Site 56488004 - Waste Disposal Midden (East and West)

  • Status

    Confirmatory sampling completed. Long term monitoring underway.
  • Site Status

    Active
  • Classification

    High Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    Federal Real Property
  • Property Type

    Federal (DFRP Property Number 56498)

Site Location

Locate this site on map
  • Latitude, Longitude

    50.424044, -114.24714
  • Municipality

    Foothills County, AB
  • Federal Electoral District

    Foothills

Site Management Strategy

  • Containment
  • Remediation
  • Continous Monitoring

Contaminant Details

Contamination Estimate

  • Cubic Meters

    5,700

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PAHs (polycyclic aromatic hydrocarbon) Groundwater
PAHs (polycyclic aromatic hydrocarbon) Soil
Metal, metalloid, and organometallic Soil

Action Plan

Site is under remediation and/or risk management steps.

Additional Information

The site is located in a Federal real property or in a Federal Program Lands.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km1
5 km73
10 km306
25 km3,047
50 km71,602

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $45,500.00
  • Remediation

    $561,443.76
  • Monitoring

    $269,375.70

FCSAP Expenditures

  • Assessment

    $32,320.00
  • Remediation

    $487,956.47
  • Monitoring

    $234,543.71

Financial/Annual Information

2022-2023

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $45,278.48
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $37,835.48
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2021-2022

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $104,353.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $97,537.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $24,207.43
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $13,408.43
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2019-2020

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $178,105.25
  • Total Monitoring Expenditure

    $178,105.25
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $167,913.25
  • FCSAP Monitoring Expenditure

    $167,913.25
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2018-2019

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $8,671.12
  • Total Monitoring Expenditure

    $8,671.12
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $8,671.12
  • FCSAP Monitoring Expenditure

    $8,671.12
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2017-2018

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $40,693.46
  • Total Monitoring Expenditure

    $40,693.46
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $32,330.47
  • FCSAP Monitoring Expenditure

    $32,330.47
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2016-2017

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $47,945.50
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $47,945.50
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2015-2016

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $41,905.87
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $41,905.87
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $25,628.87
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $25,628.87
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2014-2015

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $10,964.65
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $9,231.15
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2013-2014

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2012-2013

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2011-2012

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWHBURT001
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2010-2011

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    710
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    710
  • Highest Step Completed

    08 Implement Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2008-2009

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    710
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $59,319.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $47,455.20
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    710
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $2,500.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $2,000.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    710
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $43,000.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $30,320.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2005-2006

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    710
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No