Site 00001538 - Sheffield Mills Research Farm

  • Status

    Detailed testing completed. No further action required.
  • Site Status

    Closed
  • Classification

    Low Priority for Action

Site Details

Site Location

Locate this site on map
  • Latitude, Longitude

    45.13061, -64.485973
  • Municipality

    Kings, Subd. B, NS
  • Federal Electoral District

    Kings--Hants

Contaminant Details

Contamination Estimate

  • Cubic Meters

    5

The following contaminated media was identified on the site:

Contaminant Type Medium Type
Metal, metalloid, and organometallic Surface soil

Action Plan

Assessed and site will be closed

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km148
5 km6,610
10 km25,438
25 km56,144
50 km105,517

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $44,263.50

Financial/Annual Information

2015-2016

  • Reporting Organization

    Agriculture and Agri-Food Canada
  • Internal Identifier

    Barn / Building 34 - Lead Paint Chips in Soil
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $29,755.67
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2014-2015

  • Reporting Organization

    Agriculture and Agri-Food Canada
  • Internal Identifier

    Barn / Building 34 - Lead Paint Chips in Soil
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $14,507.83
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No