Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
52107001
Water lots(9905),Harbour Front (Naval staff house)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
05669001
Marine House Building, Halifax
Remediation / risk management completed. No further action required. 2012-2013 I Insufficient Information 08 Implement Remediation/Risk Management Strategy
03044016
Sandwich Point (7302) - Transformer (Water Pump Sta.)
Initial testing completed. No further action required. 2014-2015 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03044015
Disposed -Sandwich Pt.(7301) Fmr Pump house-AST/Transformer
Long term monitoring completed. No further action required. 2014-2015 1 High Priority for Action 10 Long-Term Monitoring (Optional)
03044014
DCD School (903) - AST at B6
Long term monitoring completed. No further action required. 2014-2015 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
03044006
DCD School (906) - Upper Garage
Confirmatory sampling completed. No further action required. 2009-2010 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
03044005
DCD School (905) - POL compound
Detailed testing completed. No further action required. 2010-2011 1 High Priority for Action 05 Detailed Testing Program
03044002
DCD School (902) - AST at B3
Long term monitoring completed. No further action required. 2013-2014 3 Low Priority for Action 10 Long-Term Monitoring (Optional)
03044001
DCD School (901) - Former USTs at Bldg B1
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
03034001
Coast Guard Base Dartmouth (Metal/PAH/Hydrocarbons in Soil/Groundwater)
Detailed testing completed. No further action required. 2014-2015 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
03020001
Parking
Confirmatory sampling completed. No further action required. 2009-2010 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
03017003
Bedford Institute of Oceanography (Shipping containers- Metal in soil)
Detailed testing completed. No further action required. 2012-2013 N Not a Priority for Action 05 Detailed Testing Program
03017002
Bedford Institute of Oceanography (Metal in soil- South of VanSteenburgh building)
Detailed testing completed. No further action required. 2012-2013 N Not a Priority for Action 05 Detailed Testing Program
03017001
Bedford Institute of Oceanography (Hydrocarbons in Soil - Fmr. UST)
Detailed testing completed. No further action required. 2015-2016 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
03013010
Fuel Lines fr Bunker AST to French Cable Wharf (1404)
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
03013009
Water Lots (9913), DREA Accoustic Barge
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03013004
DRDC (1408) - Waste solvent dumping (East of building 2)
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
03011011
Shannon Park (3409) - Fill Area, Rink
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
03011010
Shannon Park (3410) - Residential Area
Remediation / risk management completed. No further action required. 2014-2015 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03011009
Shannon Park (3408) -CHP Ash Disposal
Remediation / risk management completed. No further action required. 2014-2015 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03011008
Disposed - Water Lots, Shannon Park (9904)
Confirmatory sampling completed. No further action required. 2014-2015 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03011007
Shannon Park (3407) - Former Location of Storage (B7)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
03011006
Shannon Park (3406) - Skating Rink (B20)
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
03011005
Shannon Park (3405) - Former Storage Building (B5)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03011004
Shannon Park (3404) - Swimming Pool (B10)
Historical review completed. No further action required. 2001-2002   02 Historical Review
03011003
Shannon Park (3403) - Snow Stockpile area, behind (B4)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03011002
Shannon Park (3402) - Fmr POL Storage Behind (B2)
Remediation / risk management completed. No further action required. 2014-2015 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03011001
Shannon Park (3401) - Central Heating Plant (B4)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03010001
Water Lots (9906), French Cable Warf
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03009024
Water Lots (9907), Dockyard Annex
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03009023
Dockyard Annex (1118) - W54 Residence
Remediation / risk management completed. No further action required. 2009-2010 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
03009022
Dockyard Annex (1117) - W53 Garage
Remediation / risk management completed. No further action required. 2009-2010 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
03009015
Dockyard Annex (1101) - Hazardous Storage Area (W45)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
03009008
Dockyard Annex (1110) - Silica Sand Blast (W61)
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
03002010
Windsor Park (4511) - UST Site WP90
Confirmatory sampling completed. No further action required. 2007-2008 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
03002001
Windsor Park (4502) - Auto Hobby Club WP 87
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02991001
Ahern Avenue Old Maintenance Building
Confirmatory sampling completed. No further action required. 2013-2014 I Insufficient Information 09 Confirmatory Sampling and Final Reporting
02983001
Phase I ESA 1919 Upper Water Street Site- no contamination confirmed
Historical review not required. 2011-2012   01 Identify Suspect Sites
02920010
Stadacona Gym (3710) - Former UST
Confirmatory sampling completed. No further action required. 2007-2008 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02919022
Dockyard (1022) - Oil Waste water Treatment
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02919018
Dockyard (1018) - Base Supply (D66)
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02919002
Dockyard (1002) - Boat Shed (D5)
Initial testing completed. No further action required. 2007-2008   03 Initial Testing Program
02907004
Disposed - Willow Park (4324) - CE Stores (EY3)*
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02865006
Water Lots (9903), Bedford Degaussing Range
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863061
Shearwater - PMQs, Former Brick Yard (Hornsby's) (234B)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863060
Shearwater (243), Buried Lines Connect. Fmr Fuel Tank Farm
Historical review completed. No further action required. 2001-2002 N Not a Priority for Action 02 Historical Review
02863059
Water Lots (9910), Shearwater
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863054
CFB Shearwater (205) - Ammunition Compound
Remediation / risk management completed. No further action required. 2019-2020 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
02863053
CFB Shearwater (204B) - Former Heavy Equipment Compound
Long term monitoring completed. No further action required. 2019-2020 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
02863052
Shearwater(236)-Frm UST Loc(WWII)Bravo Taxiwy
Initial testing completed. No further action required. 2014-2015 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02863051
Osborne Head (5665) - Former Radar Site
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02863042
CFB Shearwater (242) - Hangar 3 and Annex
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863041
CFB Shearwater (241) - East Hangar Line and Ramp Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863040
CFB Shearwater (240) - West Hangar Line, Fmr UST at B15
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863039
Shearwater(239)-Former Transformer Site(Railway Spot)
Initial testing completed. No further action required. 2000-2001 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02863035
Shearwater(235)-Frm Centrl Htg Plnt(G)Trnsfrmr Vault
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863034
Shearwater(234A)-PMQs, Former Brick Yd(Hornsby's)
Long term monitoring completed. No further action required. 2012-2013 3 Low Priority for Action 10 Long-Term Monitoring (Optional)
02863033
Shearwater(233)-Fmr MT Garage(BJ)Adjcnt Trnsfrmr Substn
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863031
Shearwater(231)-W.Property Boundary
Initial testing completed. No further action required. 2000-2001 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02863030
Shearwater(230)-Bldg31,31A,31B,32(Mobl Spprt Maint)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863029
Shearwater(229)-Upr Fuel Cmpnd,Upgradient Dmpg Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02863028
Shearwater(228)-B9(Fmr Firehall,Tender Gar)Crown AssetsB70
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02863026
Shearwater (226) C. Heating Plant (56) & Fuel (rail) Comp.
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863024
Shearwater (224): Canex Garage (132), Former Firehall & UST
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
02863023
Shearwater (223) - Building 4 and H (POL)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863022
Shearwater (222A): Former POL (D) & UST (S) at bldg 212 & HY
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863021
Shearwater (221) - Lower Fuel Compound and Firing Range
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863020
Shearwater (220) - Fill Area South of Hangar H
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863019
CFB Shearwater (219) - Suspect Burn Pit No 2/Coal Storage
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
02863018
CFB Shearwater (218) - Suspect Burn Pit No 1
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863017
Shearwater (217) - Engine Run Up Area (DIPM Site)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863016
CFB Shearwater (216) - Fill Area West of Alpha Taxiway
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863014
CFB Shearwater (214) - Landfill 4
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863013
CFB Shearwater (213) - Landfill 3
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863012
CFB Shearwater (212) - Landfill 2
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863011
CFB Shearwater (211) - Landfill 1
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02863010
Shearwater (210) - Fire Fighting Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02863009
Disposed: Shearwater (209) - Coast Guard Assigned Property
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863008
CFB Shearwater (208) - Former Maintenance Hangar
Long term monitoring completed. No further action required. 2019-2020 1 High Priority for Action 10 Long-Term Monitoring (Optional)
02863006
Shearwater (206) Former Barrel site HH (DIPM Site)
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02863004
CFB Shearwater (204A) - Former Mobile Asphalt Plant
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02863003
CFB Shearwater (203) - Incinerator/Fill Site (DIPM Site)
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
02863002
CFB Shearwater (202) - EOD Disposal Area (DIPM site)
Confirmatory sampling completed. No further action required. 2016-2017 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02863001
CFB Shearwater (201) - Landfill 6 - Airfield
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859057
Disposed:Bedford Degauss Rnge(7701),Naval Reserve Tufts Cove
Historical review completed. No further action required. 1999-2000 N Not a Priority for Action 02 Historical Review
02859056
Bedford Degaussing Range (601) Ind. workshop/garage (B8)
Remediation / risk management completed. No further action required. 2019-2020 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02859055
Water Lots (9901) CFAD Bedford
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859054
Wrights Cove (8602) - CN Rail Tracks/Building
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859053
Wrights Cove (8607) - Upgradient Industrial Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859052
CFAD Bedford (832), Asbestos pipe on access road B79/107/109
Remediation / risk management completed. No further action required. 2009-2010 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859051
CFAD Bedford (831) - Open well NE of B146
Remediation / risk management completed. No further action required. 2009-2010 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859048
Bedford Degaussing Range (608) - B9 POL STORAGE CABINET
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02859046
Navy Island (7501)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02859042
Bedford Degaussing Range (603) - B6 Existing Bulk Structure
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02859041
Bedford Degaussing Range (604) B5 Existing Sc. Structure
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02859040
Bedford Degaussing Range (605) B4 Existing Sc. Structure
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02859039
Bedford Degaussing Range (602) - Paint Locker beside B7
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02859038
Wrights Cove (8605) - Two infilled areas
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02859036
Wrights Cove (8603) - Two suspected dump areas
Confirmatory sampling completed. No further action required. 2018-2019 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02859035
Wrights Cove (8606) - Storm Drain
Confirmatory sampling completed. No further action required. 2017-2018 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859034
Wrights Cove (8604) - Pond disposal area
Long term monitoring completed. No further action required. 2017-2018 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
02859033
CFAD UXO Impacted Area (830) - Rent Point explosion
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859032
CFAD East-side property (7403) - Area North of Highway 7
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859029
CFAD Bedford (809) - Otto Fuel Storage B203
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859028
CFAD Bedford (829) - Camera Hut (BD44)
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
02859027
CFAD Bedford (828) - Former Location of Buildings 47 &48
Initial testing completed. No further action required. 2009-2010 N Not a Priority for Action 03 Initial Testing Program
02859026
CFAD Bedford (827) - Former Metal Scrap Yard
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859025
CFAD Bedford (826) - Former Maintenance Area, Labs
Confirmatory sampling completed. No further action required. 2016-2017 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02859024
CFAD Bedford (825) - Former Maintenance Garage
Initial testing completed. No further action required. 2016-2017 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02859023
CFAD Bedford (824) - Former Heating Plant (B140)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859022
CFAD Bedford (823) - POL Storage Building (BD27)
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
02859021
CFAD Bedford (822) - Buildings BD169-BD178, BD182 &BD183
Confirmatory sampling completed. No further action required. 2016-2017 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02859020
CFAD Bedford (821) - Existing Jetty -NN at Wrent Point
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
02859019
CFAD Bedford (820) - Former Landfill near B206
Long term monitoring completed. No further action required. 2017-2018 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
02859018
CFAD Bedford (819) - Existing Jetty
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859017
CFAD Bedford (818) - Otto Fuel Storage (BD164)
Initial testing completed. No further action required. 2002-2003 N Not a Priority for Action 03 Initial Testing Program
02859014
CFAD Bedford (815) - Central Heating Plant (B190)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859011
CFAD Bedford (812) - Otto Fuel Waste Burning Area BD220
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859010
CFAD Bedford (811) - Former UST's, BM 95 & BM 47*
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859009
CFAD Bedford (810) - Otto Fuelling & Defuelling B48
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859008
CFAD Bedford (808) - Railcar off loading plat & B191
Initial testing completed. No further action required. 2003-2004   03 Initial Testing Program
02859007
CFAD Bedford (807) - BCE Storage Yard
Initial testing completed. No further action required. 2002-2003   03 Initial Testing Program
02859006
CFAD Bedford (806) - Sewage Treatment Plant
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02859003
CFAD Bedford (803) - Former Landfill (West of B162)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02859001
CFAD Bedford (801) - Ridge Landfill
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02858013
Bedford Degaussing Rng (607)- B1Caretaker Res (Cntrl Bldg)
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02858012
Bedford Degaussing Range (606)- B3 Existing Bulk Structure
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
02844001
Inner Sambro Island - Metals Impacts in Soil
Detailed testing completed. No further action required. 2013-2014 2 Medium Priority for Action 05 Detailed Testing Program
02842001
Chebucto Head - Metals in soil and Petroleum in groundwater and soil
Detailed testing completed. No further action required. 2013-2014 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
02835001
Sambro Island - Metals and Petroleum in soil
Remediation / risk management completed. No further action required. 2015-2016 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00026534
- AT04881617
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00026015
27 - Millbrook - 06059 - MILLBROOK 27 - AT04876617
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025797
Institute for Marine Biosciences, Sandy Cove
Confirmatory sampling completed. No further action required. 2017-2018 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00025784
IMB Halifax
Initial testing completed. No further action required. 2018-2019 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00025315
Sable Island- Potential Hydrocarbon Impacts at Former Fuel Drum Storage Area
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00025081
12 Wing Shearwater PFAS Site-Wide
Detailed testing completed. Remediation / risk management planned. 2023-2024 1 High Priority for Action 05 Detailed Testing Program
00025054
CF Ammunition Depot Bedford Site-Wide PFAS
Historical review completed. Initial testing underway. 2023-2024   02 Historical Review
00024954
Groundwater Recirculation Discharge Station Aerodome (254)
Initial testing completed. Detailed testing underway. 2023-2024   04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024953
Roads and Grounds Storage Yard
Historical review planned. 2023-2024   01 Identify Suspect Sites
00024920
Shearwater Sea King Crash Site (Site 248)
Historical review planned. 2023-2024   01 Identify Suspect Sites
00024918
Shearwater Aircraft Burn Area (Site 252)
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024917
Shearwater FFTA (Alpha Taxiway) (Site 250)
Initial testing completed. Detailed testing underway. 2023-2024 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00024915
Shearwater Former FFTA (North Delta Taxiway) (Site 251)
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00024914
Shearwater CC-144B Challenger Crash Site (Site 249)
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
00024913
Shearwater Fire Hall Storage Shed (SH40) (Site 253)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00024811
Shearwater (247) Abandoned Transformer Shed
Confirmatory sampling completed. No further action required. 2016-2017 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00023160
Sambro Island former dwelling areas - No Further Work Required
Initial testing completed. No further action required. 2012-2013   03 Initial Testing Program
00022919
Portuguese Cove Measured Mile Beacon Rear (Zinc in Soil)
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022658
Halifax RCMP
Historical review completed. No further action required. 2011-2012   02 Historical Review
00017943
WEST PENNANT (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017901
SAMBRO CREEK - no impacts Closed
Historical review completed. No further action required. 2009-2010 N Not a Priority for Action 02 Historical Review
00017802
KETCH HARBOUR (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017791
HERRING COVE (unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017598
Bear Cove MMB Rear (No Impacts)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00017597
Bear Cove MMB Front (No Impacts)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00017579
Shannon Hill MCTS Centre - No further work required
Initial testing completed. No further action required. 2012-2013   03 Initial Testing Program
00017555
Landy Building Parking Lot (Unassessed)
Historical review not required. 2013-2014   01 Identify Suspect Sites
00017551
Halifax Tide Gauge (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017542
Coast Guard Vessel Support - Unassessed
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017541
Coast Guard Large Vessel Warehouse - Unassessed
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017531
Sambro Harbour, Bull Point - Light Bouy Only
Historical review completed. No further action required. 2008-2009 N Not a Priority for Action 02 Historical Review
00017471
Sandwich Point Range Rear- No Impacts Identified
Initial testing completed. No further action required. 2012-2013   03 Initial Testing Program
00017470
Sandwich Point Range Front - Zinc Impacts in Soil
Initial testing completed. No further action required. 2012-2013 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017468
Sambro SAR (No Impacts Identified)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00017467
Sambro Remote Transmitter (Metals in Soil)
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017351
Herring Cove Boathouse (Metal Impacts)
Initial testing completed. No further action required. 2012-2013 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017315
Chebucto Head Measured Mile Beacon Front - No Concerns Identified
Initial testing completed. No further action required. 2008-2009 N Not a Priority for Action 03 Initial Testing Program
00017309
Herring Cove Breakwater (Unassessed)
Historical review not required. 2014-2015   01 Identify Suspect Sites
00017308
Herring Cove - Metal Impacts
Detailed testing completed. No further action required. 2016-2017 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00017298
Halifax Harbour Inner Range Rear (Metals in Soil)
Remediation / risk management completed. No further action required. 2016-2017 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00017297
Georges Island Halifax Harbour Inner Range Front - Metals in Soil
Detailed testing completed. No further action required. 2014-2015 2 Medium Priority for Action 05 Detailed Testing Program
00017283
Georges Island Radar - Metals in Soil
Initial testing completed. No further action required. 2012-2013 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013450
Cole Harbour RCMP
Initial testing completed. No further action required. 2010-2011   03 Initial Testing Program
00013370
Portuguese Cove MMB Front (Zinc in Soil within SSCs)
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013106
Bedford Institute of Oceanography (Fume hood discharge area-Metals in soil)
Detailed testing completed. No further action required. 2012-2013 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00013041
Dartmouth Laboratory
Initial testing completed. No further action required. 2005-2006 N Not a Priority for Action 03 Initial Testing Program
00012606
Portuguese Cove (No Impact Closed)
Initial testing completed. No further action required. 2008-2009 N Not a Priority for Action 03 Initial Testing Program
00011539
Coast Guard Helicopter Refueling Pad
Detailed testing completed. No further action required. 2013-2014 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00008673
CFB Shearwater (204C) - Former Arrestor Gears
Remediation / risk management completed. No further action required. 2017-2018 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
00008427
DCD School (912) - Gravel Entrance Parking Lot
Initial testing completed. No further action required. 2010-2011 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00005884
27 - Millbrook - 06058 - COLE HARBOUR 30 / 0202609205
Historical review not required. 2013-2014   01 Identify Suspect Sites