Site 19536001 - Klemtu
-
Status
Long term monitoring completed. No further action required. -
Site Status
Closed -
Classification
Not a Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
A reserve as defined in the Indian Act -
Property Type
Canada Lands
Site Location
-
Latitude, Longitude
52.59339, -128.53409 -
Municipality
Kitasoo 1, BC -
Federal Electoral District
Skeena--Bulkley Valley
Site Management Strategy
- Remediation
Contaminant Details
Contamination Estimate
-
Cubic Meters
2
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Soil |
Action Plan
In 2000, petroleum hydrocarbon contaminated soil was identified at the health centre: the aboveground storage tank at the health clinic, and the aboveground storage tank at the nurse's residence. Soil remediation was carried out in 2003. Follow-up sampling in 2005 indicate that less than 5 cubic metres of contaminated oil remained at the nurse's residence. An environmental site assessment conducted in February 2007 confirmed four areas of petroleum hydrocarbon soil contamination: at the aboveground storage tank at the health clinic, at the aboveground storage tank at the generator shed, at the trailer residence, and to the east of the trailer residence. Remediation was completed in the four areas that were impacted and a total of 2 cubic metres of soil was removed and placed in a biocell in the community. Site remediated.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 199 |
5 km | 349 |
10 km | 349 |
25 km | 349 |
50 km | 349 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$41,500.00 -
Remediation
$60,610.64
FCSAP Expenditures
-
Assessment
$41,500.00
Financial/Annual Information
2008-2009
Reporting Organization
Health CanadaInternal Identifier
540-KL-02Highest Step Completed
10 Long-Term Monitoring (Optional)Total Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
2 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
Yes
2007-2008
Reporting Organization
Health CanadaInternal Identifier
540-KL-02Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$60,610.64Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Health CanadaInternal Identifier
540-KL-02Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$41,500.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$41,500.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
2.75 m3Actual Hectares Remediated
0 haActual Tons Remediated
5.5 tClosed
No
2005-2006
Reporting Organization
Health CanadaInternal Identifier
540-KL-02Highest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
2.75 m3Actual Hectares Remediated
0 haActual Tons Remediated
5.5 tClosed
No
- Version:
- 37.1