This page has been archived.
Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.
It is government policy that all IM/IT and capital projects, with a total estimated cost above the level that the sponsoring Minister of the department concerned can approve, must be approved by Treasury Board (the committee of government ministers set up to review and approve expenditures). This applies even though the project may be funded from the department's authorized budget. Approval is sought by the preparation of a Treasury Board Submission, which is thoroughly reviewed by officials in the Treasury Board Secretariat before being submitted to Treasury Board Ministers.
All projects submitted for approval must be supported by documentation that adequately describes the full scope of the project including the associated management framework. All submissions relating to IM/IT are reviewed by the Portfolio Management Division (PMD) of the CIO Branch, in a business-team setting to ensure that they represent an effective and efficient solution to the operational needs as set out in the department's defined priorities or in the Long-term Capital Plan. PMD also reviews for compliance with the EMF to help departments and agencies meet their projected budget and scheduled time lines.
The approval process normally consists of two stages: Preliminary Project Approval (PPA) and Effective Project approval (EPA). Departments normally request PPA when the initial project planning and identification phase is completed but before the project definition phase starts. The formal Treasury Board approval process may be tailored to individual projects and departments, depending on the nature of the risks involved in those projects.
The requirements for PPA are as follows:
Proposal: It must list all authorities being sought from the Treasury Board, including:
Supporting documentation: consisting of the following:
Under certain circumstances, PPA may be deemed unnecessary. This is acceptable so long as all the conditions required for PPA are met within the EPA submission.
The EPA submission must include the above PPA requirements, and in addition:
After receiving Project Approval, departments have reporting obligations to the Treasury Board Secretariat. These follow the "gating" concept. Gates are significant completion events or quality milestones, placed at key points in the project lifecycle. Gates assess either the quality of the products produced so far, or the adequacy and completeness of the process to date, and a gate can only be "passed" if the products or process meet a predefined performance standard. Gates may take the form of technical reviews, risk assessments, completion of documents, demonstrations or test cases, or project audits. Gates are identified in a project's plan/schedule, and a gate review is required to formally "pass" each gate.
If, at a gate review, the gate's criteria have not been met, it is possible that a significant change in project direction may need to take place to address the lack of performance. The project should not continue "as is" unless each gate is passed.
Once projects are completed, audits are normally carried out by departmental review branches, which report directly to senior management. On a government-wide basis, projects of significant scope and/or cost may be reviewed by the Auditor-General of Canada. Large and/or long-term projects may be subject to audits while still in progress.