Site 58520002 - Rimouski Naval Reserve, boathouse

  • Status

    Detailed testing completed. Remedial action plan under development.
  • Site Status

    Active
  • Classification

    Medium Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    Federal Real Property
  • Property Type

    Federal (DFRP Property Number 70289)

Site Location

Locate this site on map
  • Latitude, Longitude

    48.4764, -68.514
  • Municipality

    Rimouski, QC
  • Federal Electoral District

    Rimouski-Neigette--Témiscouata--Les Basques

Site Management Strategy

  • Assessment

Contaminant Details

Contamination Estimate

  • Hectares

    0

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PHCs (petroleum hydrocarbons) Groundwater
PAHs (polycyclic aromatic hydrocarbon) Groundwater
PAHs (polycyclic aromatic hydrocarbon) Soil
Metal, metalloid, and organometallic Groundwater

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km1,644
5 km42,106
10 km104,636
25 km300,107
50 km389,896

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $22,444.44

Financial/Annual Information

2022-2023

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2021-2022

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2019-2020

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2018-2019

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2017-2018

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2016-2017

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2015-2016

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2014-2015

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2013-2014

  • Reporting Organization

    National Defence
  • Internal Identifier

    0355-C003
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2012-2013

  • Reporting Organization

    National Defence
  • Internal Identifier

    S-10061
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2011-2012

  • Reporting Organization

    National Defence
  • Internal Identifier

    S-10061
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $22,444.44
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2010-2011

  • Reporting Organization

    National Defence
  • Internal Identifier

    S10061
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No