Site N0002020 - Sanitary Sewer Line & Combined Services Building
-
Status
Remedial action plan completed. Remediation / risk management underway. -
Site Status
Active -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Contractual obligation -
Property Type
Non-Federal (Private Sector)
Site Location
-
Latitude, Longitude
48.543889, -58.564722 -
Municipality
Stephenville, NL -
Federal Electoral District
Long Range Mountains
Contaminant Details
Contamination Estimate
-
Cubic Meters
10
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Action Plan
Monitoring of groundwater impacts for site closure on-going.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 875 |
5 km | 8,044 |
10 km | 10,356 |
25 km | 16,414 |
50 km | 27,540 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$179,852.78 -
Remediation
$936,880.08
FCSAP Expenditures
-
Assessment
$82,621.18 -
Remediation
$758,840.08
Financial/Annual Information
- 2021-2022
- 2020-2021
- 2019-2020
- 2018-2019
- 2017-2018
- 2016-2017
- 2015-2016
- 2014-2015
- 2013-2014
- 2012-2013
- 2011-2012
- 2010-2011
- 2009-2010
- 2008-2009
- 2007-2008
- 2006-2007
- 2005-2006
2021-2022
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$223,504.54Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$189,978.86FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$244,614.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$207,921.90FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$96,895.20Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$148,000.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$148,000.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$115,000.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$115,000.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$97,939.32Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$97,939.32FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$7,699.65Total Remediation Expenditure
$300.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$600.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$14,859.29Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$74,672.66Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$44,831.84Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$44,831.84FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$37,789.34Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$37,789.34FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$10,027.02Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Transport CanadaInternal Identifier
N0002020Highest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 39