This page has been archived.
Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
Description
Health Information and Claims Processing Services (HICPS) Major Crown Project.
HICPS is the key delivery mechanism for the payment of pharmacy, medical supplies and equipment, and dental benefits under Health Canada's Non-Insured Health Benefits (NIHB) Program.
The HICPS Project was established to conduct a competitive procurement to replace the existing HICPS contract, to manage the implementation of the new service contract and ensure a smooth transition from the current incumbent to the new contractor.
Project Phase
Project Implementation: The HICPS Major Crown Project entered the project implementation phase with the December 4, 2007 award of the HICPS contract to ESI Canada.
HICPS supports the delivery of much-needed health benefits for over 790,000 eligible First Nations and Inuit clients. The HICPS Project Implementation phase will terminate in December 2009 with a project evaluation. The new Health Information and Claims Processing Services will be put into production, taking over service provision on December 1, 2009.
Lead Department or Agency: | Health Canada |
Contracting Authority: | Public Works and Government Services Canada |
Participating Departments and Agencies: | Indian and Northern Affairs Canada |
Prime Contractor: | ESI Canada, Mississauga, Ontario, Canada |
Major Subcontractors: | Resolve Corporation, Toronto, Ontario, Canada |
Major Milestones | Date |
---|---|
Initial meetings with Contractor, coordination of implementation phase project plan | Contract Award (December 4, 2007 through January 2008) |
Business Requirements Gathering and Design | February 2008 to August 2008 |
HICPS Development | September 2008 to April 2009 |
HICPS Testing and Acceptance | May to September 2009 |
Documentation, Simulations, Validation, Data Conversion and Training | September 2009 to November 2009 |
HICPS Implementation (ESI Canada officially takes over real-time service provision) | December 1, 2009 |
Evaluation of the HICPS Project and lessons learned | December 2010 to March 2011 |
Progress Report and Explanations of Variances
The definition phase of the HICPS project (including the request for proposals process through bid evaluation and ultimately contract award) was concluded on budget and the project implementation phase is now underway as of December 4, 2007.
Industrial Benefits
The Industrial Regional Benefits (IRB) model was modified to focus on benefiting the Aboriginal economic community, rather than a specific industry or region of Canada, resulting in an Aboriginal benefit requirement (ABR) which is unique to the HICPS Project.
The development of the ABR approach for the HICPS Project was informed by industry feedback through two Requests for Information (RFI) consultation processes, and approved by Treasury Board. As HICPS' Prime Contractor, ESI Canada will be required to ensure a mandatory and substantial Aboriginal benefits requirement representing direct or indirect benefits to Aboriginal businesses or individuals.