Contaminated Site 00013420

  • Status

    Initial testing completed. No further action required.
  • Site Status

    Closed
  • Classification

Site Details

Site Location

  • Municipality

    Cumberland, Subd. A, NS
  • Federal Electoral District

    Cumberland--Colchester

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $15,713.35

FCSAP Expenditures

  • Assessment

    $14,170.41

Financial/Annual Information

2012-2013

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    PR H/14
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $5,382.35
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $4,305.88
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2011-2012

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    PR H/14
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2010-2011

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    PR H/14
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $8,000.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $8,000.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    PR H/14
  • Highest Step Completed

    02 Historical Review
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    Royal Canadian Mounted Police
  • Internal Identifier

    PR H/14
  • Highest Step Completed

    02 Historical Review
  • Total Assessment Expenditure

    $2,331.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $1,864.53
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes