Search Results

Search Results Summary
Criteria:
  • Federal Electoral District: Halifax
Select Additional Criteria...
Sort Key:Site Name (ascending)
Sites Found:153
Alternate Views
Choose an alternate view: Map XML CSV Financials Report
Results View Options

Results by Site Impact

Change results view to: Name and Location Contaminants and Media

FCSI Identifier
Site Name
Status Fiscal Year Classification Highest Step Completed
02907001
Disposed Willow Pk (4321) Frmr Heating Plant (EY4 CE Supply)
Confirmatory sampling completed. No further action required. 2019-2020 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02907005
Disposed - Willow Park (4325) - CE Production Centre (EY5)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02919008
Dockyard (1008) - SRU Building Bosuns Shops (D125)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02919011
Dockyard (1011) - Inflammable Stores (D57)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919015
Dockyard (1015) - Underwater Repair building (D53)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919017
Dockyard (1017) - Outside Fitters and Machine Shop (D108)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919023
Dockyard (1023) - Corrosion Prevention & Sub Squadron
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919028
Dockyard (1028) - HazMat Facility (D207)
Initial testing completed. No further action required. 2002-2003   03 Initial Testing Program
02919046
Dockyard (1032) - Fomer CN Rail Line btwn parking & building
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02859005
Wrights Cove (8601) - Former Above Ground Fuel Lines
Confirmatory sampling completed. No further action required. 2013-2014 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02859050
Wrights Cove (8608) - National Gypsum Leased property
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919005
Dockyard (1005) - PMQ's and Garage (D77, D78, D79 & D81)
Remediation / risk management completed. No further action required. 2014-2015 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919006
Dockyard (1006) - Pollution Control DREA (D17)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919009
Dockyard (1009) - Base Exchange (D82)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02919010
Dockyard (1010) - Electronics Shop (D20)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919012
Dockyard (1012) - Base Fire Hall (D196)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02919014
Dockyard (1014) - Main Base Supply (D206)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919016
Dockyard (1016) - Central Heating Plant (D62)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919020
Dockyard (1020) - SRU Main Building (D200)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919021
Dockyard (1021) - Submarine Shelter (D170)
Initial testing completed. Detailed testing underway. 2023-2024 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02919024
Dockyard (1024) - FMG and SRU (D166)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919026
Dockyard (1026) - Base Transport (D172)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02919029
Dockyard (1029) - Rectifier Building (D47)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919031
Dockyard (1031) - Transformers East of Building D14
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919041
Dockyard (1033) - Former B122 and 60
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919047
Dockyard (1034) - Former D7
Remediation / risk management completed. No further action required. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919035
Dockyard (1035) - Former D15
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919048
Dockyard (1036) - Former D17
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919036
Dockyard (1037) - Former D19
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919039
Dockyard (1038) - Former D88
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919037
Dockyard (1039) - Former D95
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919040
Dockyard (1040) - Former D20
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919049
Dockyard (1041) - Fomer D49
Remediation / risk management completed. No further action required. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02919042
Dockyard (1042) - Former D159
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919050
Dockyard (1043) - Former D59
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919043
Dockyard (1044) - Former D127
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919044
Dockyard (1045) - Former D109
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919045
Dockyard (1046) - Former D63
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919038
Dockyard (1047) - Former D71
Historical review completed. No further action required. 2000-2001 N Not a Priority for Action 02 Historical Review
02919003
Dockyard (1003) - Rectifier House (D74)
Initial testing completed. No further action required. 2000-2001 3 Low Priority for Action 03 Initial Testing Program
02919007
Dockyard (1007) - Sheet metal & Refrig. Shops (D19)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02919013
Dockyard (1013) - Base Supply (D40 and D155)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919019
Dockyard (1019) - Packing and Preservation Bldg (D67)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919025
Dockyard (1025) - Shipwrights Shop (D174)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919030
Dockyard (1030) - Maritime Command Headquarters (D14)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02898001
Bedford Basin Measured Mile Beacon - PCB, PAH, and metals in sediments of Waterlot
Initial testing completed. No further action required. 2023-2024   03 Initial Testing Program
02914001
Halifax Armoury Building (2201) - Main Armoury Building
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02858006
Bedford Rifle Range (706) - Office Building (B47)
Confirmatory sampling completed. No further action required. 2009-2010 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00027546
Olde Barrels Cove
Initial testing completed. Detailed testing underway. 2023-2024   03 Initial Testing Program
00000957
Disposed - Ahern Avenue (302) - Building 3
Initial testing completed. No further action required. 2011-2012 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
02907002
Disposed - Willow Park (4322) - Paint Shop (EY7)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02859049
CFAD Bedford (805) - Pump House with AST (B192)
Initial testing completed. No further action required. 2009-2010 N Not a Priority for Action 03 Initial Testing Program
02859012
CFAD Bedford (813) - B157, B158, B33*
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
02859016
CFAD Bedford (817) - Former Transformer Huts*
Long term monitoring completed. No further action required. 2013-2014 N Not a Priority for Action 10 Long-Term Monitoring (Optional)
02859004
CFAD Bedford (804) - Torpedo Dye Disposal Area - East B75
Long term monitoring completed. No further action required. 2013-2014 3 Low Priority for Action 10 Long-Term Monitoring (Optional)
03044004
DCD School (904) - Possible Former Greenhouse
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
03044007
DCD School (907) - Fire Fighting Training Area
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
03044009
DCD School (909) - Creek, Lagoon and Beach
Confirmatory sampling completed. No further action required. 2019-2020 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
03044010
DCD School (910) - Former Ordnance Demolition Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
03044011
DCD School (911) - Construction Debris Site
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
52106002
Fergusons Cove (1501) - Sound Range Building
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
00012305
Pennant Harbour - Barium and Lead in Soil
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00025108
HMC Dockyard Halifax PFAS Sitewide
Historical review planned. 2023-2024   01 Identify Suspect Sites
00000857
Bettys Island - Metals, Hydrocarbons and PAH contamination
Confirmatory sampling completed. No further action required. 2013-2014 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00011532
Sable Island - AEC 2 - PHC Impact in Soil at AEB Tank Farm
Detailed testing completed. No further action required. 2010-2011 2 Medium Priority for Action 06 Classify the site using the CCME National Classification System
02884001
Melville Island (5901) - Marina Storage (B1)
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884002
Melville Island (5902) - Old Ice House (B2)
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884003
Melville Island (5903) - Clubhouse (B4)
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884004
Melville Island (5904) - Marina Storage (B6)
Remediation / risk management completed. No further action required. 2019-2020 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
02884006
Melville Island (5906) - Workshop (B8)
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884007
Melville Island (5907) - Former Chapel Site (B10)
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884009
Melville Island (5909) - Marina Railway Site
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884010
Melville Island (5910) - Fuel Storage/Dispensing Area
Confirmatory sampling completed. No further action required. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02884011
Melville Island (5911) - Cradle Yard
Confirmatory sampling completed. No further action required. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02884012
Melville Island (5912) - Mooring Field
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884013
Melville Island (5913) - Causeway
Initial testing completed. No further action required. 2000-2001 N Not a Priority for Action 03 Initial Testing Program
07610122
Sable Island
Remedial action plan completed. Remediation / risk management underway. 2023-2024 1 High Priority for Action 07 Develop Remediation/Risk Management Strategy
00011540
Sable Island - APEC 10 - Abandonned Landfill
Initial testing completed. No further action required. 2013-2014 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
81514001
Sable Island - Hydrocarbon Impacts in West Light A
Confirmatory sampling completed. No further action required. 2021-2022 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
00011535
Sable Island - AEC 9 - Metal Impact in Groundwater at AEB Compound
Detailed testing completed. No further action required. 2010-2011 N Not a Priority for Action 06 Classify the site using the CCME National Classification System
00017473
Saul Island - Metals in Soil
Initial testing completed. No further action required. 2012-2013 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017326
Ketch Harbour Remote Receiver (Unassessed)
Historical review not required. 2013-2014   01 Identify Suspect Sites
00012985
Fort Massey Cemetery
Historical review completed. No further action required. 2023-2024   02 Historical Review
00017368
Lower Prospect (No Soil)
Historical review completed. No further action required. 2009-2010   02 Historical Review
02916001
RA Park (3301) - Officers Mess (RA1)
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
02916002
RA Park (3302) - Office Facility (RA2)
Long term monitoring completed. No further action required. 2022-2023 2 Medium Priority for Action 10 Long-Term Monitoring (Optional)
02918021
Willow Park (4301) - Base Maintenance HQ & Shops (WL1)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918001
Willow Park (4302) - Base Maintenance Shops (WL2)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918002
Willow Park (4303) - Base Maintenance Shops (WL3)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918004
Willow Park (4305) - Base Maintenance Shop (WL9)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918010
Willow Park (4311) - Canex (WL30)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918011
Willow Park (4312) - RCCS Garage (WL31)
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918012
Willow Park (4313) - POL Shed (WL33)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918013
Willow Park (4314) - Vehicle Paint Shop (WL34)
Confirmatory sampling completed. No further action required. 2018-2019 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918022
Willow Park (4320) - Salt Dome (WL36)
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00008521
Willow Park (4327) - TEME North Site
Remedial action plan completed. Remediation / risk management underway. 2023-2024 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
00008522
Willow Park (4328) - Armoury South Site
Detailed testing completed. Remediation / risk management planned. 2023-2024 I Insufficient Information 05 Detailed Testing Program
02907006
Willow Park POL Stores (4323)
Initial testing completed. No further action required. 2001-2002   03 Initial Testing Program
02918005
Willow Park (4306) - Utilities Shed (WL15) & Former WL34*
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918007
Willow Park (4308) - Outdoor POL Storage Area (Fmr WL24)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918008
Willow Park (4309) - Former Radioactive Pit (Fmr WL27)
Confirmatory sampling completed. No further action required. 2019-2020 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02918015
Willow Park (4316) - Former Outdoor Bulk POL Storage WL39*
Confirmatory sampling completed. No further action required. 2018-2019 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02918017
Willow Park (4318) - Suspect Fmr Grease/Oil Pit (WL17)
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
03002006
Windsor Park (4505) - PMQ Barracks
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 N Not a Priority for Action 08 Implement Remediation/Risk Management Strategy
03002005
Windsor Park (4504) - Military Police (WP92)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
03002009
Windsor Park (4508) - Former Rifle Range (WP11 & WP30)
Initial testing completed. No further action required. 2017-2018 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03002012
Windsor Park (4509) - PMQ's (WP4, WP5 & WP9 - WP12)
Initial testing completed. No further action required. 2011-2012 N Not a Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
03002011
Windsor Park (4510) - School Property (fmr WP42)
Initial testing completed. No further action required. 2000-2001 N Not a Priority for Action 03 Initial Testing Program
03002008
Windsor Park - Former RCE Garage (4507)
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
03002002
Windsor Park (4501) - CHP (WP62) & POL Shed (WP58)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
00017566
Sackville River Fishway - Unassessed
Historical review not required. 2012-2013   01 Identify Suspect Sites
02919032
Water Lots (9908) - Dockyard
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 1 High Priority for Action 09 Confirmatory Sampling and Final Reporting
02913001
Water Lots (9911) - HMCS Scotian
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00017900
SAMBRO (PAHs and Metals in Sediment)
Initial testing completed. Detailed testing underway. 2023-2024 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00017907
Shad Bay- (No Impacts Identified)
Historical review completed. No further action required. 2008-2009 N Not a Priority for Action 02 Historical Review
00008393
LST 209 deep ocean disposal site
Initial testing completed. No further action required. 2010-2011 I Insufficient Information 03 Initial Testing Program
02921001
Disposed - South & Harvey St (3501) - Main Marcom Building
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
02920001
Stadacona (3701) - Heating Plant (S11)
Confirmatory sampling completed. No further action required. 2019-2020 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02920002
Stadacona (3702) - Diesel Shop (S88)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02920003
Stadacona (3703) - Protestant & RC Chapel (S7)
Initial testing completed. No further action required. 2000-2001   03 Initial Testing Program
02920005
Stadacona (3705) - CE Production Centre (S30)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02920007
Stadacona (3707) - CFIC Building (S89)
Confirmatory sampling completed. No further action required. 2022-2023 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02920009
Stadacona (3708) - Gardens - rear of Bldg S52(Admiral's Res)
Confirmatory sampling completed. No further action required. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02920011
Stadacona (7601) - Queens Printer Bulding S93 EPRINTIT
Historical review completed. No further action required. 2001-2002 N Not a Priority for Action 02 Historical Review
02920013
Stadacona (7603) - Queens Printer Bldf S93 Tattoo Off./Stge
Historical review completed. No further action required. 2001-2002 N Not a Priority for Action 02 Historical Review
02920014
Stadacona (7604) - Queens Printer Bldg S93 Furn./Coal chute
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy
00027605 Initial testing completed. Detailed testing underway. 2022-2023 2 Medium Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00027606 Initial testing completed. Detailed testing underway. 2022-2023 3 Low Priority for Action 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00013454
Tantallon RCMP
Initial testing completed. No further action required. 2009-2010   03 Initial Testing Program
00000855
Terence Bay (remediation complete)
Confirmatory sampling completed. No further action required. 2008-2009 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
00017922
TERENCE BAY (No Hydrocarbons in Soil)
Initial testing completed. No further action required. 2012-2013   03 Initial Testing Program
00017433
Terence Bay Graveyard (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017931
UPPER PROSPECT (Unassessed)
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017455
Prospect Wharf (No Issues)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00017500
Terence Bay Wharf (No Soil)
Historical review completed. No further action required. 2009-2010   02 Historical Review
00017550
Halifax Lab Complex (Unassessed)
Historical review not required. 2013-2014   01 Identify Suspect Sites
00017838
LOWER PROSPECT (no land based contamination CLOSE)
Historical review completed. No further action required. 2012-2013   02 Historical Review
00017896
PROSPECT - unassessed Divested and Closed
Historical review not required. 2012-2013   01 Identify Suspect Sites
00017923
TERENCE BAY (Sediment Impacts)
Initial testing completed. Detailed testing underway. 2023-2024 I Insufficient Information 04 Pre-Classify contaminated site using the CCME National Classification System (optional)
00027770
Georges Island National Historic Site
Remediation / risk management completed. No further action required. 2021-2022 2 Medium Priority for Action 08 Implement Remediation/Risk Management Strategy
02859015
CFAD Bedford (816) - Ammunition Disposal Furnace (BD188)
Initial testing completed. No further action required. 2009-2010 N Not a Priority for Action 03 Initial Testing Program
02884005
Melville Island (5905) - Bubbler Shed (B7)
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02884008
Melville Island (5908) - Boat Storage/Parking Lot Site
Detailed testing completed. No further action required. 2019-2020 3 Low Priority for Action 07 Develop Remediation/Risk Management Strategy
02918006
Willow Park (4307) - Former Service Station (WL23)
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918014
Willow Park (4315) - Outdoor Coiled Wire Storage area
Confirmatory sampling completed. No further action required. 2017-2018 N Not a Priority for Action 09 Confirmatory Sampling and Final Reporting
02918018
Willow Park (4319) - Vehicle Maintenance Garage WL22
Confirmatory sampling completed. No further action required. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919001
Dockyard (1001) - CE Office and Shops (D2)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 3 Low Priority for Action 09 Confirmatory Sampling and Final Reporting
02919004
Dockyard (1004) - Mainguy Building (D201)
Confirmatory sampling completed. Long term monitoring underway. 2023-2024 2 Medium Priority for Action 09 Confirmatory Sampling and Final Reporting
02920004
Stadacona (3704) - Pump House (S41)
Historical review completed. No further action required. 2000-2001   02 Historical Review
02920012
Stadacona (7602) - Queens Printer Bldg S93 Trident Offices
Historical review completed. No further action required. 2001-2002 N Not a Priority for Action 02 Historical Review
03002004
Windsor Park (4503) - Former Heating Plant (WP45)
Initial testing completed. No further action required. 2000-2001 N Not a Priority for Action 03 Initial Testing Program
03002007
Windsor Park (4506) - Former Gas Chamber (WP49)
Initial testing completed. No further action required. 2001-2002 N Not a Priority for Action 03 Initial Testing Program
03044008
DCD School (908) - Contaminated Spoil Fill Area
Remediation / risk management completed. Confirmatory sampling underway. 2023-2024 3 Low Priority for Action 08 Implement Remediation/Risk Management Strategy