Site 16103001 - McKay Creek Compound

  • Status

    Initial testing completed. No further action required.
  • Site Status

    Closed
  • Classification

    Low Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    Federal Real Property
  • Property Type

    Federal (DFRP Property Number 16103)

Site Location

Locate this site on map
  • Latitude, Longitude

    50.641872, -116.01253
  • Municipality

    East Kootenay G, BC
  • Federal Electoral District

    Kootenay--Columbia

Contaminant Details

Contamination Estimate

The following contaminated media was identified on the site:

Contaminant Type Medium Type
Metal, metalloid, and organometallic Not Available

Action Plan

Site is under asssessment steps.

Additional Information

The site is located in a National Park of Canada.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km0
5 km287
10 km1,054
25 km7,277
50 km8,953

Financial/Annual Information

2013-2014

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWPKOOT001
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2012-2013

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWPKOOT001
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2011-2012

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AWPKOOT001
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2010-2011

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    342
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2009-2010

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    342
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2008-2009

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    342
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2007-2008

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    342
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2006-2007

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    342
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2005-2006

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    342
  • Highest Step Completed

    04 Pre-Classify contaminated site using the CCME National Classification System (optional)
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No