Site 00023997 - Ridge Road

  • Status

    Initial testing completed. No further action required.
  • Site Status

    Closed
  • Classification

Site Details

Site Location

Locate this site on map
  • Latitude, Longitude

    45.394594, -75.561275
  • Municipality

    Ottawa, ON
  • Federal Electoral District

    Orléans

Site Management Strategy

  • Additional assessment

Contaminant Details

Contamination Estimate

The following contaminated media may exist on the site:

Contaminant Type Medium Type
PAHs (polycyclic aromatic hydrocarbon) Soil
Metal, metalloid, and organometallic Groundwater
Metal, metalloid, and organometallic Soil

Population

This table contains the population estimates at distances around the site.

Radius Population
1 km27
5 km29,259
10 km304,718
25 km1,129,604
50 km1,423,445

Summary of Annually Reported Data

Total Expenditures

  • Assessment

    $24,926.03

FCSAP Expenditures

  • Assessment

    $19,940.62

Financial/Annual Information

2018-2019

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    98346
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $888.58
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $710.86
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    Yes

2017-2018

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    98346
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $0.00
  • Total Remediation Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $0.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2016-2017

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    98346
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $6,410.45
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $5,128.36
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2015-2016

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    98346
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $2,648.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $2,118.40
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No

2014-2015

  • Reporting Organization

    National Capital Commission
  • Internal Identifier

    98346
  • Highest Step Completed

    03 Initial Testing Program
  • Total Assessment Expenditure

    $14,979.00
  • Total Remediation Expenditure

    $0.00
  • Total Care Maintenance Expenditure

    $0.00
  • Total Monitoring Expenditure

    $0.00
  • FCSAP Assessment Expenditure

    $11,983.00
  • FCSAP Remediation Expenditure

    $0.00
  • FCSAP Care Maintenance Expenditure

    $0.00
  • FCSAP Monitoring Expenditure

    $0.00
  • Actual Cubic Meters Remediated

    0 m3
  • Actual Hectares Remediated

    0 ha
  • Actual Tons Remediated

    0 t
  • Closed

    No