Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Table 1: Details on Transfer Payments Programs (TPP)

Infrastructure Canada will manage the following transfer payment programs in excess of $5 million annually:

The summary of the Three-Year Plan for Transfer Payment Programs, as prescribed by the Policy on Transfer Payments, will be available at the latest June 30, 2009, at: http://www.infc.gc.ca/infc-eng.html/.


Canada Strategic Infrastructure Fund

1. Name of transfer payment program: Canada Strategic Infrastructure Fund

2. Start date: 2003-04

3. End date: 2012-13

4. Description: Directed to projects of major federal and regional significance in areas that are vital to sustaining economic growth and enhancing the quality of life of Canadians.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: Safer and improved water quality in major communities; safer and faster movement of people and goods on Canada's major land transportation routes; reduced production of greenhouse gases and airborne pollutants; more-effective urban development; increased economic activity including tourism.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending
2009-10
9. Planned Spending
2010-11
10. Planned Spending
2011-12
11. Program activity Targeted Project-Based Infrastructure Funding        
12. Total grants        
12. Total contributions 732,502 513,410 385,851 268,981
12. Total other types of transfer payments        
13. Total program activity1 732,502 513,410 385,851 268,981
14. Planned evaluations Formative Formal    
15. Planned audits   Assurance Follow-up Audit    

1 Total program activity numbers include $81.7 million in 2008-09, $89.1 million in 2009-10, $47.8 million in 2010-11, and $2.2 million in 2011-12, from funds provided under the Building Canada Fund.


Border Infrastructure Fund

1. Name of transfer payment program: Border Infrastructure Fund

2. Start date: 2003-04

3. End date: 2013-14

4. Description: Targets Canada-United States border crossing points and activity funding for investments in physical infrastructure, intelligent transportation system infrastructure and improved analytical capacity.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: A reduction in border bottlenecks; greater uptake of border fast tracking programs by frequent users; expansion or improvement in border/system capacity.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending
2009-10
9. Planned Spending
2010-11
10.Planned Spending
2011-12
11. Program activity Targeted Project-Based Infrastructure Funding        
12. Total grants        
12. Total contributions 114,383 66,715 46,722 39,069
12. Total other types of transfer payments        
13. Total program activity 114,383 66,715 46,722 39,069
14. Planned evaluations Formative Formal    
15. Planned audits   Assurance Follow-up Audit    


Municipal Rural Infrastructure Fund

1. Name of transfer payment program: Municipal Rural Infrastructure Fund

2. Start date: 2004-05

3. End date: 2010-11

4. Description: To support smaller-scale municipal infrastructure projects that improve the quality of life, sustainable development and economic opportunities, particularly of smaller communities.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: Improved and increased stock of core public infrastructure in areas such as water, wastewater, culture and recreation; improved quality of life and economic opportunities for smaller communities.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending
2009-10
9. Planned Spending
2010-11
10. Planned Spending
2011-12
11. Program activity Targeted Project-Based Infrastructure Funding        
12. Total grants        
12. Total contributions 399,885 483,763 36,233 0
12. Total other types of transfer payments        
13. Total program activity1 399,885 483,763 36,233 0
14. Planned evaluations Formative Formal   Summative
15. Planned audits Assurance Audit   Assurance Follow-up Audit  

1 Total program activity numbers include $50.4 million in 2008-09, $113.6 million in 2009-10, and $25.0 million in 2010-11, from funds provided under the Building Canada Fund.


Research, Knowledge and Outreach Program

1. Name of transfer payment program: Research, Knowledge and Outreach Program

2. Start date: 2004-05

3. End date: 2009-10

4. Description: To enhance implementation of Infrastructure Canada's Research Strategy, which focuses on three components: knowledge generation, community-building, and knowledge transfer.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: Greater understanding of the role and significance of infrastructure and infrastructure issues; more informed policy and decision making; increased knowledge of infrastructure, including infrastructure development, governance arrangements, best practices, shared federal experiences and emerging challenges and opportunities.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending
2009-10
9. Planned Spending
2010-11
10. Planned Spending
2011-12
11. Program activity Knowledge and Research        
12. Total grants        
12. Total contributions 3,408 2,055 0 0
12. Total other types of transfer payments        
13. Total program activity 3,408 2,055 0 0
14. Planned evaluations   Summative    
15. Planned audits   Assurance Audit Assurance Follow-up Audit  


Gas Tax Fund

1. Name of transfer payment program: Gas Tax Fund

2. Start date: 2005-06

3. End date: Ongoing

4. Description: The Gas Tax Fund program strives to meet the diverse infrastructure needs of all communities while contributing to national environmental outcomes. The Gas Tax Fund makes capital investments in environmentally sustainable municipal infrastructure to improve water and air quality and reduce greenhouse gas emissions. It is designed to build competitive and sustainable communities by providing reliable, predictable up-front funding for eligible investments in water, wastewater, solid waste, public transit, community energy systems and local roads and bridges.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: To support environmentally sustainable infrastructure in support of shared national outcomes. Theses outcomes are cleaner air, cleaner water, and reduced greenhouse gas emissions.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending
2009-10
9. Planned Spending
2010-11
10. Planned Spending
2011-12
11. Program activity Gas Tax Fund        
12. Total grants        
12. Total contributions        
12. Total other types of transfer payments 1,012,134 1,974,980 1,974,452 1,974,452
13. Total program activity 1,012,134 1,974,980 1,974,452 1,974,452
14. Planned evaluations Process, Summative Formal Value-for-Money  
15. Planned audits Assurance audit   Assurance Follow-up Audit  


Provincial-Territorial Base Funding Program

1. Name of transfer payment program: Provincial-Territorial Base Funding Program

2. Start date: 2007-08

3. End date: 2013-14

4. Description: These funds will provide greater flexibility to address infrastructure needs, particularly for the benefit of smaller jurisdictions which need to respond to basic needs regardless of the size of their population.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: To promote enhanced competitiveness and productivity of the economy; cleaner air, water and land; stronger and healthier communities; and to support the restoration of the fiscal balance.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending1
2009-10
9. Planned Spending1
2010-11
10.Planned Spending1
2011-12
11. Program activity Provincial-Territorial Infrastructure Base Fund        
12. Total grants        
12. Total contributions        
12. Total other types of transfer payments 654,486 823,563 824,196 0
13. Total program activity 654,486 823,563 824,196 0
14. Planned evaluations     Formative  
15. Planned audits   Assurance Audit    

1. Actual annual spending levels will be based on the number of jurisdictions that agree to match accelerated P\T Base funds.


Building Canada Fund

1. Name of transfer payment program: Building Canada Fund

2. Start date: 2008-09

3. End date: 2016-17

4. Description: To invest in provincial and community infrastructure to address both national, provincial/territorial and community priorities.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: To promote a stronger economy, a cleaner environment, and stronger and safer communities.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending1
2009-10
9. Planned Spending1
2010-11
10.Planned Spending1
2011-12
11. Program activity Targeted Project-Based Infrastructure Funding        
12. Total grants        
12. Total contributions 522,776 1,229,394 1,575,817 1,641,427
12. Total other types of transfer payments        
13. Total program activity2 522,776 1,229,394 1,575,817 1,641,427
14. Planned evaluations       Joint Formative
15. Planned audits     Assurance Audit  

1. Actual annual spending levels will be based on the number of jurisdictions that agree to match accelerated BCF funds.

2. Total program activity numbers include $132.1 million in 2008-09, $202.6 million in 2009-10, $72.9 million in 2010-11 and $2.2 million for 2011-12 in funding for projects which are managed under CSIF and MRIF program mechanisms.


Green Infrastructure Fund

1. Name of transfer payment program: Green Infrastructure Fund

2. Start date: 2009-10

3. End date: 2013-14

4. Description: Green infrastructure includes infrastructure that supports a focus on the creation of sustainable energy such as modern energy transmission lines. Budget 2009 provides $1 billion over five years for the Green Infrastructure Fund. Funding will be allocated based on merit to support green infrastructure projects on a cost-shared basis.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: Targeted investments in green infrastructure can improve the quality of the environment and will lead to a more sustainable economy over the longer term. Sustainable energy infrastructure will contribute to improved air quality and lower carbon emissions.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending
2009-10
9. Planned Spending
2010-11
10. Planned Spending
2011-12
11. Program activity Targeted Project-Based Infrastructure Funding        
12. Total grants        
12. Total contributions   200,000 200,000 200,000
12. Total other types of transfer payments        
13. Total program activity   200,000 200,000 200,000
14. Planned evaluations        
15. Planned audits        


Infrastructure Stimulus Fund

1. Name of transfer payment program: Infrastructure Stimulus Fund

2. Start date: 2009-10

3. End date: 2010-11

4. Description: Budget 2009 establishes a new $4-billion Infrastructure Stimulus Fund that will provide funding to provincial, territorial and municipal infrastructure rehabilitation projects. Funding will be available for two years for projects that will begin construction during the 2009 and 2010 construction seasons. Should agreements not be reached expeditiously with a province or territory, funding may be used to support the rehabilitation of federal or other infrastructure.

5. Strategic outcome(s): Quality, cost-effective public infrastructure that meets the needs of Canadians in a competitive economy, a clean environment and liveable communities.

6. Expected results: The rehabilitation work will help maintain the safety and prolong the economic life of assets that were built decades ago.


(in $ thousands) 7. Forecast Spending
2008-09
8. Planned Spending
2009-10
9. Planned Spending
2010-11
10. Planned Spending
2011-12
11. Program activity Targeted Project-Based Infrastructure Funding        
12. Total grants        
12. Total contributions   2,000,000 2,000,000 0
12. Total other types of transfer payments        
13. Total program activity   2,000,000 2,000,000 0
14. Planned evaluations        