Site 00026433 - Pukaskwa National Park Borrow Pit
-
Status
Classification completed. Remedial action plan under development. -
Site Status
Active -
Classification
Medium Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
National Park of Canada -
Property Type
Canada Lands
Site Location
-
Latitude, Longitude
48.291445, -86.134458 -
Municipality
Thunder Bay, Unorganized, ON -
Federal Electoral District
Algoma--Manitoulin--Kapuskasing
Site Management Strategy
- Assessment
Contaminant Details
Contamination Estimate
-
Cubic Meters
4,487
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Surface water |
PHCs (petroleum hydrocarbons) | Groundwater |
PHCs (petroleum hydrocarbons) | Surface soil |
PHCs (petroleum hydrocarbons) | Soil |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Surface water |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Groundwater |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Surface soil |
BTEXs (benzene, toluene, ethylbenzene, and xylene) | Soil |
Metal, metalloid, and organometallic | Soil |
Action Plan
The site is under assessment steps.
Additional Information
The site is located in a national park of Canada
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 0 |
5 km | 0 |
10 km | 0 |
25 km | 0 |
50 km | 1,998 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$198,256.84 -
Remediation
$78,300.61
FCSAP Expenditures
-
Assessment
$163,069.59 -
Remediation
$65,376.61
Financial/Annual Information
2023-2024
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$78,300.61Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$65,376.61FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2022-2023
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2021-2022
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$32,553.59Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$21,358.59FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
06 Classify the site using the CCME National Classification SystemTotal Assessment Expenditure
$41,233.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$31,076.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
04 Pre-Classify contaminated site using the CCME National Classification System (optional)Total Assessment Expenditure
$27,002.00Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$25,880.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$97,468.25Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$84,755.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
01 Identify Suspect SitesTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
Parks Canada AgencyInternal Identifier
AEPPUKT004Highest Step Completed
01 Identify Suspect SitesTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No