Site 00025803 - Institute for Research in Construction, Carleton Place
-
Status
Detailed testing completed. Remedial action plan under development. -
Site Status
Active -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 09388)
Site Location
-
Latitude, Longitude
45.175159, -76.182 -
Municipality
Mississippi Mills, ON -
Federal Electoral District
Lanark--Frontenac--Kingston
Site Management Strategy
- Assessment
Contaminant Details
Contamination Estimate
-
Cubic Meters
10,300
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
Metal, metalloid, and organometallic | Groundwater |
Other organics | Surface water |
Other organics | Groundwater |
Other organics | Soil |
Action Plan
Considerable environmental assessment work has been carried out on-site and off-site to reduce and mitigate risks to human health and the environment. An interim risk management strategy was established, including a remediation project (soil removal and bedrock capping, completed in summer-fall 2016) and installation of an on-site water treatment system (completed in winter 2023). Work is underway to update the long-term risk management strategy for the site, incorporating climate change considerations. Research activities at the site are suspended. The property and facility continue to be maintained and monitored for security.
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 83 |
5 km | 8,197 |
10 km | 25,786 |
25 km | 87,308 |
50 km | 1,036,016 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$2,840,370.95 -
Remediation
$4,768,978.33
FCSAP Expenditures
-
Assessment
$1,169,370.00 -
Remediation
$999,121.79
Financial/Annual Information
2021-2022
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$570,156.84Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$465,793.02FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2020-2021
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$616,366.29Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$480,328.77FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$1,212,900.59Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$860,704.16Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$829,606.43Total Remediation Expenditure
$447,319.81Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$445,000.00FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$1,087,908.40Total Remediation Expenditure
$1,061,530.64Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$667,000.00FCSAP Remediation Expenditure
$53,000.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
4681.92 tClosed
No
2015-2016
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
05 Detailed Testing ProgramTotal Assessment Expenditure
$590,217.34Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$274,768.78Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$27,870.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$27,870.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
National Research Council CanadaInternal Identifier
NRC- IRC Carleton PlaceHighest Step Completed
03 Initial Testing ProgramTotal Assessment Expenditure
$30,000.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$29,500.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 38