Contaminated Site 00022835

  • Status

    Detailed testing completed. Remedial action plan under development.
  • Site Status

    Active
  • Classification

    Medium Priority for Action

Site Details

Site Location

  • Municipality

    Ottawa, ON
  • Federal Electoral District

    Orléans

Contaminant Details

Contamination Estimate

  • Hectares

    780

The following contaminated media was identified on the site:

Contaminant Type Medium Type
BTEXs (benzene, toluene, ethylbenzene, and xylene) Groundwater

Action Plan

Additional contamination was found during a demolition project. Additional assessment is required.

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $239,230.06
  • Remediation

    $109,216.00

FCSAP Expenditures

  • Assessment

    $195,315.63
  • Remediation

    $97,509.00

Financial/Annual Information

2022-2023

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $30,904.25
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $24,723.40
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2021-2022

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $10,854.51
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $8,683.61
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2019-2020

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $4,087.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $3,270.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2018-2019

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $59,953.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $47,962.40
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2017-2018

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $48,292.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $38,634.32
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2016-2017

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $97,509.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $97,509.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2015-2016

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $5,179.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $4,143.20
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2014-2015

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $11,707.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    25.7 t
  • Closed

    No

2013-2014

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $10,542.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $8,433.60
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2012-2013

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $11,983.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $9,586.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2011-2012

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $10,946.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $8,756.80
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2010-2011

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $8,770.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $8,770.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $10,884.30
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $10,884.30
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2008-2009

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $26,835.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $21,468.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    6976
  • Highest Step Completed

    01 Identify Suspect Sites
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No