Results by Site Impact
Change results view to: Name and Location Contaminants and Media
FCSI Identifier Site Name |
Status | Fiscal Year | Classification | Highest Step Completed |
---|---|---|---|---|
00001290
ASH RIVER BELOW MORAN CREEK |
Confirmatory sampling completed. No further action required. | 2010-2011 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00001293
MURRAY CREEK AT 216 STREET, LANGLEY |
Confirmatory sampling completed. No further action required. | 2010-2011 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00002508
Port Hardy, BC (Consolidated) |
Initial testing completed. No further action required. | 2019-2020 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00002565
Zeballos River Near Zeballos |
Confirmatory sampling completed. No further action required. | 2010-2011 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00003180
SLESSE CREEK NEAR VEDDER CROSSING |
Confirmatory sampling completed. No further action required. | 2009-2010 | 2 Medium Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00006595
686 - Bonaparte - 07165 - BONAPARTE 3 - 7000082196 |
Initial testing completed. Detailed testing underway. | 2022-2023 | 2 Medium Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00006606
84 - Montagnais de Unamen Shipu - 06109 - ROMAINE 2 - 0302648806 |
Remediation / risk management completed. No further action required. | 2014-2015 | 3 Low Priority for Action | 08 Implement Remediation/Risk Management Strategy |
00006764
538 - Heiltsuk - 07857 - BELLA BELLA 1 - 0903014806 |
Confirmatory sampling completed. No further action required. | 2018-2019 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
00007599
051 - Listuguj Mi'gmaq Government - 06088 - LISTUGUJ - 0304233709 |
Historical review completed. No further action required. | 2010-2011 | 02 Historical Review | |
00014403
Hawkins Island - Surrounding structure |
Detailed testing completed. Remedial action plan under development. | 2022-2023 | 1 High Priority for Action | 06 Classify the site using the CCME National Classification System |
00015311
Good Harbour Range Front - No Contamination Identified |
Initial testing completed. No further action required. | 2014-2015 | 03 Initial Testing Program | |
00015312
Good Harbour Range Rear - No Contamination Identified |
Initial testing completed. No further action required. | 2014-2015 | 03 Initial Testing Program | |
00024121
DOME LAKE (LAMBERT VEIN, TT) |
Initial testing completed. Detailed testing underway. | 2022-2023 | 1 High Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00024692
Manhattan Building |
Initial testing completed. No further action required. | 2015-2016 | N Not a Priority for Action | 04 Pre-Classify contaminated site using the CCME National Classification System (optional) |
00027533
Gordie Howe International Bridge |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09401040
Alaska Highway - Steamboat Maintenance Camp |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09401050
Alaska Highway - Toad River Maintenance Camp |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09401060
Alaska Highway - Muncho Lake Maintenance Camp |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09401080
Alaska Highway - Fireside Maintenance Camp |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 2 Medium Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09401090
Alaska Highway - Iron Creek Maintenance Camp |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
09401270
Alaska Highway - Former Military Establishment (Ft Nelson Rec Centre) P-08I |
Confirmatory sampling completed. No further action required. | 2019-2020 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
09401280
Alaska Highway - Former Kledo Creek Bridge Construction Camp R-01 |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 1 High Priority for Action | 07 Develop Remediation/Risk Management Strategy |
11022121
Foxfield Battle Assault Range |
Remedial action plan completed. Remediation / risk management underway. | 2022-2023 | 3 Low Priority for Action | 07 Develop Remediation/Risk Management Strategy |
11022122
CAEN Battle Assault Range |
Initial testing completed. No further action required. | 2018-2019 | 03 Initial Testing Program | |
20624001
Former St-Germain Foundry inc. |
Confirmatory sampling completed. Long term monitoring underway. | 2022-2023 | 1 High Priority for Action | 09 Confirmatory Sampling and Final Reporting |
20832120
Cambridge Bay Upper Air Station (Consolidated) |
Detailed testing completed. Remediation / risk management planned. | 2022-2023 | 2 Medium Priority for Action | 05 Detailed Testing Program |
23148001
Contrecoeur landfill |
Remediation / risk management completed. Confirmatory sampling underway. | 2022-2023 | 1 High Priority for Action | 08 Implement Remediation/Risk Management Strategy |
- Version: