Site 00023977 - 160 Middle Street
-
Status
Confirmatory sampling completed. Long term monitoring underway. -
Site Status
Active -
Classification
High Priority for Action
Site Details
-
Reporting Organization
-
Reason for Involvement
Federal Real Property -
Property Type
Federal (DFRP Property Number 01918)
Site Location
-
Latitude, Longitude
45.419112, -75.715639 -
Municipality
Ottawa, ON -
Federal Electoral District
Ottawa Centre
Site Management Strategy
- Additional assessment
- Risk Management
Contaminant Details
Contamination Estimate
-
Hectares
0
The following contaminated media was identified on the site:
Contaminant Type | Medium Type |
---|---|
PHCs (petroleum hydrocarbons) | Soil |
PAHs (polycyclic aromatic hydrocarbon) | Soil |
Metal, metalloid, and organometallic | Groundwater |
Metal, metalloid, and organometallic | Soil |
Population
This table contains the population estimates at distances around the site.
Radius | Population |
---|---|
1 km | 8,252 |
5 km | 223,239 |
10 km | 643,239 |
25 km | 1,220,598 |
50 km | 1,437,710 |
Summary of Annually Reported Data
Total Expenditures
-
Assessment
$42,802.18 -
Remediation
$59,599.00
FCSAP Expenditures
-
Assessment
$40,760.70 -
Remediation
$50,660.00
Financial/Annual Information
- 2020-2021
- 2019-2020
- 2018-2019
- 2017-2018
- 2016-2017
- 2015-2016
- 2014-2015
- 2013-2014
- 2012-2013
- 2011-2012
- 2010-2011
- 2009-2010
2020-2021
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$42,930.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$36,491.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2019-2020
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$714.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$607.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2018-2019
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
06 Reclassify the Site Using CCME National Classification SystemTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$15,955.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$13,562.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2017-2018
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$10,207.38Total Remediation Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$8,165.90FCSAP Remediation Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2016-2017
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2015-2016
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2014-2015
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2013-2014
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2012-2013
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2011-2012
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$0.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$0.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2010-2011
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
09 Confirmatory Sampling and Final ReportingTotal Assessment Expenditure
$26,383.00Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$26,383.00FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
2009-2010
Reporting Organization
National Capital CommissionInternal Identifier
786Highest Step Completed
01 Identify Suspect SitesTotal Assessment Expenditure
$6,211.80Total Remediation Expenditure
$0.00Total Care Maintenance Expenditure
$0.00Total Monitoring Expenditure
$0.00FCSAP Assessment Expenditure
$6,211.80FCSAP Remediation Expenditure
$0.00FCSAP Care Maintenance Expenditure
$0.00FCSAP Monitoring Expenditure
$0.00Actual Cubic Meters Remediated
0 m3Actual Hectares Remediated
0 haActual Tons Remediated
0 tClosed
No
- Version:
- 38