Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Project | Original Estimated Total Cost ($ millions) |
Revised Estimated Total Cost ($ millions) |
Actual Cost Total ($ millions) |
2010-2011 ($ millions) | Expected Date of Close-out | |||
---|---|---|---|---|---|---|---|---|
Main Estimates | Planned Spending | Total Authorities | Actual | |||||
Program Activity | ||||||||
Supercomputer facility upgrade to electrical and cooling capacity (effective project approval) (project close-out phase) | $6.1 | $6.9 | $6.9 | $0 | $0 | $0 | $0 | Project completed in 2009–2010 |
UPS replacement – Dorval facility (effective project approval) (project implementation phase) | $10.6 | $15.4 | $1.8 | $0.3 | $0.3 | $0.3 | $0.3 | Project cancelled in May 2011-2012 but close-out costs in fiscal year 2011-2012 expected. |
TOTAL | $16.7 | $22.3 | $8.7 | $0.3 | $0.3 | $0.3 | $0.3 |