Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Table 3: Details on Project Spending


Capital Projects by Program Activity ($ Million)
Program Activity Current Estimated
Total Cost
Actual
2006-07
Actual
2007-08
2008-09
Main
Estimates
Planned
Spending
Total
Authorities
Actual
 Custody
A. New Accommodation Projects              
Archambault New CRSM & Redevelopment 33 0.1 0.7 0.1 0.1 0.1 0.1
Saskatchewan Pen 96-Bed Maximum Unit 21.8 6.3 11.2 2.1 2.1 2.1 3.1
Kent 96-Bed Maximum Unit 21.8 0.6 10.8 9.7 10 9.7 9.4
               
B. Major Asset Preservation              
Springhill Institution Refurbish/Replace 35.2 9.2 0.7 2.8 2.6 2.8 2.6
Collins Bay Refurbish/Replace 54.3 19.1 3 0.3 0.3 0.3 0.2
Cowansville Refurbish/Replace 49.5 4.2 0.9 0.5 0.2 0.5 0.1
               
Total Capital Spending   39.5 27.3 15.5 15.3 15.5 15.5

Notes:
(1) CSC’s delegation authority level is $18 million according to TB decision of December 14, 1995;
                therefore, only capital projects with total estimated cost of $18 million or above have been listed.

Internal Notes:
Current Total Estimated Cost is the latest formally-approved Project Total Estimated Cost.
Actual 2006-2007 is a repetition from the DGF submission for previous fiscal years.
Actual 2007-2008 is a repetition from the DGF submission for previous fiscal years.
2008-09 Main Estimates is the amount presented by DGF in the NCAOP for FY 2008-09.
2008-09 Total Planned Spending is the DGF internal Forecast Cash Requirement at the beginning of FY 2008-09.
2008-09 Total Authority is a repetition of the content of the “Main Estimates” column unless a formal change of approval has been received such as through Supplementary Estimates (note 1).
2008-09 Actual is the official CSC-Finance value for total FY 2008-09 expenditures on each project.