Site 00023978 - Pathway below Parliament Hill

  • Status

    Initial testing completed. Detailed testing underway.
  • Site Status

    Active
  • Classification

Site Details

Site Location

Locate this site on map
  • Latitude, Longitude

    45.424684, -75.702026
  • Municipality

    Ottawa, ON
  • Federal Electoral District

    Ottawa Centre

Site Management Strategy

  • Additional assessment

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km10,127
5 km225,793
10 km619,330
25 km1,210,781
50 km1,436,747

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $13,563.61

FCSAP Expenditures

  • Assessment

    $10,850.89

Financial/Annual Information

2022-2023

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    96202
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $295.86
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $236.69
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2021-2022

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    96202
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $7,509.20
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $6,007.36
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    96202
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $5,758.55
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $4,606.84
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No