Search Results

Search Results Summary
Criteria:
  • Federal Electoral District: Ottawa Centre
Select Additional Criteria...
Sort Key:FCSI Identifier (ascending)
Sites Found:104
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
58479003
Booth Street
Remediation / risk management completed. No further action required. 2011-2012 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
58479002
Booth Street
Remediation / risk management completed. No further action required. 2011-2012 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
58479001
Booth Street
Remediation / risk management completed. No further action required. 2011-2012 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
58475001
555 Booth Street
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
54521001
Former Sir John Carling Building
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
50064001
Environmental Health Centre
Confirmatory sampling completed. No further action required. 2009-2010 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
24426002
Vacant Land (Former temporary Building # 8)
Confirmatory sampling completed. No further action required. 2009-2010 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
09412005
Mooney's Bay Marina (Hog's Back)
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
08895002
Birks Building
Detailed testing completed. No further action required. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
08895001
Parliamentary Precinct Block 2
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
08886001
Former NCC Building
Confirmatory sampling completed. No further action required. 2009-2010 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
08839001
Library and Archives Canada Building
Remediation / risk management completed. No further action required. 2009-2010 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
08838001
Garden of Provinces et Territories
Detailed testing completed. No further action required. 2014-2015 N Not a Priority for Action 07 Develop Remediation/Risk Management Strategy
08837001
West Memorial Building
Remedial action plan completed. Remediation / risk management underway. 2023-2024 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
08835005
West Part of Bank Street Valley (see 08834.001 for East Part)
Remediation / risk management completed. No further action required. 2009-2010 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
08835004
Justice, Supreme Court, Confederation, Fed. Annex, Central Heating Plant Buildings
Confirmatory sampling completed. No further action required. 2019-2020 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
08835003
St. Laurent Square
Remediation / risk management completed. No further action required. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
08835002
Cliff Street Central Heating Plant
Remediation / risk management completed. No further action required. 2019-2020 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
08834003
East Block Building
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
08834002
Centre Block Building
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
08834001
East Part of Bank Street Valley (see 08835.005 for West Part)
Remediation / risk management completed. No further action required. 2009-2010 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
08831001
National Press Block
Confirmatory sampling completed. No further action required. 2009-2010 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
08803005
Booth Street Buildings (William Logan and Administration)
Remediation / risk management completed. No further action required. 2019-2020 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
08803004
Booth Street Buildings (William Logan and Administration)
Confirmatory sampling completed. No further action required. 2009-2010 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
08803003
Booth Street Buildings (William Logan and Administration)
Confirmatory sampling completed. No further action required. 2009-2010 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
08803001
Booth Street Buildings (William Logan and Administration )
Confirmatory sampling completed. No further action required. 2009-2010 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
08625036
Central Experimental Farm
Remediation / risk management completed. No further action required. 2011-2012 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
08625031
Central Experimental Farm
Detailed testing completed. Remedial action plan under development. 2023-2024 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
08625023
Central Experimental Farm
Detailed testing completed. No further action required. 2015-2016 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
08625021
Central Experimental Farm
Confirmatory sampling completed. No further action required. 2011-2012 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
08625019
Central Experimental Farm
Detailed testing completed. No further action required. 2012-2013 3 Low Priority for Action 06 Classify the site using the CCME National Classification System
08625018
Central Experimental Farm
Detailed testing completed. No further action required. 2011-2012 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
08625001
Central Experimental Farm
Detailed testing completed. No further action required. 2014-2015 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00028122
L'Esplanade Laurier
Initial testing completed. No further action required. 2023-2024   03 Initial Testing Program
00028121
Jackson Building (122 Bank Street)
Initial testing completed. No further action required. 2023-2024   03 Initial Testing Program
00027638
Dominion Observatory
Historical review completed. No further action required. 2018-2019   02 Historical Review
00027617
Middle Street
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00027616
161 Middle Street
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00027615
Middle Street to Booth Street
Detailed testing completed. No further action required. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00027614
Ottawa River
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00027602
Middle Street
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00027601
160 Middle Street
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00027600
156 Middle Street
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00024016
Cliff Street
Historical review planned. 2023-2024   01 Identify Suspect Sites
00024015
Chaudiere Island Lot P
Detailed testing completed. No further action required. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024014
Chaudiere Island Lot Pa
Detailed testing completed. No further action required. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024013
Booth Street East, West of Wellington
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024012
Booth Street, West of LeBreton near Chaudiere Falls
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00024011
Cliff Street
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00024009
Westboro Beach
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00024007
150 Middle Street
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00024005
Queen Elizabeth Drive N of, W of Preston
Detailed testing completed. No further action required. 2018-2019 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00024003
80 Bayview Garage
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024002
80 Bayview Shed 2
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024001
80 Bayview Shed
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00024000
80 Bayview Main Building
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00023999
234 Atlantis Ave
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00023998
Sir John A MacDonald Parkway - Westboro Beach
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023990
Victoria Island
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00023988
Confederation Park
Detailed testing completed. No further action required. 2022-2023 2 Medium Priority for Action 07 Develop Remediation/Risk Management Strategy
00023987
Burnside Site
Detailed testing completed. Remedial action plan under development. 2023-2024 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00023983
Central LeBreton
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00023978
Pathway below Parliament Hill
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00023977
160 Middle Street
Confirmatory sampling completed. No further action required. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00023976
Colonel By Drive
Initial testing completed. No further action required. 2018-2019   03 Initial Testing Program
00023361
Lebreton - East
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023356
Pathway below Parliament Hill
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00023340
Canland B
Confirmatory sampling completed. No further action required. 2016-2017 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00023337
Bate Island
Long term monitoring completed. No further action required. 2018-2019 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
00023334
Garden of The Provinces
Detailed testing completed. Remediation / risk management planned. 2023-2024 N Not a Priority for Action 05 Detailed Testing Program
00023321
Former Dow's Lake Landfill and Commissioner's Park
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023316
LeBreton East
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00023315
Former Bayview Landfill
Detailed testing completed. Remediation / risk management planned. 2023-2024 2 Medium Priority for Action 05 Detailed Testing Program
00023306
Victoria Island
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
00023304
Former Dow's Lake Landfill and Commissioner's Park
Detailed testing completed. No further action required. 2018-2019 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00023303
Champagne Corridor, Breezehill Ave At Somerset Street
Detailed testing completed. No further action required. 2015-2016 3 Low Priority for Action 05 Detailed Testing Program
00023301
90 Bayview Rd
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023300
100 Bayview Road
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00023298
Ottawa River Parkway, North of Bayview Road
Initial testing completed. Detailed testing underway. 2023-2024 1 High Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00022846
Nicholas and Queensway
Detailed testing completed. No further action required. 2018-2019 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00022834
Land East of Tailrace - LeBreton
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00022831
Bayview
Detailed testing completed. Remedial action plan under development. 2023-2024 1 High Priority for Action 06 Classify the site using the CCME National Classification System
00008424
Dow's Lake Armoury and Drill Hall
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00008423
Cartier Square Armoury,Frmr UST,along drill hall Queen E.Dr.
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00001700
Central Experimental Farm
Remediation / risk management completed. No further action required. 2022-2023 1 High Priority for Action 08 Implement Remediation/Risk Management Strategy
00001621
Central Experimental Farm
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00001620
Central Experimental Farm
Initial testing completed. No further action required. 2015-2016   03 Initial Testing Program
00001619
Central Experimental Farm
Initial testing completed. No further action required. 2015-2016 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00001618
Central Experimental Farm
Remediation / risk management completed. No further action required. 2022-2023 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
00001542
Central Experimental Farm
Detailed testing completed. No further action required. 2015-2016 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00001541
Central Experimental Farm
Initial testing completed. No further action required. 2015-2016 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00001540
Central Experimental Farm
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000016
Riverfront Park
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00000015
LeBreton Flats - Nepean Bay
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000014
Lebreton South
Detailed testing completed. No further action required. 2007-2008 2 Medium Priority for Action 05 Detailed Testing Program
00000013
LeBreton Flats
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000012
LeBreton Flats
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000011
LeBreton Flats
Detailed testing completed. No further action required. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000010
LeBreton Flats
Detailed testing completed. No further action required. 2022-2023 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000009
LeBreton Flats
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000008
LeBreton Flats
Detailed testing completed. No further action required. 2019-2020 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000007
LeBreton Flats
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000006
LeBreton Flats
Detailed testing completed. Remedial action plan under development. 2023-2024 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
00000004
LeBreton Flats
Detailed testing completed. No further action required. 2014-2015 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System