Site N0281023 - Old U.S. Military Section Dump- APEC 2
-
Status
Remediation / risk management completed. No further action required. -
Site Status
Closed -
Classification
Insufficient Information
Site Details
-
Reporting Organization
-
Reason for Involvement
Contractual obligation -
Property Type
Non-Federal (Provincial Government)
Site Location
-
Latitude, Longitude
60.117778, -128.821944 -
Municipality
Yukon, Unorganized, YT -
Federal Electoral District
Yukon
Contaminant Details
Contamination Estimate
-
Hectares
0
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
Metal, metalloid, and organometallic | Groundwater |
Action Plan
2020/21 - 1 well was sampled for COC as part of the Yukon Groundwater Monitoring Program. This well was decommissioned following the results. 2018/19 - 2 wells sampled for Contaminants of Concern as part of the Yukon Groundwater Monitoring Program 2017/18 - Installed 1 groundwater monitoring well and sampled for COC as part of the Yukon Groundwater Monitoring Program Since no contaminants of concern (CoC) were identified at this site, site closure is recommended. This involves the placement of a vegetated earthen cap over the remaining debris to minimize further erosion and exposure of buried debris.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 34 |
10 km | 979 |
25 km | 1,152 |
50 km | 1,273 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$22,806.97 -
Remediation
$9,771.90 -
Care & Maintenance
$4,000.00
Financial/Annual Information
- 2020-2021
- 2019-2020
- 2018-2019
- 2017-2018
- 2014-2015
- 2013-2014
- 2012-2013
- 2011-2012
- 2010-2011
- 2009-2010
- 2008-2009
- 2007-2008
- 2006-2007
- 2005-2006
2020-2021
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$8,043.15Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2019-2020
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$4,199.97Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2013-2014
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
08 Implement Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$12,607.00Total Remediation Expenditure
$1,728.75Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Transport CanadaInternal Identifier
N0281023Highest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$6,000.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$4,000.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 37.1