Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Status Report on Major Crown Projects

Parliamentary Precinct Project - Long Term Vision and Plan

1. Description

In 2007, Public Works and Government Services Canada (PWGSC) updated the Long-Term Vision and Plan (LTVP) for the Parliamentary Precinct. This update was undertaken in conjunction with the parliamentary partners - the Senate, the House of Commons and the Library of Parliament. The LTVP established a comprehensive approach for rehabilitating the heritage buildings, providing additional parliamentary accommodations and creating a secure and welcoming environment for parliamentarians, staff, visitors and tourists. It confirmed the long-term vision and guiding principles for the Precinct and the extensive set of planning and design principles created to guide future development. A major component of the LTVP Update was the creation of a new implementation framework designed to improve results and enhance accountability. This framework establishes short-term objectives in the context of the long-term vision and provides a strategy for getting projects underway and completed in an efficient and timely manner. The implementation strategy is composed of a broad strategic direction and a series of rolling five-year programs. The strategic direction establishes the renovation of the core historic parliamentary buildings - the West Block, Centre Block and East Block - as the first priority. Since Centre Block cannot be renovated while occupied, the East and West Blocks will be renovated first. This will be done not only to accommodate the interim uses from Centre Block, but also to address the pressing restoration work that is required on these two buildings. This work initiates a series of projects to create interim accommodation for those functions displaced from the East and West Blocks and, in a cascading fashion, triggers further projects required to house those displaced from buildings renovated for interim Parliamentary uses.

The rolling five-year programs establish short-term cycles for the approval of specific projects to implement the strategic direction. These shorter cycles provide greater flexibility in responding to government and parliamentary priorities, building conditions and current market conditions, and allowing for better accuracy in determining functional requirements and establishing project costs and scheduling. Each five-year program is composed of three components:

The Major Capital Program, which includes primary projects necessary to advance the overall objective of restoring the key heritage buildings;

The Recapitalization Program, which includes a series of urgent building interventions (related mostly to exterior masonry repairs), required to ensure the ongoing viability of buildings and address health and safety issues. These projects will be part of the full restoration work that will ultimately be done on these buildings and by undertaking them early will ensure that future projects are less complicated and costly; and

The Planning Program, which includes the development of more refined plans and reliable cost estimates for projects in the next five-year program.

2. Project Phase

Accordingly, the first five-year program includes projects for each of the three components. The core focus of the Major Capital Program is the stabilization and renovation of the West Block. Other projects will provide appropriate interim space to sustain the operations of Parliament while the West Block is being renovated, and will create interim and permanent facilities that meet the operational needs of Parliament and allow future phases of the LTVP to proceed in a cost-efficient manner. Specific projects will be undertaken in La Promenade Building, the Wellington Building, the former Bank of Montreal Building, and in several office buildings in downtown Ottawa.

The Recapitalization Program focuses on the core historic buildings and their physical state, and includes a series of projects for East Block, Centre Block and Confederation Building. These projects will ensure that the key buildings are consistently restored, as required; addressing problems that cannot wait until the major renovation projects can begin. The primary focus of these projects will be the long term restoration of discrete components of the buildings to extend their life.

The Planning Program will focus on preparing for the renovations of East Block. The intent is to ensure that West Block and East Block renovations are completed simultaneously so that work on the Centre Block can ultimately proceed without delay. The Planning Program will also include feasibility studies for future Centre Block renovations, and several master plans (including: underground infrastructure, west sector master plan, landscape master plan update, materiel handling and transportation, and Blocks 1,2,3).

Funding for individual projects within this five-year program will follow the normal approval process for government expenditures and will be approved by Treasury Board on a project-by-project basis.

3. Lead and Participating Departments

  1. Lead Department or Agency: Public Works and Government Services Canada.
  2. Contracting Authority: Public Works and Government Services Canada.
  3. Participating Departments and Agencies: Senate of Canada, House of Commons, Library of Parliament.

4. Prime Contractor and Major Sub-Contractors

See separate notes for each specific project.

5. Major Milestones

See separate notes for each specific project.

6. Progress Report and Explanation of Variances

See separate notes for each specific project.

7. Industrial Benefits

See separate notes for each specific project.

Parliamentary Precinct Project - Wellington Building

1. Description

The Wellington Building is located at 180 Wellington Street, across from Parliament Hill. It is a six-storey structure first built in 1925 and later enlarged in the 1950's by Metropolitan Life Insurance Company. The House of Commons has been the major tenant since the Crown expropriated the building in 1973. Renovations of the building are required to address health and safety issues, replace obsolete building systems and meet building code requirements. The building will be completely vacated during the renovations. The Wellington Building is part of the Long Term Vision and Plan and will be used for Parliamentary accommodations.

2. Project Phase

The work will be completed in two phases to expedite project delivery. Phase 1 will include interior demolition, asbestos abatement and seismic reinforcement work. Phase 2, dependent on additional funding, will include the restoration of the exterior envelope, renovation of the base building and fit-up the interior space. The entire renovation is targeted to be completed in 2015 (depending on additional funding). The current total cost estimate is $425.2 million(current dollars, excluding GST). Separate project approval has been received for alternatespace at 181 Queen Street and 131 Queen Street.

3. Lead and Participating Departments


Lead Department Public Works and Government Services Canada
Contracting Authority Public Works and Government Services Canada
Participating Departments Senate of Canada, House of Commons, Library of Parliament

4. Prime Contractor and Major Sub-Contractors


Prime Contractor
(Architectural, Mechanical and Electrical)
Design consultant for the Wellington renovation project is
NORR Architects and Engineers Ltd., 175 Bloor Street East, Toronto, Ontario, M4W 3R8
Major Subcontractor(s)

Adjeleian Allen Rubeli (Structural)
75 Albert Street Suite 1005
Ottawa ON K1P 5E7

Fournier Gersovitz Moss and Associates (Heritage)
1435 rue St. Alexandre #1000
Montreal QC H3A 2G4

5. Major Milestones


Major Milestone Date
Preliminary Functional Program Completed July 2007
Revised Preliminary Project Approval and Phase 1 Effective Project Approval March 2008
Consultant Contract Award August 2008
Final Functional Program October 2009
Final Schematic Design Report October 2009
Phase 1 Construction Start April 2010
Phase 2 Effective Project Approval 2012*
Phase 1 Construction Completion 2012
Phase 2 Construction Start 2012*
Phase 2 Construction Completion 2015

*Subject to additional funding

6. Progress Report and Explanation of Variances

The Relocation Program is underway to completely empty the Wellington Building, whereby fourteen House of Commons operational units are being transferred to alternative locations in Crown-owned and leased facilities prior to start of construction in April 2010. Some relocations are temporary, pending completion of the renovation, while others are permanent. Alternative locations include 131 Queen, 155 Queen, 2086 Walkley Road, Confederation Building and 2455 Don Reid Drive in Ottawa and 45 Sacré Coeur in Gatineau.

7. Industrial Benefits

Several multi-million dollar contracts will be awarded over a seven-year period for building construction, information technology systems, multimedia systems, furniture and other equipment. An estimated 1,500 private sector jobs will be generated by this project.

Parliamentary Precinct Project - West Block

1. Description

The West Block, located within the Parliamentary Precinct, is the oldest of the parliamentary buildings located on the "Hill". It is a three-storey building that was built in three phases starting in 1859 and completed in 1906. The West Block provides accommodation for Members of Parliament (MPs) and for parliamentary functions and support services.

2. Project Phase

Renovations of the building are required to address health and safety and asset integrity conditions. In order to implement the renovations, the building has to be completely vacated, thus requiring the provision of alternate accommodations for the MPs, parliamentary functions such as committee rooms and support services. Consequently, the program of work will be undertaken in two phases.

Phase 1 involves:

  1. Emergency stabilization and rehabilitation of towers;

  2. Repairs and conservation of the exterior masonry;

  3. Fit-up of alternate accommodations in the La Promenade building and other locations for MPs, committee rooms and support services; and

  4. The permanent relocation of the food production facility for Parliament Hill to a remote site.

Phase 2 involves*:

  1. Fit-up of space for the relocation of Confederation Room 200 to the former Bank of Montreal building;

  2. Asbestos abatement, interior demolition, and general rehabilitation of the West Block building; and

  3. Associated infrastructure to support legislative functions during the renovation of the Centre Block, including a courtyard infill to accommodate Chamber activities, and provision of a security screening and material handling facility.

*Subject to additional funding

The current schedule calls for MPs and support staff to vacate the West Block in 2010, with construction to start on specific areas of West Block shortly thereafter. Overall completion is scheduled for 2020.

Current Treasury Board Preliminary Project Approval is $769.2 million, excluding GST.

3. Lead and Participating Departments


Lead Department Public Works and Government Services Canada
Contracting Authority Public Works and Government Services Canada
Participating Departments Senate of Canada, House of Commons, Library of Parliament

4. Prime Contractor and Major Sub-Contractors


Prime Contractor
Design consultant for the West Block renovation and fit-up project is ARCOP/FGM, architects in joint venture, 1244 Ste-Catherine Ouest, 3rd floor, Montreal PQ, H3G 1P1
Prime Contractor
Design consultant for the La Promenade fit-up project is KWC Architects Inc. 110 Argyle Avenue, Ottawa, Ontario K2P 1B4
Prime Contractor

General contractor for the La Promenade fit-up project is Pomerleau Inc., 220-343 Preston St. Ottawa, Ontario,K1S 1N4

Prime Contractor
General contractor for the North Towers stabilization and rehabilitation project is L'Unique General Insurance inc., 425, blvd. de Maisonneuve Ouest, suite 750, Montréal (Québec) H3A 3G5 with Verrault, 1080 cote du Beaver Hall, Suite 800, Montreal, Quebec, H2Z 1S8
Prime Contractor
General contractor for construction of the Food Production Facility for Parliament Hill is PCL Construction Ltd, 49 Auriga Drive, Nepean, Ontario, K2E 8A1
Prime Contractor
Design consultant for the Bank of Montreal rehabilitation project is NORR Architects and Engineers Ltd., 175 Bloor Street East, Toronto, Ontario, M4W 3R8

5. Major Milestones


Major Milestone Date
Revised Preliminary Project Approval June 2005
Partial Effective Project Approval (Phase 1) June 2005
$17.2 million Spending Authority Approved for the development of preliminary design to EPA for West Block, Bank of Montreal, Wellington Committee rooms and project management support services for the program December 2006
Effective Project Approval (Phase 1) February 2007
MPs, parliamentary functions and support services vacate West Block 2010
Effective Project Approval 2010*
Major Construction Start 2010*
Major Construction Completion 2020*
La Promenade swing space completion 2010
Bank of Montreal 2014*
Food Production Facility 2010

*Subject to additional funding

6. Progress Report and Explanation of Variances

The West Block Program of work consists of sub-projects involving emergency stabilization of towers and masonry, several interim space projects, major renovations of the building and construction of a courtyard infill.

Stabilization:

The work presently underway is required in order to ensure the most at risk areas of the building envelope are stabilized. The work includes:

  • South East Tower masonry pilot project - completed.

  • North Towers - construction started.

  • Tower scaffolding - contract documents for the MacKenzie and Laurier Towers, completed. Work will be done in Phase 2 as part of the overall building envelope program, unless building condition demands an earlier start date*.

  • Masonry Wall Investigation and Research Project - conducted with the Intelligent Sensing for Innovative Structures (ISIS) Canada and three Canadian universities. This initiative is nearing completion. The objective is to gain and share leading edge knowledge on seismic reinforcing methodologies for heritage masonry walls. PWGSC constructed masonry wall sections, similar to those used in our Parliament buildings, in the University of Calgary seismic laboratories, in order to simulate seismic events and assess the reaction of various reinforcement methodologies.

*Subject to additional funding

Relocation Projects:

  • La Promenade swing space (temporary accommodation) - scope of the project consists of restoring the building and fitting up 62 MP suites and 3 committee rooms for parliamentarians. The demolition and building envelope remediation (Phase I) contract has been completed. The construction contract for the fit up package was awarded and construction has begun. As part of the design process, a mock up suite was constructed, tested successfully and approved by the House of Commons.

  • Bank of Montreal Building, located at 144 Wellington Street - has been identified as the permanent alternate location for West Block's Confederation Room 200 functions. A major RFP was posted on MERX and a prime consultant contract for the main design work was awarded to Norr Architects and Engineers, 200 Tremblay Road, suite 152, Ottawa. Completion is scheduled for 2014*.

  • Food Production Facility - will be permanently relocated off-site. Solicitation for a design build contractor was awarded to PCL Construction Ltd, 49 Auriga Drive, Nepean, Ontario, K2E 8A1 (Ottawa). Completed Fall 2009.

*Subject to additional funding

7. Industrial Benefits

Several multi-million dollar contracts will be awarded over a ten-year period for building construction, information technology systems, multimedia systems, furniture and other equipment. An estimated 3,500 private sector jobs will be generated by this program of work.

Pension Modernization Project

1. Description

The Government of Canada Pension Modernization Project (GCPMP) has been initiated to renew PWGSC's pension administration systems and business processes in order to ensure the sustainability of the pension administration and improve services to employees, employers and pensioners. The current pension administration processes and system infrastructure are nearly 40 years old. They depend on outdated technology that is expensive to maintain, limits the Government's ability to provide modern services such as web-based self-service, and relies on inefficient and error prone manual processes. The GCPMP will replace existing systems with commercial off-the-shelf software products, streamline business processes, and introduce broader, more flexible service delivery methods. Although the project is focused on the Public Service Superannuation Act administration, the project will implement a multi-plan solution that will provide for other pension plans within the public service.

2. Project Phase

The GCPMP began its Implementation Phase in July 2007, following receipt of Effective Project Approval from the Treasury Board. The GCPMP Implementation Phase will take approximately four and a half years to complete.

3. Lead and Participating Departments


Lead Department Public Works and Government Services Canada
Contracting Authority Public Works and Government Services Canada
Participating Departments Public Works and Government Services Canada

4. Prime Contractor and Major Sub-Contractors

Prime Contractor EDS Canada Inc.
50 O'Connor St., 6th Floor, Ottawa, Ontario K1P 6B9
Major Subcontractor(s)

James Evans & Associates (JEA)
4th floor, 844 Courtney St., Victoria, British Columbia
V8W 1C4

Vangent Canada Limited
169 Colonnade Road, Nepean, Ontario
K2E 7J4

5. Major Milestones

This subsection lists the major milestones associated with the progress of the Major Crown Project (MCP).

Major Milestone Date
Preliminary Project Approval for completion of Project Definition Completed May 2004
Approval of contract award Completed October 2005
Contract Award Completed November 2005
Completion of Project Definition Completed June 2007
Effective Project Approval for Implementation Completed June 2007
Implementation Phase
Implementation of Release 1.0
(Client Services)
Completed February 2009
Implementation of Release 1.5
(Case Management functions)
Revised to December 2009
Implementation of Release 1.6 (decoupled from R.1.5) (Imaging functions) January 2010
Implementation of Release 2.0
(Contributor functions and functions related to Pension Benefits Division Act - except functions related to Service Purchase and Leave Without Pay)
Revised to June 2010
Implementation of Release 2.5 (Contributor functions related to Service Purchase and Leave Without Pay) Revised to November 2010
Implementation of Release 3.0
(Annuitant and Accounting functions)
October 2011
Final maintenance transition January 2012
Close-Out Phase January 2012

6. Progress Report and Explanation of Variances

Project Definition Phase (completed June 2007):

  • At Preliminary Project Approval, the Treasury Board approved the completion of the Project Definition Phase and funding in the amount of $18,742 million (excluding GST). The GCPMP completed this phase at a cost of $18,335 million, although there was a delay of approximately six months in obtaining Effective Project Approval.

Implementation Phase (in progress):

  • At Effective Project Approval, in June 2007, the Treasury Board approved implementation of the GCPMP and funding in the amount of $184,750 million. The amount budgeted from June 2007 to September 30, 2008, was $67,310,380. Actual expenditures for implementation activities from June 2007 to September 30, 2008, are $39,179,955. The cost variance resulted from lower-than-estimated costs for Human Resources, operations, maintenance and the delay in the Release 1.0.

  • Release 1.0 was completed six weeks behind schedule for the Siebel components and three months behind schedule for the telephony components. This represents an 8% schedule variance on 85% of the release's scope (Siebel components) and a 10% variance for the telephony components (remaining 15% of Release 1.0 scope).

  • The GCPMP is currently involved in activities related to Releases 1.5, 2.0 and 2.5. Release 1.5 is three months behind schedule for the Siebel components as a result of the three-month delay in Release 1.0. The imaging component will be further delayed due to technical problems encountered during readiness testing. At the release level, this represents a 20% variance on the Siebel scope and a 27% variance on the imaging scope. Release 2.0 is also three months behind schedule due to the three-month delay in Release 1.0. As well, the start of Release 2.5 was deferred by four months to minimize the impacts of the delays of previous releases. However, at the project level perspective, these delays are not expected to impact the overall project implementation, which is still expected to be completed in early 2012.

7. Industrial Benefits

A multi-million dollar contract has been awarded for the COTS products, as well as for the professional services to implement the new systems, and for support services and ongoing maintenance. The implementation will be conducted in several phases over a four-and-a-half-year period (2007-2011). During that time it is expected that there will be some temporary positions required to support the system implementation and business transformation activities. In the long term, the project will provide the infrastructure and processes essential to the sustainability of current pension administration operations, and of positions in Shediac, New Brunswick.

Transformation of Pay Administration Initiative – Pay Modernization Project

1. Description

PWGSC received preliminary project approval in July 2009 for the Transformation of Pay Administration Initiative which is made up of two projects; Pay Modernization and Pay Consolidation. The goal of this initiative is to transform the systems and processes by increasing flexibility and web self-service for managers and employees and improving efficiency in service delivery; thereby generating significant government-wide operational savings. Of these two projects that make up this initiative the Pay Modernization Project has been identified by Treasury Board (TB) as being a Major Crown Project.

The Pay Modernization Project involves the renewal of PWGSC's compensation administration services, systems and business processes. The Pay Modernization Project will replace PWGSC's 40-year-old technology and business processes with a commercial-off-the-shelf pay solution in order to ensure PWGSC's continuing ability to fulfill its mandate and to provide modern, "industry standard" services to public service employees.

2. Project Phase

Project Definition Phase (post preliminary project approval)

3. Lead and Participating Departments and Agencies


Lead Department Public Works and Government Services Canada
Contracting Authority Public Works and Government Services Canada
Participating Departments

This project will be delivered by PWGSC ABC branch in partnership with ITSB.

Although there are no participating departments in the project delivery, there are primary stakeholders as follows:

  1. Treasury Board of Canada Secretariat: TBS, as the employer for the core public administration, according to the Financial Administration Act (FAA) Schedule I and IV, sets compensation policies and negotiates collective agreements with unions representing employees of those organizations.

  2. Separate Agencies: These organizations, named in Schedule V of the FAA, negotiate collective agreements, set compensation policy for their employees, and have primary responsibility to ensure that their employees receive accurate and timely pay and benefits.

  3. Crown Corporations and Other Federal Entities: As the employer, these organizations, named under Schedules II and III of the FAA, or are not listed under a specific FAA schedule, negotiate collective agreements and set compensation policy for their employees.

  4. Departments, Agencies and other Organizations: These organizations have primary responsibility to ensure that their employees receive accurate and timely pay and benefits.

4. Prime Contractor and Major Sub-Contractors


Prime Contractor

There is no Prime Contractor currently on board.

The current schedule identifies that the procurement activities for acquiring the Prime Contractor are planned for completion by the end of January 2011.

Major Subcontractor(s)

There is currently a standing offer with PriceWaterhouseCoopers for the provision of Advisory Services for the duration of the project.

The current schedule identifies that the procurement activities for acquiring the firm for the Project Management Office (PMO) are planned for completion by the end February 2010 and the procurement activities for acquiring the Prime Contractor are planned for completion by the end of January 2011.

5. Major Milestones


List of Major Milestones Date

Definition Phase

  • Request for Information for Commercial Off-the-Shelf/Solution Integrator (ongoing - closes October, 2009)

  • Request for Proposal for Project Management Services (ongoing - closes October, 2009)

  • Request for Proposal and Contract Award for Commercial Off-the-Shelf/Solution Integrator

  • Fit-Gap

  • Business Model (Processes)

  • Technical Architecture

  • Design

  • Confirm schedule and costs

October 2009 to April 2012

Implementation Phase

  • Configuration

  • Testing

  • Training

  • Implementation

May 2012 to July 2015

6. Progress Report and Explanation of Variances


  • Initially, on July 30, 2009, the Treasury Board approved the “Initiative to Fix the Pay System” (Transformation of Pay Administration) which included the Pay Modernization Project with an estimated cost of $192,067,332 (including GST).

  • The Pay Modernization Project start date was October 1, 2009.

  • The Pay Modernization Project is currently in its definition phase and is on schedule and on budget.

  • Activities on schedule include:

    • Request for Proposal (Project Management Office)

    • Request For Information (System Integrator, commercial off-the-shelf products (COTS))

    • Request For Proposal Development (Bid Posting; Bid Evaluation; Vendor Selection; and, Contract Approval)

7. Industrial Benefits


The following table outlines the expected outcomes as a result of implementing the initiative, as indicated in the Performance Measurement Framework:
Outcome Type Outcome
Strategic Outcome GC is employer of choice
Increased Contribution to PS Renewal/MAF
Increased stakeholder confidence in Payroll Administration function
Supports Recommendations of OGGO Report
Greening Government Operations
Final Outcome Increased Pay Administration Sustainability
Increased GC Operational Savings
Measured Outcome Increased employee satisfaction
Decreased time to train pay administration staff
Decreased cost to deliver pay administration
Decreased materiel usage (e.g. paper, mail)
Decreased work effort for Compensation Advisors

The region of delivery for the Pay Modernization Project is the National Capital Area.