Site 17432001 - RP-1 Rocky Point CFAD Active Propellant Burn Area

  • Status

    Detailed testing completed. Remedial action plan under development.
  • Site Status

    Active
  • Classification

    Low Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    Federal Real Property
  • Property Type

    Federal (DFRP Property Number 17432)

Site Location

Locate this site on map
  • Latitude, Longitude

    48.3164, -123.559
  • Municipality

    Metchosin, BC
  • Federal Electoral District

    Esquimalt--Saanich--Sooke

Site Management Strategy

  • Periodic Monitoring
  • Additional assessment

Contaminant Details

Contamination Estimate

  • Cubic Meters

    50

The following contaminated media was identified on the site:

Contaminant Type Medium Type
Metal, metalloid, and organometallic Groundwater
Metal, metalloid, and organometallic Soil
Energetics Groundwater
Energetics Soil

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km67
5 km1,275
10 km7,829
25 km336,234
50 km469,944

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $29,558.97
  • Remediation

    $3,332.60
  • Monitoring

    $1,000.00

Financial/Annual Information

2022-2023

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2021-2022

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2020-2021

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $2,236.30
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2019-2020

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2018-2019

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2017-2018

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2016-2017

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2015-2016

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2014-2015

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2013-2014

  • Reporting Organization

    National Defence
  • Internal Identifier

    0359-C001
  • Highest Step Completed

    06 Classify the site using the CCME National Classification System
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2012-2013

  • Reporting Organization

    National Defence
  • Internal Identifier

    S-258
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2011-2012

  • Reporting Organization

    National Defence
  • Internal Identifier

    S-258
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $27,322.67
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2010-2011

  • Reporting Organization

    National Defence
  • Internal Identifier

    S258
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $1,000.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    National Defence
  • Internal Identifier

    S258
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2008-2009

  • Reporting Organization

    National Defence
  • Internal Identifier

    S258
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $3,332.60
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    National Defence
  • Internal Identifier

    S258
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    National Defence
  • Internal Identifier

    S258
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2005-2006

  • Reporting Organization

    National Defence
  • Internal Identifier

    S258
  • Highest Step Completed

    05 Detailed Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No