Site 00024292 - Sandy Pond Day-Use Area

  • Status

    Confirmatory sampling completed. No further action required.
  • Site Status

    Closed
  • Classification

    Medium Priority for Action

Site Details

  • Reporting Organization

  • Reason for Involvement

    National Park of Canada
  • Property Type

    Canada Lands

Site Location

Locate this site on map
  • Latitude, Longitude

    48.493347, -54.018103
  • Municipality

    Division No. 7, Subd. D, NL
  • Federal Electoral District

    Bonavista--Burin--Trinity

Site Management Strategy

  • Remediation
  • Additional assessment
  • Assessment

Contaminant Details

Contamination Estimate

  • Cubic Meters

    800

The following contaminated media was identified on the site:

Contaminant Type Medium Type
PAHs (polycyclic aromatic hydrocarbon) Groundwater
PAHs (polycyclic aromatic hydrocarbon) Soil
Other organics Groundwater
Other organics Soil

Action Plan

Site closed. No futher action is required.

Additional Information

The site is located in a National Park of Canada.

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km0
5 km7
10 km458
25 km9,665
50 km27,703

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $20,846.00
  • Remediation

    $177,885.00
  • Monitoring

    $30,739.00

FCSAP Expenditures

  • Remediation

    $36,000.00

Financial/Annual Information

2013-2014

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AEPTERT003
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2012-2013

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AEPTERT003
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2011-2012

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    AEPTERT003
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2010-2011

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    832
  • Highest Step Completed

    09 Confirmatory Sampling and Final Reporting
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $36,000.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $30,739.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $36,000.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2009-2010

  • Reporting Organization

    Parks Canada Agency
  • Internal Identifier

    832
  • Highest Step Completed

    08 Implement Remediation/Risk Management Strategy
  • Total Assessment Expenditure

    $20,846.00
  • Total Remediation Expenditure

    $141,885.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No