Information identified as archived on the Web is for reference, research or recordkeeping purposes. It has not been altered or updated after the date of archiving. Web pages that are archived on the Web are not subject to the Government of Canada Web Standards. As per the Communications Policy of the Government of Canada, you can request alternate formats on the "Contact Us" page.

Status Report on Projects Operating with Specific Treasury Board Approval1


Project Original Estimated
Total Cost
($K)
Revised Estimated
Total Cost
($K)
Actual
Cost Total
($K)
2010-11 ($K)2 Expected Date of
Close-Out
Main
Estimates
Planned
Spending
Total
Authorities
Actual
Refugee Protection
Replacement of STAR Phase I 7,037 6,529 4,814 3,337 3,337 3,337 3,284 2011
Replacement of STAR Phase II 4,202 5,713 1,095 1,112 1,112 1,112 1,095 2012

1 All taxes excluded.

2 No additional funding sought during 2010-11. Only sought the authority for expenditures within existing reference levels.