFB Shearwater (212) - Landfill 2
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863013
CFB Shearwater (213) - Landfill 3
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863014
CFB Shearwater (214) - Landfill 4
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859054
Wrights Cove (8602) - CN Rail Tracks/Building
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859055
Water Lots (9901) CFAD Bedford
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02860012
Hartlen Point (5554) - (B156 Old Work Shop)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863001
CFB Shearwater (201) - Landfill 6 - Airfield
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863003
CFB Shearwater (203) - Incinerator/Fill Site (DIPM Site)
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
02863006
Shearwater (206) Former Barrel site HH (DIPM Site)
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02859029
CFAD Bedford (809) - Otto Fuel Storage B203
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859032
CFAD East-side property (7403) - Area North of Highway 7
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859033
CFAD UXO Impacted Area (830) - Rent Point explosion
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859046
Navy Island (7501)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859050
Wrights Cove (8608) - National Gypsum Leased property
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859053
Wrights Cove (8607) - Upgradient Industrial Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859011
CFAD Bedford (812) - Otto Fuel Waste Burning Area BD220
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859014
CFAD Bedford (815) - Central Heating Plant (B190)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859018
CFAD Bedford (819) - Existing Jetty
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859020
CFAD Bedford (821) - Existing Jetty -NN at Wrent Point
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
02859023
CFAD Bedford (824) - Former Heating Plant (B140)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859026
CFAD Bedford (827) - Former Metal Scrap Yard
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02858010
Beford Rifle Range (710) - Former Rifle and Skeet Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02858011
Bedford Rifle Range (714) - Former 1940's Infrastructure
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02859001
CFAD Bedford (801) - Ridge Landfill
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859003
CFAD Bedford (803) - Former Landfill (West of B162)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859009
CFAD Bedford (810) - Otto Fuelling & Defuelling B48
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859010
CFAD Bedford (811) - Former UST's, BM 95 & BM 47*
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024918
Shearwater Aircraft Burn Area (Site 252)
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024954
Groundwater Recirculation Discharge Station Aerodome (254)
Initial testing completed. Detailed testing underway. 2023-2024   04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025081
12 Wing Shearwater PFAS Site-Wide
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
02858001
Bedford Rifle Range(701) former pesticide drum disposal area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02858004
Bedford Rifle Range (704) - Rifle Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02858005
Bedford Rifle Range (705) - Pistol Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00024958
FOX-MAIN Hydrocarbon Plume
Initial testing completed. Detailed testing underway. 2023-2024 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
70019001
FOX-M LRR (Hall Beach, NU - Landfill)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
C7021001
DEW-Line - FOX-M Hall Beach
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008431
CFRB Hamilton/HMCS Star
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024951
John Foote Armoury
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008429
South Escarpment Stillwaters (SES 1100 series)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00025030
Goose Bay Site Wide PFAS
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
01822018
Canadian Side & Northside
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
01822043
Hydrant Area Fuel Plumes (HYD9010)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
01822076
Main Base and Civil Aviation Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
01822085
Upper Tank Farm - Fuel Recovery Site (UTF 4000 Series)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
01822086
Survival Tank Farm (STF 3000 Series)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
01822087
South Escarpment Landfills (SES 1000 Series)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
01822094
Lower Tank Farm (LTF 2000 Series)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
N7075001
Dome Mountain, RCAF and Camp Sites (5 W)
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
N7077001
Main Gate & Hamilton River Road Plume (UPL 16000 series) 5W
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
12577001
St-Charles Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00025112
5 CRPG Former Small Arms Range - Hermitage
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00000955
Alpha Range
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00000956
Bravo Range
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024817
PLER Site Release
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
14876004
Landfill Site 31
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15729008
Landfill Site 28
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15729009
Landfill Site 29
Initial testing completed. No further action required. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15730001
PLER POL
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
15730005
F-18 A/C Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
69968001
FOL IQALUIT - Nose dock hangar (T-325)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 I Insufficient Information 08 Implement Remediation/Risk Management Strategy
00024869
Fuel Oil Spill 13 Hgr
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00025049
14 Wing Greenwood Site-Wide PFAS
Detailed testing completed. Remedial action plan under development. 2023-2024   06 Classify the site using the CCME National Classification System
02717001
Former Sludge Pit Runway 26 - Greenwood
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02717002
Former Sludge Pit Adjacent Golf Course - Greenwood
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02717004
POL Compound - Greenwood
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
02717006
MADD Shack Dump Area-Greenwood
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02717114
Battery Disposal Sump Hangar 8
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02717073
Sewage Treatment Plant POL Storage
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
02717082
25 Yard Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02717083
Heavy Machinery Practice Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02717085
7 Hangar Floor Drains
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02717099
UST #40 B-125 Water Pumphouse
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02717105
Operation Area Soils & GW (11 Hgr)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02717007
Active EOD Range - Greenwood
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
02717008
Bldg. 110 Community Centre - Greenwood
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02717010
CE Storage Area - Greenwood
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02717012
AMSE paint shop floor drain, Hangar 4 - Greenwood
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
02717013
Armament Area - Greenwood
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
02717015
Hangar 5 - Greenwood
Remediation / risk management completed. No further action required. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02739001
Aldershot Landfill/Former Incinerator
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02739002
Mill Pond and Sewage Lagoons - Aldershot
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
02739003
Former Garage (B46) and Septic Tank Area - Aldershot
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02739011
Former 500yd Range - Aldershot
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
02739014
Former Building 37 Aldershot
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
02739026
Former EME Vehicle Maintenance Garage and Sewer - Aldershot
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000911
Residential Housing Units Fort Henry Heights
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024837
Anglin's Bay
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
09406001
Soil remediation Site/Abandoned Landfill, Gore Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09406002
600 Yard Rifle Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09406006
75 Yard Small Arms Classification Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09406008
Abandoned Landfill - McNaughton Barracks
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
09407007
B24 Vimy Hydraulic Hoist
Detailed testing completed. Remedial action plan under development. 2023-2024 I Insufficient Information 06 Classify the site using the CCME National Classification System
09445001
Fort Frontenac Water Lots
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
09445002
Fort Frontenac Courtyard
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00008495
CAM-B
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
69765001
CAM-2 SRR (Gladman Point) - Site Summit
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
69766001
CAM-D SRR (Simpson Lake) - Site Summit
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
C7013001
DEW-Line - PIN-2 Cape Young
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
C7015001
DEW Line - PIN-4 Byron Bay
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7016001
DEW-Line - PIN-3 Lady Franklin Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7017001
DEW-Line - CAM-1 Jenny Lind Island
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7018001
DEW-Line CAM-2 Gladman Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7019001
DEW-Line - CAM-4 Pelly Bay
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7027001
DEW-Line - CAM-3 Shepherd Bay
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
69735001
Trail - Casino Ranges
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
58374001
Trail Stoney Creek Training & Demolition Area
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008559
Megantic Lake Armoury
Confirmatory sampling completed. Long term monitoring underway. 2023-2024   09 Confirmatory Sampling and Final Reporting
10829001
Stony Point (fmr Camp Ipperwash)
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024984
ALD-4 PMQ Heating Oil USTs
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024985
ALD-5 Former Mobile Kitchen
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00024988
ALD-8 Bldg 022 - Main Operations
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00024991
ALD-12 Antenna Field
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
16568001
ALD-1 Aldergrove Former Sewage Lagoon
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
16568002
ALD- 2 Aldergrove Former Skeet Range
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00000982
Petawawa Research Forest
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008335
CFB Petawawa RTA - Area 8 (Demolition Range)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00001007
Kipp Rifle Range
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008537
Lethbridge Airport CF18 Crash Site
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
05928001
Building 1 - Levis Armoury
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
10868001
TCE Contamination - Highbury Complex
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
10869001
Wolseley Barracks
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
10885002
HMCS Prevost Armoury
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
06710016
St-Hubert, playing field, reservoir T-40 
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
06710017
St-Hubert, Hangar 3, hydraulic elevators 
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008529
MA-1a Masset Skeet Range
Long term monitoring completed. No further action required. 2023-2024 1 High Priority for Action 10 Long-Term Monitoring (Optional)
00024955
MA-3 Masset Former Operation Centre
Detailed testing completed. Remediation / risk management planned. 2023-2024 3 Low Priority for Action 05 Detailed Testing Program
00024957
MA-4 Masset Radio Communications Center
Detailed testing completed. No further action required. 2023-2024 I Insufficient Information 05 Detailed Testing Program
10992001
Garrison Landfilll; Closed
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008625
RP-4 Rocky Point Bentinck Island Active Site
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008626
RP-10 Rocky Point Bldg 36A Steam-out Hut- Former/Current AST
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008628
RP-12 Rocky Point Vehicle Maintenance Garage
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00008631
RP-15 Rocky Point Whirl Bay
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024949
RP-3c Rocky Point White Phosphorus Active Disposal Area
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024974
AH-7 Albert Head Northwest Power Generation Region
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
17432004
RP-2a Rocky Point Active Explosive Ordnance Disposal
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
17432010
RP-2b Rocky Point Former Landfill B
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
17432011
RP-3ad Rocky Point Small Arms Slag Dump Former Landfills
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
17430001
MH-1 Mary Hill Machine Shop Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
17430002
MH-3 Mary Hill Former Rifle Range Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
17430004
MH-4 Mary Hill Battery
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
17430006
MH-2 Mary Hill Former Rocket Range
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
17431002
AH-5 Albert Head- Grenade Range (Active Site)
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
17432001
RP-1 Rocky Point CFAD Active Propellant Burn Area
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024975
AH-8 Albert Head Sewage Lagoon
Detailed testing completed. No further action required. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00024976
AH-10 Albert Head Energetics Testing & Shoreline Region
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024978
AH-9 Albert Head Gun Embankments, Central Uplands Region
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00025045
MH-5 MARY HILL FORTIFICATION LANDFILL
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00025046
MH-6 MARY HILL SEARCHLIGHT AND POWERHOUSE (MH-1027)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00025064
MH-7 MARY HILL FORMER NW BURN SITE
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008489
Salisbury Sm. Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
05613001
Mount Apica - north slope
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
05647014
Montmagny Armoury
Detailed testing completed. Remediation / risk management planned. 2023-2024 N Not a Priority for Action 05 Detailed Testing Program
07221008
Used snow sites, ASU LP 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00000927
15 Wing Hangar 6
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000928
15 Wing Former Skeet Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000929
15 Wing Hangar 2
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000930
15 Wing Landfarm
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000933
15 Wing Landfill
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00000935
15 Wing Hangar 5
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00000954
15 Wing Former FFTA
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024851
15 Wing EME Shop Test Site 1
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024853
15 Wing Fire Hall Test Area 1
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
13820001
15 Wing B58 & EME Shop Test Site 2
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
14121004
Burdick Range
Detailed testing completed. No further action required. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
18976001
Power Plant at Det Holberg
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00024979
NMC Bunker Nanaimo Military Camp
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008364
NRR-1A Nanaimo Rifle Range 600 yd & Beyond
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025080
NRR-1C Nanaimo Rifle Range 25m Pistol Range & Beyond ACTIVE
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03288003
New Glasgow Armoury (2901) - Armoury Buidling
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03288004
New Glasgow Armoury (2902) - POL Storage Building
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00024838
Niagara-on-the-Lake Tank Training Area
Detailed testing completed. No further action required. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
10626002
Niagara-on-the-lake Rifle Range
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
06294001
Adminstrative Area-Domaine, Lozeau and Bougainville Islands
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
06872002
Moras Island
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024877
22 Wing Building 45
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00024927
22 Wing PFAS Monitoring
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00025082
22 Wing Behind Building 14
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
11378001
22 Wing RV Compound
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
11378002
22 Wing Former POL Tank Farm
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
11378005
22 Wing 25m Outdoor Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00001001
Skeet Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008356
Camp Hughes
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008577
Grenade Range (Area A)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
00024952
Fire Fighting Training Area #2
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
12439001
Inactive Landfill
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
12439007
Rifle Range 3 (small arms)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00025031
PB-5 Pat Bay hangar wash pad
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00025033
PB-6: Pat Bay Hanger 17 fmr POL Shed/UST
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025078
PB-7 PAT BAY CONTAMINATION FROM OFFSITE ASTs/USTs
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
17132004
PB-2 Pat Bay Hangar 17 Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024845
Building B-12
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024883
CFHA - 203 MacKenzie Avenue
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00024894
Building B19
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024912
Former Building B6
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024940
CFHA - 157, 159, 161, 163, 165, 167 St. Lawrence Avenue
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00024971
CFHA - 36 Restigouche Road
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
04089011
POL Service Area - K20
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
04089024
C7 Hobby Shop
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
04089039
Salt and Sand Sheds
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00025099
CFHA - 48 Dakota Drive, Oromocto
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00025102
CFHA - 24 Comox Street, Oromocto
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00025109
CFHA - 48 Carleton Street, Oromocto
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00025122
CFHA – 76 MacLaren Drive, Oromocto
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
04089001
POL Compound
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
04089008
Fire Fighting Training Area and Adjacent Swamp
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00025083
CFHA – 9-11 Oneida Street, Oromocto, NB
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00025085
CFHA - 6 McElroy Crescent, Oromocto, NB
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00025093
CFHA - 48 Inchby Drive, Oromocto, NB
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00025094
CFHA - Huron Street, Oromocto
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00025097
CFHA - 191 St. Lawrence Avenue, Oromocto
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00025098
CFHA - 20 Oneida Street, Oromocto
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00025028
CFHA - 6-7 Dunn Court, Oromocto, NB
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00025057
CFHA - 10 Armstrong Court, Oromocto, NB
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025058
CFHA - 28 Comox Street, Oromocto, NB
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00025059
CFHA - 29 Shirley Court, Oromocto, NB
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00025060
CFHA - 50 Dakota Drive, Oromocto, NB
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00025061
CFHA - 59 Restigouche Road, Oromocto, NB
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00000937
CFS Leitrim, Former UST site between buildings #250D & #138
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00000940
Connaught Rnge Primary Trng Ctre- 35 Shirley Blvd, B34 AST
Detailed testing completed. No further action required. 2023-2024   05 Detailed Testing Program
00008334
Uplands Marina, CFSU(O)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008425
Connaught Ranges Range Butt Stop Stockpile
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
00008700
Connaught Skeet Range
Detailed testing completed. Remedial action plan under development. 2023-2024   06 Classify the site using the CCME National Classification System
08598005
Connaught Range Primary Training Ctre Former Transport Comp.
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
58322001
Golf Course Maintenance Compound (401), CFB Ottawa (south)
Long term monitoring completed. No further action required. 2023-2024 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
08598006
Connaught Range Primary Training Centre Former Landfill Site
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
08598007
Connaught Range Primary Training Centre - Building 36
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
58321001
Hunt Club Road Pinestand Property, Ottawa Airport
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
58321002
Pipeline (near Tank Farm), 7 Wing CFB Ottawa
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
58321003
Former Central Heating Plant (Building 309), Uplands
Confirmatory sampling completed. No further action required. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
58321009
Uplands Self-Help Housing Maintenance Compound
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00025055
Camp Utopia and Ranges
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00000984
Fire Fighting Training Areas
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00000991
Dry Solid Waste Landfill
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00008348
CANEX contaminated site
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00024924
Building PC-317
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
09586002
Pt Petre - Previous artillery range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
09596001
Carrying Place north of bldg.
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
34476004
Mtn View - Inner Landfill Site
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008493
BAF-2
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00008497
FOX-1
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00008498
FOX-A
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
00008668
FOX-4, Cape Hooper
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00024931
FOX-3 Dewar Lakes, Nunavut
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
20247006
Alert Main Station
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7020001
DEW-Line - CAM-5 Mackar Inlet
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7022001
DEW-Line-FOX-2 Longstaff Bluff
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7023001
DEW-Line - FOX-3 Dewar Lakes
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7024001
DEW Line FOX-4 Cape Hooper
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7026001
DEW-Line - DYE-M Cape Dyer
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
20247025
Alert TX Site
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
20247029
Alert Airfield
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
34422006
BAF-3 Brevoort Island LRR
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
34430001
Northern Fuel Cache Site - Resolution Island
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
69775001
FOX-B SRR (Nadluardjuk Lake) - North-West of site summit
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
70069014
Eureka - North Airstrip Apron
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008669
FOX-5, Broughton Island
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
C7025001
DEW Line-FOX-5 Broughton Island
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008453
Former small arm range Falaise
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008457
Quebec Citadel
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008468
S.DRDC-other former firing rngs
Detailed testing completed. No further action required. 2023-2024 3 Low Priority for Action 05 Detailed Testing Program
00008469
South Complex
Detailed testing completed. No further action required. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00008558
Beauport armoury
Detailed testing completed. Remediation / risk management planned. 2023-2024 3 Low Priority for Action 05 Detailed Testing Program
05750001
St-Malo Armoury
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
29757016
Former Firing Temp for SNC Tec site (ZIP 1), Donnacona Block
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
29757022
Former stop-butt for building 235, DRDC-South 
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
29757025
Stop-butts 207 and 211, DRDC-South (S6) 
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
05751001
PMQ Old Quebec City
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
29757001
Small calibre (Former dump), DRDC-South 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
29757002
Dry material (former dump for), DRDC-South 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
29757003
Atmosphere simulation (former dump), DRDC-South 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
29757012
Former stop-butts 341-316, DRDC-South (S14) 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
29757014
South Outfall, DRDC-South 
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00008347
Cadet Camp Landfill & Firing Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00008541
New ATESS Refinishing Shop
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024810
Hangar 5 & 6
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00024856
Fire Hall, Building 19
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00025016
8 Wing 10 Hangar
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025077
8 Wing Site Wide PFAS
Detailed testing completed. Remedial action plan under development. 2023-2024   06 Classify the site using the CCME National Classification System
09540005
EME Shop, Bldg 113 and Skeet Range
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
09540009
Middleton Park Landfill Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09540010
AMDU Landfill Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
09540012
8 W Fire Fighting Training Area /Hazardous Materials Storage
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
09540016
Area of Bldg 163 & 201
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
09540020
POL Compound - area of removed tanks
Remediation / risk management completed. No further action required. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00008371
BAR-DA1, Liverpool Bay, SRR Site
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
34452001
BAR-BA3 SRR (Storm Hills, NWTel Parson's Lake) Site Summit
Remedial action plan completed. Remediation / risk management underway. 2023-2024 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
C7010001
DEW-Line - BAR-4 Nicholson Peninsula
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7011001
DEW-Line - PIN-M Cape Parry
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7012001
DEW-Line - PIN-1 Clinton Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
N7083001
BAR-E SRR (Horton River) - Site Summit
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
58520001
Rimouski Naval Reserve, Montée Industrielle street
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
58520002
Rimouski Naval Reserve, boathouse
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
05906036
Rivière-du-loup Armoury, Thériault Boulevard
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008363
HRR-1 Heals Rifle Range 400yd & Beyond
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024999
VA-6 Three fueling tanks and the gas dock
Initial testing completed. No further action required. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025012
HRR-5 Heals Rifle Range Main Compound Training Area
Remedial action plan completed. Remediation / risk management underway. 2023-2024 I Insufficient Information 07 Develop Remediation/Risk Management Strategy
00025014
HRR-8 Heals Rifle Range Former 400-1000 yrd Range
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00025029
HRR-7 Heals Rifle Range Soil Storage Near Pistol Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00025079
HRR-9 HEALS RIFLE RANGE 100 yd PISTOL RANGE & Beyond (Active
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
17178003
HRR-2 Heals Rifle Range Former Grenade & Trap Shooting Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00000997
Aircraft boneyard-Ghost Squadron
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00008344
25 m small arms range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00008345
Car Club - used oil storage
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00024846
Fire Hall, Building 85
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024847
FOL - Maintenance Transport Shop, 76
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024961
Former Gas Station
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
07930019
Cadet camp-Former dry material disposal site
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
07930021
Former B-244 APU location 
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
69920001
HMCS Champlain - Chicoutimi Naval Reserve
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
07930013
Former 161 kV electrical substation - Building 111
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
07930014
Former sewage treatment plant - Building 118 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
07930015
New destruction centre for explosives - New EOD
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
07930016
Former demolition centre for explosives - Former EOD
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
07930017
Marsh - North of highway 170 
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
07930018
Bowser maintenance shop - Building 77
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
07930004
Aerodrome - West of runway 18-36 
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
07930006
Former landfill site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
07930007
FFTA & PFAS Bagotville
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
07930009
POL tank farm
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
07930011
Central Heating Plant 
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
07930012
Landfarming site 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024962
Former PCB Storage Area
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024972
Radar PAR
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00025036
Pond Site B225
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00025038
Juliette Tank
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00025062
Former Underground Tank B215
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025101
TCE au site du QRA
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008337
Former skeet range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008402
Firing range(Centre de biathlon Myriam-Bedard)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00008441
former small arm range Caen
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00008446
Woodland at NE.corner of Dugas&Jean-Brillant
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008511
former grenade range Château F
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008512
Former firing range G1
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
29757005
Sector for bldg 307, DRDC-Trials
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
29757006
''MDR'' (former dump for), DRDC-Trials 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
29757007
TCE Contamination- Valcartier
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
29757008
Dry material 2,500 m (former dump for), DRDC-Trials
Detailed testing completed. No further action required. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
29757009
Plateau (demolition site), DRDC-Trials 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
29757024
North Outfall, DRDC-North 
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
05906047
Former dump Château Road
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
05906053
Training areas, TERMOLI firing range
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
05906054
Training areas, LIRI Impact
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
05906058
Building 310
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
05906059
Castor center PHL T-610
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
05906060
AFFF Heliport
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
05906010
Biathlon (Myriam-Bédard Centre) 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
05906011
Forest Station 
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
05906037
Home base, lift - bldg 110
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
05906038
Home base, bldg 311, ACI-311 
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
05906041
Le RHIN former demolition area
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
05906044
Training areas, former CARPIQUET firing range
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00024825
Battle Runs 12A and 15A
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00024878
Cratère Training Range
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00024980
VC-301
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
05906001
Ground of building 622 (DEV-6) 
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
05906002
Base building 621 
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
05906008
Former Jean-Brillant Snow Dump 
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00008513
Former firing range G
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
00008515
former firing range G3
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00008543
Former Ammo Dump, Bernatchez Rd.
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008556
Former firing range P
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00008636
Past Landfill activities (A2)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008637
Past landfill activities - C
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00008405
North redoubt CMR St-Jean
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00008406
CMR Chapel
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008463
South redoubt RMC St-Jean
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00008564
Water filtration plnt of city in CMR St-Jean
Detailed testing completed. Remediation / risk management planned. 2023-2024 N Not a Priority for Action 05 Detailed Testing Program
00024834
Tanks K1090 and K 1091 near Building 102
Detailed testing completed. Remediation / risk management planned. 2023-2024 N Not a Priority for Action 05 Detailed Testing Program
06679001
Hydraulic elevator H-101, ASU St-Jean 
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
06679002
Former Garage and service station, ASU St-Jean 
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
06679007
St-Jean Garrson, Used snow site near H104 (2A) 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
06679009
St-Jean Garrson, Used snow site (2B) 
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
06680004
Royal Military College, Former reservoir T20 (building 102)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00008391
Pine Street Armoury
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00000925
HMCS Jolliet-Sept-Iles naval reserve
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
N7096001
Former CFS Moisie - Site Admin
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00008582
Sector 6 demolition site
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
05906016
Arnhem Firing Range
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
05906040
Training sector, ''AP'' and ''TE'' impact area 
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
05906052
Training areas, BOFFIN firing range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
05906061
Land adjacent to the former well P-2 
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
29757017
Former firing temp formed by Donnacona Block (ZIP 2) 
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
29757020
Former Impact Area (rebound/ricochet) Donnacona Blck(ZIP 5) 
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00348002
CFS St John's (5110) - Parkers Pond Transmitter Site
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00418002
CFS St John's (4801) - 200 Compound
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
32044002
CFS St Johns (5210) - Shea Height's Tank Farm
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
32046002
Pier 26 (5301) - British Property Site 7c (Cabot Boatshed)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
32047002
Pier 27 (5302) - Brit. Prop. Site 7c
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00008357
Training Area Borrow Pit
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00008491
Former landfill north of 195 Ave
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00008539
B184-Former APU for Steam Plant
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00008565
Former POL/JTFW Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00008701
B314 parking lot
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00025042
CFB Edmonton Site-Wide PFAS
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
00025050
West of 1 Field Ambulance Building
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
15531009
SAC Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
N7070001
Fire Fighting Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
N7071001
Bldg 187
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00008691
Burwash CFTA
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008535
Sussex Small Arms Rifle Range
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00008471
Old UXO destructn site St-Maurice Proof rng
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00008561
Trois-Rivières Armoury
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03130001
Truro Armoury (4001) - Armoury Building (B1)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
C7009001
DEW-Line - BAR-3 Tuktoyaktuk
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
18704002
Vernon Mt Commonage 300m Rifle Range
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
34337002
VIC-1 HMCS Malahat Waterlot
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00008352
Burn Pit (adjacent to Range Warden Compound)
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00008353
Pickled Sand Storage Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00008460
Range and training Area Characterization - NOT A CS
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00008685
Encroachment SE Corner of Wainwright RTA
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00025043
Wainwright Site-Wide PFAS
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
15305004
Constructed Fire Training Area
Remediation / risk management completed. No further action required. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
15305006
Dump on Shore of Bushy Head Lake
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
15305009
Former Firing Range 7
Initial testing completed. No further action required. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
29793001
Former Red Route Dump East Site
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
N7060001
Former Red Route Dump
Initial testing completed. No further action required. 2023-2024   03 Initial Testing Program
02762009
Newport Corner (3110) - Sewage Treatment Plant (package)
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00024857
17 Wing Former B87 EME Shop
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024858
17 Wing B88 Fire Hall
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024859
17 Wing NW of Log Building 129
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00024948
Kapyong Site
Confirmatory sampling completed. No further action required. 2023-2024   09 Confirmatory Sampling and Final Reporting
12579001
17 Wing Bulk Fuel POL & B82 Pumphouse
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
12579004
17 Wing Former Building 87
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
20612001
Float Dock 440 Sqn Yellowknife
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00008374
BAR-B, Stokes Point, SRR Site - Beach
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7007001
DEW-Line: BAR-1 Komakuk Beach
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
C7008001
DEW-Line - BAR-2 Shingle Point
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting