Site 10855009 - Golfland Area 6 PCB Site (Former Sub-station) - London Airport
-
Status
Remedial action plan completed. Remediation / risk management underway. -
Site Status
Active -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 10855)
Site Location
-
Latitude, Longitude
43.022222, -81.150833 -
Municipality
London, ON -
Federal Electoral District
London--Fanshawe
Contaminant Details
Contamination Estimate
-
Hectares
1
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PAHs (polycyclic aromatic hydrocarbon) | Surface water |
PAHs (polycyclic aromatic hydrocarbon) | Groundwater |
PAHs (polycyclic aromatic hydrocarbon) | Sediment |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Surface water |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Sediment |
Metal, metalloid, and organometallic | Soil |
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) | Groundwater |
PCBs (Polychlorinated Biphenyl) and PCDD/Fs (polychlorinated dibenzo-p-dioxin/dibenzofuran) | Soil |
Other organics | Not Available |
Other Physical/Chemical (pH, temperature, dissolved solids, turbidity, etc.) | Groundwater |
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 97 |
5 km | 41,437 |
10 km | 193,799 |
25 km | 445,256 |
50 km | 721,524 |
Summary of Annually Reported Data
Total Expenditures
-
Remediation
$97,728.93
Financial/Annual Information
- 2023-2024
- 2022-2023
- 2021-2022
- 2020-2021
- 2019-2020
- 2018-2019
- 2017-2018
- 2016-2017
- 2015-2016
- 2014-2015
- 2013-2014
- 2012-2013
- 2011-2012
- 2010-2011
- 2009-2010
- 2008-2009
- 2007-2008
- 2006-2007
- 2005-2006
2023-2024
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2022-2023
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2021-2022
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$97,728.93Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2008-2009
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2007-2008
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2006-2007
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2005-2006
Reporting Organization
Transport CanadaInternal Identifier
10855009Highest Step Completed
07 Develop Remediation/Risk Management StrategyTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 41